Rate analysis: PCC 1:3:6 per m³

Short answer

Use dry volume 1.54 m3 per m3 with ratio sum 10; cement 4.435 bags, sand 0.462 m3, aggregate 0.924 m3, plus assumed labour and lump water. Add 15% overhead and 10% profit to direct cost 18,360 NPR, giving rate 22,950 NPR per m3.

Prepare an analysis of rate for P.C.C. (1:3:6) per m³.

Rates and labour norms below are illustrative (DUDBC-style); use the current District Rate for a real estimate. Cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled NPR 1,500/day, unskilled NPR 1,100/day, overhead 15%, profit 10%.

Quantities per m³ of PCC (1:3:6)

  • Dry volume =1.54= 1.54 m³; sum of ratio =10= 10
  • Cement =1/10×1.54=0.1540= 1/10\times1.54 = 0.1540 m³ =4.435= 4.435 bags
  • Sand =3/10×1.54=0.4620= 3/10\times1.54 = 0.4620 m³; aggregate =6/10×1.54=0.9240= 6/10\times1.54 = 0.9240 m³
  • Labour: 1.0 skilled and 6.0 unskilled days per m³ (assumed norm).

Analysis

ItemQtyUnitRate (NPR)Amount (NPR)
Cement4.435bag1,000.004,435.00
Sand0.4620m³3,500.001,617.00
Coarse aggregate0.9240m³4,500.004,158.00
Skilled labour1.000day1,500.001,500.00
Unskilled labour6.000day1,100.006,600.00
Water and curing (lump)1LS50.0050.00
Direct cost18,360.00
Contractor's overhead @ 15%2,754.00
Contractor's profit @ 10%1,836.00
Total (rate per m³)22,950.00

Rate of PCC (1:3:6) = NPR 22,950.00 per m³.