- Practice · 8 marks
Wheatstone bridge for strain gauges
Short answer
For four active arms, Vo = Vex/4(dR1/R - dR2/R + dR3/R - dR4/R), or Vex G/4(eps1 - eps2 + eps3 - eps4). Quarter bridge uses one active gauge, half bridge two, full bridge four; adjacent arms subtract and opposite arms add, giving temperature compensation.
Derive the output of a Wheatstone bridge with all four arms active. Hence explain the quarter-bridge, half-bridge and full-bridge arrangements for strain measurement and how temperature compensation is obtained.
A Wheatstone bridge converts the small resistance changes of strain gauges into a measurable voltage.
Bridge output
Four arms (between A and B), (B-C), (C-D), (D-A). The excitation is applied across A and C, and the output is measured between B and D.
A
/ \
R1 R4
/ \
B D output V_o between B and D
\ /
R2 R3
\ /
C (V_ex across A and C)
The bridge is balanced () when .
Let each arm be initially and change by . For small changes:
With :
Adjacent arms subtract and opposite arms add, which is the basis of compensation.
Arrangements
| Bridge | Active gauges | Output | Remarks |
|---|---|---|---|
| Quarter | 1 | Dummy gauge in adjacent arm for temperature compensation | |
| Half | 2 (one tension, one compression) | Bending beam; compensates temperature and axial load | |
| Full | 4 (two tension, two compression) | Highest output, best compensation |
Temperature compensation
Temperature changes the resistance of all gauges equally (the same ). Because adjacent arms subtract, this common change cancels. In a quarter bridge a dummy gauge (same type, same temperature, mounted on unstrained material) is placed in the adjacent arm. In half and full bridges the active gauges act as each other's compensators. Strain from bending or axial load can similarly be separated by placing gauges in the correct arms (e.g. on top and bottom of a beam).
Comments
- Output of a quarter bridge is slightly nonlinear for large ; half and full bridges are more linear.
- A three-wire connection compensates the lead resistance.
- Balancing and calibration (shunt calibration) are done before use.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Shaft torque measurement using strain gauges · Instrumentation and Measurement, chapter 7
- Gauge resistance change and quarter-bridge output · Instrumentation and Measurement, chapter 6
- Full-bridge cantilever load cell output · Instrumentation and Measurement, chapter 6
- Elastic transducers and strain gauge load cells · Instrumentation and Measurement, chapter 7
- Bonded and unbonded gauges, selection, installation · Instrumentation and Measurement, chapter 6
- Full bridge inverter; dc-dc output power control · Advanced Electronics, chapter 7
- Polarization; quarter and half wave plates · Engineering Physics, chapter 4
- Half-controlled bridge with R load, α = 45° · Power Electronics, chapter 2
- Half-bridge square-wave inverter at 120 Hz · Power Electronics, chapter 5