Monthly progress report: Bagmati Bridge
Short answer
A memo reports May 2027 work on the Bagmati Bridge. South abutment piles and pile cap finished, 6 of 24 girders cast, and Rs. 4.1 crore spent. Overall progress is 20 percent against a 22 percent plan, delayed by rain and river conditions.
Write a monthly progress report to be submitted to the Chief Engineer, Department of Roads on the construction of a Bagmati Bridge near Thapathali.
MEMORANDUM
To : Er. Hari Prasad Lamsal, Chief Engineer,
Department of Roads, Babarmahal, Kathmandu
From : Er. Ashim Pradhan, Project Manager, Bagmati
Bridge Project
Date : 3 June 2027
Subject : Monthly progress report on the construction of
the Bagmati Bridge near Thapathali (May 2027)
Introduction
The project is to construct a 90 m, double-lane RCC bridge across the Bagmati river near Thapathali, to reduce traffic on the existing bridge. The contract period is 15 months from 1 March 2027. This report covers the work done in the third month (May 2027).
Work completed
- Piers and abutments: the pile foundation of the south abutment and Pier 1 was finished (24 piles); piles for Pier 2 are 50 percent done.
- Pile cap: casting of the south abutment pile cap was completed.
- Girders: casting yard established; 6 of 24 precast girders were cast.
- Materials: cement, rods and aggregates were tested and found satisfactory.
- Safety and environment: river water was diverted using a temporary channel; the working area was fenced.
- Traffic: a diversion plan was made with the Traffic Police.
- Expenditure: Rs. 1.8 crore this month, Rs. 4.1 crore so far.
| Item | Plan (%) | Actual (%) |
|---|---|---|
| Pile foundation | 65 | 60 |
| Substructure | 20 | 15 |
| Girder casting | 25 | 25 |
| Overall | 22 | 20 |
Problems faced
- Pre-monsoon rain raised the river level and slowed the pile work for 6 days.
- Pollution and waste in the river made working conditions difficult.
- The 11 kV line near the north abutment has to be shifted by the electricity authority.
Work planned for the next period
- Complete the piles of Pier 2 and the north abutment.
- Cast 8 more girders.
- Request the Nepal Electricity Authority to shift the line.
- Prepare a monsoon safety plan.
Conclusion
The overall progress is 20 percent against the plan of 22 percent. The delays can be made up in the dry season, but the monsoon safety plan must be strictly followed.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- First monthly progress report: lab construction (memo) · Communication English, chapter 7
- First monthly progress report in memo format · Communication English, chapter 7 · asked 2×
- First monthly progress report: internet connectivity (memo) · Communication English, chapter 7 · asked 2×
- Third monthly progress report: micro-hydro, Dhading (memo) · Communication English, chapter 7
- Monthly progress report on micro-hydro project · Communication English, chapter 7 · asked 3×
- Progress report: view tower construction · Communication English, chapter 7
- Design and construction problems of hill roads · Transportation Engineering I, chapter 5 · asked 11×
- BOD of Bagmati sample at 30°C · Sanitary Engineering, chapter 5
- Building near river bank; stop construction? · Engineering Professional Practice, chapter 7