- Asked 3/22
- 2073 Shrawan · 4 marks
Rate analysis: 12 mm plaster 1:3 ceiling
Short answer
For 10 m² of 12 mm ceiling plaster (1:3), dry mortar 0.1524 m³ requires 1.097 bags cement and 0.1143 m³ sand. Direct cost NPR 5,027.05; with 15% overhead and 10% profit, total rate = NPR 6,283.82 per 10 m² (628.38/m²).
Prepare an analysis of rate for 12 mm thick cement plaster (1:3) in ceiling per 10 m².
Rates and labour norms below are illustrative (DUDBC-style norms; use the current District Rate and norms of the project area for a real estimate): cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled labour NPR 1,500/day, unskilled labour NPR 1,100/day, water lump sum, contractor's overhead 15% and profit 10% on direct cost (VAT excluded).
Quantities per 10 m²
- Wet mortar m³; dry m³
- Cement m³ bags; sand m³
- Labour for ceiling (overhead work, about 25% more than wall plaster): mason 1.2 days, labourer 1.3 days; plus staging.
Analysis
| Item | Qty | Unit | Rate (NPR) | Amount (NPR) |
|---|---|---|---|---|
| Cement | 1.097 | bag | 1,000.00 | 1,097.00 |
| Sand | 0.1143 | m³ | 3,500.00 | 400.05 |
| Skilled labour (mason) | 1.20 | day | 1,500.00 | 1,800.00 |
| Unskilled labour | 1.30 | day | 1,100.00 | 1,430.00 |
| Staging, water and curing (lump) | 1 | LS | 300.00 | 300.00 |
| Direct cost | 5,027.05 | |||
| Contractor's overhead @ 15% | 754.06 | |||
| Contractor's profit @ 10% | 502.71 | |||
| Total (rate per 10 m²) | 6,283.82 |
Rate = NPR 6,283.82 per 10 m² (NPR 628.38 per m²).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 20 mm plaster 1:4 per 100 m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4
- Materials: 12 mm plaster 1:6 per 10 m² · Estimating and Costing, chapter 4
- Rate analysis: M20 (1:1½:3) RCC per 10 m³ · Estimating and Costing, chapter 4
- Rate analysis: 25 mm 1:2:4 concrete floor · Estimating and Costing, chapter 4
- Rate analysis: 40 mm asphalt wearing coat · Estimating and Costing, chapter 4
- Rate analysis: 40 mm PCC 1:2:4 floor · Estimating and Costing, chapter 4