Time-settlement curve, 3 m clay
Short answer
Final settlement is 25 cm. From t=60 days at U=20%, cv = 47.1 cm²/day. At 3 years (1095 days) the time factor is 0.573, giving U≈80% and settlement ≈20 cm. The curve rises steeply at first and asymptotically approaches 25 cm.
A structure built on a 3 m thick single drained clay layer settled 5 cm in 60 days after it was built. If this settlement corresponds to 20 percent average consolidation of the clay layer, plot the time settlement curve of the structure for a period of 3 years from the time it was built.
Given: single-drained layer, m cm. Settlement 5 cm at days corresponds to .
Step 1: Final settlement
Step 2: Coefficient of consolidation. For , .
Step 3: Time for various . days. Use for and for . Settlement cm.
| (%) | Time (days) | Settlement (cm) | |
|---|---|---|---|
| 10 | 0.008 | 15 | 2.5 |
| 20 | 0.031 | 60 | 5.0 |
| 30 | 0.071 | 135 | 7.5 |
| 40 | 0.126 | 240 | 10.0 |
| 50 | 0.196 | 375 | 12.5 |
| 60 | 0.286 | 547 | 15.0 |
| 70 | 0.403 | 769 | 17.5 |
| 80 | 0.567 | 1083 | 20.0 |
| 90 | 0.848 | 1620 | 22.5 |
Step 4: Settlement at 3 years ( days):
Plot: draw time (days, 0 to 1095) on the horizontal axis and settlement (cm) downward on the vertical axis; join the points above with a smooth curve. The curve is steep at first and flattens towards 25 cm.
t (days) 0 200 400 600 800 1000 1095
S (cm) 0
| *
5 | *
10 | *
15 | *
20 | * * <- 3 yr
25 - - - - - - - - - - - - - - (final)
Answer: the structure settles about 20 cm in 3 years; the curve approaches the final value of 25 cm.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Clay 4 m, 90% in 4 hours, time in years · Soil Mechanics, chapter 9
- Clay 10 m, 2.54 cm sample, half settlement · Soil Mechanics, chapter 9
- 5 m clay, Cc 0.25, 65% consolidation · Soil Mechanics, chapter 9 · asked 2×
- 3 m clay, cv 0.025 cm²/min, times · Soil Mechanics, chapter 9
- Settlement 4 cm in 2 months, time for 10 cm · Soil Mechanics, chapter 9
- 5 m clay, Cc 0.25, 50% consolidation · Soil Mechanics, chapter 9 · asked 2×
- Percent strength gain at 14 days · Concrete Technology and Masonry Structure, chapter 4
- Crest, average and schedule speed; speed-time curve · Utilization of Electrical Energy, chapter 4
- Average demand, village survey 2013, design 25 years · Water Supply Engineering, chapter 3 · asked 2×
- Demand of rural municipality, base period 3 years · Water Supply Engineering, chapter 3