Soil stabilization methods; soil cement construction

Short answer

Stabilization methods include mechanical, cement, lime, bituminous, lime-flyash, chemical, and thermal. Soil-cement road construction: pulverise soil, spread cement (4-8%), mix dry, add water to OMC, compact within 2 hours to 98% density, cure 7 days, then apply surface.

List out different soil stabilization methods. Write down construction procedure of soil cement stabilized road including details of equipment and material requirement.

Methods of soil stabilisation

Soil stabilisation is improving the engineering properties of a soil (strength, volume stability, durability, resistance to water) so that it can be used in a road layer. Methods and where each is used:

MethodPrincipleApplicable to
Mechanical (granular, blending)Mix two or more soils to get a good gradation and compactGravel and sand-clay mixes for base and sub-base on low volume roads
Cement stabilisationCement hydrates and binds the grainsSandy and gravelly soils, low plasticity (PI below 20); base and sub-base
Lime stabilisationCation exchange and pozzolanic reaction reduce plasticity and give strengthClayey soils (PI above 10), black cotton soils and sub-grade
Bituminous stabilisationBitumen coats and waterproofs particlesSands, gravels and low plastic soils; desert/sandy areas
Lime-flyash / lime-pozzolanaPozzolanic actionSoils with moderate clay plus fly ash; base and sub-base
Chemical (calcium chloride, sodium chloride, polymers, enzymes)Reduces dust and moisture changeGravel roads, dust control
Thermal (heat, freezing) and geotextile reinforcementDry or reinforce the soilSpecial areas, soft grounds

Construction of soil cement stabilised road

Soil-cement (cement-stabilised) base is a mix of soil, cement and water, compacted to give a strong, durable layer (IRC:SP:89, IS:4332).

Materials: granular or sandy soil (PI below 20, fines below 50 percent, maximum size 40 mm; clay and organic soil unsuitable); ordinary Portland cement 4-8 percent by dry weight (decided by laboratory trial: 7-day UCS 1.7-3 MPa); clean water.

Equipment: pulveriser (rotavator) or grader, cement spreader (or bags), water tanker, rollers (vibratory 8-10 t, pneumatic tyre), motor grader, curing sprayer.

Construction procedure

  1. Prepare the subgrade, trim and compact; set line and levels.
  2. Spread the soil in a uniform layer and pulverise to break clods.
  3. Spread the cement in a uniform layer at the specified rate (by bags at fixed spacing or by mechanical spreader).
  4. Mix dry cement and soil with rotavator or grader until colour is uniform; add water to the optimum moisture content and mix again.
  5. Compact immediately (within 2 hours of adding water) to 98 percent of modified Proctor density, using a vibratory roller and then a pneumatic roller; shape with the grader.
  6. Cure for 7 days with moist cover or a bituminous prime coat (bitumen emulsion) to retain moisture; keep traffic off.
  7. Provide the bituminous surface or the next layer after curing.
  8. Control: cement content (titration), moisture and density, UCS cubes, thickness and level.