Materials: 150 m³ brick 1:4, 120 m² plaster

Short answer

For 150 m3 brickwork in 1:4 mortar, assuming 230x110x55 mm bricks with 10 mm joints and dry volume 1.27 times wet: bricks 80,129, cement 281.6 bags, sand 39.12 m3. For 120 m2 20 mm plaster: cement 17.6 bags, sand 2.44 m3. Totals: cement 299.2 bags, sand 41.56 m3.

Calculate the quantities of materials required for the following works: i) 150 m³ of brick work in (1:4) cement mortar in super structure ii) 120 m² of 20 mm thick cement sand plaster (1:4).

Assumptions: dry volume 1.27 × wet for mortar; 1 m³ cement = 28.8 bags; brick 230 × 110 × 55 mm with 10 mm joints (not given); no wastage.

(i) 150 m³ of brickwork in 1:4 mortar

  • Brick with mortar =0.240×0.120×0.065=1872.0×10−6= 0.240 \times 0.120 \times 0.065 = 1872.0\times 10^{-6} m³; bricks per m³ =1/(1872.0×10−6)=534.19= 1/(1872.0\times10^{-6}) = 534.19
  • Bricks for 150.00 m³ =534.19×150.00=80,128= 534.19 \times 150.00 = 80,128 nos (say 80,129)
  • Volume of bricks only =0.230×0.110×0.055=1391.5×10−6= 0.230\times0.110\times0.055 = 1391.5\times10^{-6} m³ each; wet mortar per m³ =1−534.19×1391.5×10−6=0.2567= 1 - 534.19\times1391.5\times10^{-6} = 0.2567 m³
  • Wet mortar for 150.00 m³ =38.502= 38.502 m³; dry =1.27×38.502=48.897= 1.27\times38.502 = 48.897 m³
  • Cement =1/5×48.897=9.779= 1/5\times48.897 = 9.779 m³ =281.6= 281.6 bags
  • Sand =4/5×48.897=39.118= 4/5\times48.897 = 39.118 m³

(ii) 120 m² of 20 mm plaster (1:4)

  • Wet mortar =120.0×0.0200=2.4000= 120.0 \times 0.0200 = 2.4000 m³; dry volume =1.27×2.4000=3.0480= 1.27 \times 2.4000 = 3.0480 m³
  • Cement =1/5×3.0480=0.6096= 1/5 \times 3.0480 = 0.6096 m³ =17.56= 17.56 bags
  • Sand =4/5×3.0480=2.4384= 4/5 \times 3.0480 = 2.4384 m³

Answer: (i) bricks 80,129, cement 281.6 bags, sand 39.12 m³. (ii) cement 17.6 bags, sand 2.44 m³. Total cement = 299.2 bags; total sand = 41.56 m³.

✓ Answer checked by Claude Opus 5.5 (high effort)