- 2072 Magh · 4 marks
Construction of cement floor
Short answer
Cement concrete floor: hardcore base, 1:2:4 concrete (75-100 mm), 12-25 mm cement-sand (1:2) topping applied while green, trowelled smooth with neat cement, cured 7-10 days.
Explain method of construction of cement floor.
A cement concrete floor is made of cement concrete finished with a cement-sand topping. It is cheap, strong, durable and fire-resistant, and is used in houses, godowns, schools and offices.
Method of construction
- Preparation: the ground is cleaned, levelled and compacted. A layer of 100-150 mm hardcore (brick soling) is laid and rammed. On damp sites, a damp proof membrane is added.
- Base concrete: cement concrete 1:2:4 (or 1:3:6 for light use), 75-100 mm thick, is laid in panels of about 2 m x 2 m, using wooden or steel strips as screed guides. It is tamped and levelled.
- Topping: while the concrete is still green (within 2-3 hours), a 12-25 mm topping of cement-sand mortar 1:2 is applied.
- Finishing: the surface is levelled with a straight edge and trowelled. Neat cement is then sprinkled on it and finished with a steel trowel (punning) to get a smooth surface. The dividing strips can be removed and the joints filled.
- Curing: the floor is covered with wet sand or gunny bags and kept wet for 7-10 days.
topping 1:2 (12-25 mm) ~~~~~~~~~~
PCC 1:2:4 (75-100 mm) ..........
hardcore (150 mm) oooooooooo
compacted earth //////////
The floor can be coloured by adding oxide pigments, and a hardener (such as iron filings) is added for heavy-duty floors.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Floor insulation and sound insulation methods · Building Technology, chapter 1
- Suspended ground floor; tile flooring · Building Technology, chapter 7
- Soil stabilization methods; soil cement construction · Transportation Engineering II, chapter 3
- Construction steps of cement concrete pavement · Transportation Engineering II, chapter 3
- Materials: 115 m² PCC floor, 110 m² plaster · Estimating and Costing, chapter 4 · asked 2×
- Rate analysis: 25 mm 1:2:4 concrete floor · Estimating and Costing, chapter 4