- 2078 Baisakh · 5 marks
Clay 4 m, 90% in 4 hours, time in years
Short answer
Using time scaling with drainage path squared, field time = lab time × (4000/10)^2 = 640,000 hours, about 73 years. Single drainage in field, double in lab.
There is a bed of compressible clay of 4 m thickness with pervious sand on top and impervious rock at the bottom. In a consolidation test on an undisturbed specimen of clay from this deposit, 90% settlement was reached in 4 hours. The specimen was 20 mm thick. Estimate the time in years for the building founded over this deposit to reach 90% of its final settlement.
Principle: the same soil has the same and, for the same , the same . So
Drainage paths
- Field: sand on top, impervious rock at the bottom, so single drainage: m mm.
- Laboratory: the 20 mm specimen in an oedometer drains at top and bottom, so mm.
Time
Answer: about 73 years for the building to reach 90% of its final settlement.
If the specimen were drained at one face only, the answer would be about 18 years.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Consolidation test, 90% time, k, Cc · Soil Mechanics, chapter 9
- Clay 10 m, 2.54 cm sample, half settlement · Soil Mechanics, chapter 9
- Time-settlement curve, 3 m clay · Soil Mechanics, chapter 9
- Primary settlement, sand over clay, 110 kPa · Soil Mechanics, chapter 9
- 5 m clay, Cc 0.25, 50% consolidation · Soil Mechanics, chapter 9 · asked 2×
- 5 m clay, Cc 0.25, 65% consolidation · Soil Mechanics, chapter 9 · asked 2×
- Differential settlement allowed, clay vs sand · Foundation Engineering, chapter 6
- Tensile test numerical, 40 mm specimen · Civil Engineering Materials, chapter 1
- Thickness of d/s impervious floor of a fall · Irrigation and Drainage Engineering, chapter 7
- Sand deposit reserve in tons · Engineering Geology II, chapter 7