- 2076 Bhadra · 8 marks
5-disc string at 66 kV, ratios 5 and 6
Short answer
For m=0.2 (C=5C1), string efficiency is 54.16%. When distance increases so C=6C1 (m=1/6), efficiency rises to 57.47%. Reducing shunt earth capacitance improves voltage distribution uniformity.
Each conductor at 66 kV is suspended by a string of 5 similar insulators, the capacitance of each disc being 5 times the capacitance to earth. Determine the % string efficiency. If the distance between the insulators and tower structure is increased so as to make the capacitance of the disc 6 times the earth capacitance, what will happen to the string efficiency?
With no guard ring, the voltage across the discs increases towards the line, because each link pin leaks charging current to the tower through its shunt capacitance .
Data
Phase voltage:
Number the discs 1 (tower end) to 5 (line end). At each junction, the current through the lower disc equals the current through the upper disc plus the current to earth:
Case 1: , so
, so kV.
| Disc | kV () | kV () |
|---|---|---|
| 1 | 3.847 | 4.255 |
| 2 | 4.616 | 4.965 |
| 3 | 6.309 | 6.501 |
| 4 | 9.263 | 9.122 |
| 5 (line end) | 14.070 | 13.262 |
Case 2: , so
, so kV and kV.
Answer: The string efficiency is 54.16 % when . Moving the insulators further from the tower lowers the shunt capacitance so that . The efficiency then rises to 57.47 %, and the line-end disc voltage falls from 14.07 kV to 13.26 kV. A lower ratio always gives a more uniform distribution.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- String of 4 insulators at 66 kV, ratio 10 · Power System Analysis I, chapter 2
- 5-disc string at 66 kV: nearest and farthest disc · Power System Analysis I, chapter 2
- String efficiency: 66 kV, 4 discs, 10% · Power System Analysis I, chapter 2 · asked 2×
- Maximum voltage of 3-disc string, 17.5 kV per unit · Power System Analysis I, chapter 2
- String of 5 insulators on 100 kV, ratio 0.1 · Power System Analysis I, chapter 2
- Voltage distribution on 4-disc string at 33 kV · Power System Analysis I, chapter 2
- True length of suspended distance AB (66) · Surveying I, chapter 2
- 400 kV lines: configuration, V-string, earth wires · Transmission and Distribution System Design, chapter 4
- Guard ring capacitances for 5-disc string · High Voltage Engineering, chapter 5
- Design: 250 m head plant, 66 kV double circuit · Power Plant Design, chapter 4 · asked 13×