- Asked 2/32
- 2078 Chaitra · 4 marks
- 2069 Bhadra · 4 marks
Preparing cement mortar by manual process
Explain step by step procedure for preparing cement mortar by manual process (preparation of cement sand mortar 1:6).
Manual mixing of cement mortar is done for small works, when a mixer is not available. For a 1:6 cement-sand mortar (1 part cement to 6 parts sand by volume), the steps are as follows.
Materials and tools
Cement (OPC 43 grade), clean river sand (passing a 4.75 mm sieve, free from silt and organic matter), clean water; a watertight platform (masonry or steel sheet, 3 m × 3 m), shovels, trowels, a gauge box, buckets.
Procedure
- Measure the sand: Measure the volume of sand with a gauge box (e.g. 6 boxes for 1 bag of cement; 1 bag of 50 kg = 0.035 m³).
- Spread the sand: Spread the sand in a uniform layer, 150 to 200 mm thick, on a clean, hard platform.
- Add cement: Spread the cement evenly over the sand.
- Dry mixing: Mix the sand and cement with shovels, turning the heap over at least 3 times, until the mix has a uniform colour.
- Making a crater: Form the dry mix into a ring with a hollow at the centre.
- Adding water: Add water slowly into the centre, without letting it escape, using just enough to get a workable consistency (too much water weakens the mortar).
- Wet mixing: Turn and re-mix 3 to 4 times with a shovel until the mortar is uniform and has the correct consistency.
- Use: Use the mortar within 30 minutes of adding water (before the initial set). Hardened mortar must not be re-tempered; unused mortar is discarded.
- Cleaning: Clean the platform and tools after use.
- Curing: Cure the finished work for at least 7 days.
1. sand layer 2. + cement 3. dry mix
~~~~~~~~~~~~~ =========== (turn x3)
4. crater -> add water -> turn x3-4 -> mortar
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Mortar properties; cement and sand for 10 cum · Building Technology, chapter 3
- Cement-sand plastering and its types · Building Technology, chapter 9 · asked 3×
- Cement and sand for 100 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Cement and sand for 200 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Mortar for 10 m³ brickwork (1:4) numerical · Building Technology, chapter 3
- First class brickwork in 1:6 mortar numerical · Building Technology, chapter 3
- Stepwise preparation of cement mortar · Civil Engineering Materials, chapter 6 · asked 4×
- Detailed specification of cement sand mortar 1:4 · Construction Management, chapter 12 · asked 2×
- Detailed specification of cement sand mortar 1:6 · Construction Management, chapter 12 · asked 2×
- Precautions while applying cement mortar · Civil Engineering Materials, chapter 6 · asked 3×