Soil stabilization methods and lime stabilized road

Short answer

Methods: mechanical blending, cement (PI<20), lime (PI>10), bituminous, lime-flyash, chemical, thermal/reinforcement. Lime stabilization uses 3–8% lime mixed with pulverized clayey soil (PI>10); after moistening and optional mellowing, it is compacted to 95–98% MDD and cured for 7 days. UCS of 0.7–1.0 MPa at 7 days is required.

List out the various methods of soil stabilization used in highway construction. When each of the method of stabilization is applicable? Discuss the material, and construction procedure of lime stabilized road.

Methods of soil stabilisation and where they apply

Soil stabilisation is improving the engineering properties of a soil (strength, volume stability, durability, resistance to water) so that it can be used in a road layer. Methods and where each is used:

MethodPrincipleApplicable to
Mechanical (granular, blending)Mix two or more soils to get a good gradation and compactGravel and sand-clay mixes for base and sub-base on low volume roads
Cement stabilisationCement hydrates and binds the grainsSandy and gravelly soils, low plasticity (PI below 20); base and sub-base
Lime stabilisationCation exchange and pozzolanic reaction reduce plasticity and give strengthClayey soils (PI above 10), black cotton soils and sub-grade
Bituminous stabilisationBitumen coats and waterproofs particlesSands, gravels and low plastic soils; desert/sandy areas
Lime-flyash / lime-pozzolanaPozzolanic actionSoils with moderate clay plus fly ash; base and sub-base
Chemical (calcium chloride, sodium chloride, polymers, enzymes)Reduces dust and moisture changeGravel roads, dust control
Thermal (heat, freezing) and geotextile reinforcementDry or reinforce the soilSpecial areas, soft grounds

Lime stabilised road

Materials: soil (clay or silty clay, PI above 10); lime (quicklime or hydrated lime) at 3 to 8 percent by dry weight of soil, of high purity (available CaO content as specified, usually not less than 50-70 percent; IS:712, IRC:SP:89); water.

Equipment: grader/pulveriser (rotavator), lime spreader, water tanker, sheep-foot and smooth-wheel/pneumatic rollers, cutting tools.

Construction procedure

  1. Prepare the subgrade or soil layer: clear, grade and trim it to line and level.
  2. Pulverise the soil (all clods below 25 mm) with a rotavator or grader.
  3. Spread the lime uniformly at the required percentage (by lorry spreader or from bags).
  4. Mix the lime with the soil by rotavator or grader and add water to reach the optimum moisture content. For heavy clays, leave the mix after this first mixing to mellow for 24 to 48 hours.
  5. Remix and compact, first with a sheep-foot roller and then with a smooth-wheel or pneumatic tyre roller, to 95-98 percent of maximum dry density.
  6. Cure by keeping the layer moist for 7 days (or cover with sand or bitumen emulsion), and protect the surface from rain and traffic; lay the surface course after curing.
  7. Quality control: lime content, degree of pulverisation, moisture content, density and unconfined compressive strength (UCS of about 0.7-1.0 MPa at 7 days).