- 2078 Chaitra · 2+2+4 marks
Three reservoirs with two parallel pipes
Short answer
(i) Q₃/Q₄ = √(r₄/r₃) = 1.438, so Q₃ = 1.438 Q₄. (ii) Hydraulic grade line at junction D is 108.95 m. (iii) Pipe flows: Q₁=1.942, Q₂=0.073 (to B), Q₃=1.102, Q₄=0.766, Q₅=1.868 m³/s.
Three reservoirs are connected as shown below, with the connecting pipes having the following properties (length, diameter, friction factor and minor losses) as shown below:
| Pipe | L (m) | D (mm) | f | |
|---|---|---|---|---|
| 1 | 280 | 500 | 0.021 | 3.5 |
| 2 | 980 | 300 | 0.022 | 0.0 |
| 3 | 270 | 550 | 0.017 | 0.0 |
| 4 | 700 | 650 | 0.028 | 3.5 |
| 5 | 780 | 750 | 0.030 | 1.5 |
The corresponding reservoir elevation are: = 185 m, = 105 m and = 70 m. [Figure: reservoir A connected by pipe 1 to junction D; reservoir B connected to D by pipe 2; pipes 3 and 4 run in parallel from D, then pipe 5 leads to reservoir C]. Calculate: (i) The relationship between the flow rates in the two parallel pipes that form part of the system. (ii) The value of the Hydraulic Grade Line (HGL) at junction D, and (iii) The flow rates in all five pipes for this value.
Layout assumed from the figure. A feeds junction D by pipe 1; B joins D by pipe 2; from D two pipes, 3 and 4, run in parallel to a junction E; pipe 5 then runs from E to reservoir C. Minor losses are included through : for each pipe the head loss is , with
| Pipe | r (s²/m⁵) | ||
|---|---|---|---|
| 1 | 11.76 | 3.5 | 20.174 |
| 2 | 71.87 | 0 | 733.10 |
| 3 | 8.345 | 0 | 7.536 |
| 4 | 30.15 | 3.5 | 15.578 |
| 5 | 31.20 | 1.5 | 8.539 |
(i) Relation between the flows in the two parallel pipes
They have the same head loss, so :
The equivalent resistance of the pair is given by , so s²/m⁵, and .
(ii) HGL at junction D
Let be the HGL at D. Pipe 5 is in series with the parallel pair (3, 4), so .
- Pipe 1: (A to D)
- Pipe 2: , towards B if , from B if
- Pipe 5:
- Continuity at D: (when B is receiving), or (when B is supplying).
Trials ( means B supplies D, means B receives):
| (m) | ||||
|---|---|---|---|---|
| 100 | 2.053 | +0.083 | 1.640 | +0.496 |
| 105 | 1.991 | +0.000 | 1.771 | +0.220 |
| 108 | 1.954 | -0.064 | 1.845 | +0.044 |
| 110 | 1.928 | -0.083 | 1.893 | -0.048 |
The sum changes sign between 108 and 110 m, and the balance is at
Since m, pipe 2 carries water to reservoir B.
(iii) Flow rates
| Pipe | Q (m³/s) | Direction |
|---|---|---|
| 1 | 1.942 | A to D |
| 2 | 0.073 | D to B |
| 3 | 1.102 | D to E |
| 4 | 0.766 | D to E |
| 5 | 1.868 | E to C |
Pipe 5: m³/s. The HGL at junction E is m, so and m³/s.
Continuity check at D: .
Answer: (i) ; (ii) HGL at D m; (iii) , (to B), , , m³/s.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Three reservoirs with 250 mm concrete pipes · Hydraulics, chapter 3 · asked 2×
- Three reservoirs: pipe AEC length and level B · Hydraulics, chapter 3
- Three reservoirs with pump in pipe 2 · Hydraulics, chapter 3
- Manometer reading in pipe with minor losses · Hydraulics, chapter 2
- Siphon with 90 mm pipe, number and length · Hydraulics, chapter 2
- Series-parallel pipes with control valve · Hydraulics, chapter 2 · asked 2×
- Friction pile length, 300 mm, 250 kN · Foundation Engineering, chapter 8
- Series and parallel pipe network · Fluid Mechanics, chapter 8
- Flow between reservoirs (15 cm and 25 cm pipe) · Hydro Power, chapter 1
- Friction pile length, 350 mm, 1200 kN · Foundation Engineering, chapter 8