- 2078 Poush · 4 marks
Sheet pile seepage quantity numerical
Short answer
For sheet pile with k=4×10⁻⁴ m/s, H=3 m, penetration ratio 0.7, flow net gives Nf=3, Nd=8. Seepage q = kH(Nf/Nd) = 4.5×10⁻⁴ m³/s per m (≈39 m³/day per m).
A deposit of cohesionless soil with a permeability of cm/s has a depth of 10 m with an impervious ledge below. A sheet pile wall is driven into this deposit to a depth of 7 m. The wall extends above the surface of the soil and a 3 m depth of water acts on one side. Sketch the flow net and determine the seepage quantity per metre length of the wall.
Given
cm/s m/s. Permeable layer depth m, sheet pile penetration m (so ), net head m.
Flow net
H=3m ▽ |P|
~~~~~~~~~~~~~|P|~~~~~~ (downstream ground)
ground |P| 7 m
3 flow channels, 8 equipotential drops
______________|__|________
======== impervious, 10 m deep ========
Draw the flow net with the pile tip 3 m above the impervious layer. Sketching it gives about
- flow channels
- equipotential drops
Seepage quantity
A check with the exact solution for a single sheet pile of penetration ratio gives , i.e. m³/s per m, so the flow net values agree.
Answer: m³/s per metre length ( m³/day per m).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Impervious dam seepage discharge · Soil Mechanics, chapter 7
- Earth dam with filter, seepage quantity · Soil Mechanics, chapter 7
- Infinite slope, cohesionless, steady seepage · Soil Mechanics, chapter 11
- Flow net under sheet pile, discharge · Soil Mechanics, chapter 7
- Sheet pile flow net; graded filter · Soil Mechanics, chapter 7
- Average permeability of layered soil · Soil Mechanics, chapter 6
- Cantilever sheet pile, simplified method · Foundation Engineering, chapter 5
- Cantilever sheet pile, 5 m excavation · Foundation Engineering, chapter 5
- Anchor reduces cantilever sheet pile depth · Foundation Engineering, chapter 5
- Cantilever sheet pile, 8 m excavation · Foundation Engineering, chapter 5