Materials: 105 m³ PCC 1:4:8, 725 m² plaster
Short answer
i) 105 m³ PCC (1:4:8) with dry factor 1.54: cement 358.2 bags, sand 49.75 m³, aggregate 99.51 m³. ii) 725 m² of 20 mm plaster (1:4) with dry factor 1.27: cement 106.1 bags, sand 14.73 m³.
Calculate the quantities of materials required for the following items of work: i) 105 m³ of PCC (1:4:8) in foundation ii) 725 m² of 20 mm thick cement plaster (1:4) in wall.
Assumptions: dry volume = 1.54 × wet volume for concrete and 1.27 × wet volume for mortar; 1 m³ of cement = 28.8 bags of 50 kg; no wastage is added.
(i) 105 m³ PCC (1:4:8) in foundation
- Wet volume m³; dry volume m³ (sum of ratio )
- Cement m³ bags (50 kg)
- Sand m³
- Coarse aggregate m³
(ii) 725 m² of 20 mm plaster (1:4)
- Wet mortar m³; dry volume m³
- Cement m³ bags
- Sand m³
Answer: (i) cement 358.2 bags, sand 49.75 m³, aggregate 99.51 m³. (ii) cement 106.1 bags, sand 14.73 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Materials: 115 m² PCC floor, 110 m² plaster · Estimating and Costing, chapter 4 · asked 2×
- Materials: 100 m² plaster 1:6, 100 m³ PCC 1:2:4 · Estimating and Costing, chapter 4
- Materials: 75 m³ brick 1:3, 115 m² PCC floor · Estimating and Costing, chapter 4
- Materials: 150 m³ brick 1:4, 120 m² plaster · Estimating and Costing, chapter 4
- Materials: 12 mm plaster 1:6 per 10 m² · Estimating and Costing, chapter 4
- Rate analysis: 20 mm plaster 1:4 per 100 m² · Estimating and Costing, chapter 4 · asked 3×
- Well foundation: excavation, sinking, brick, PCC curb · Estimating and Costing, chapter 6 · asked 2×
- Masonry work, materials for 20 cum brickwork · Building Technology, chapter 3