- 2073 Shrawan · 8 marks
Gumbel exceedance probability and 0.1 flood
Short answer
P(X>15000) =1 - exp[-e^{-α(15000-β)}] with α=1.28255/3000, β=10000-0.48×3000, giving 0.0617. Dischrge with exceedance probability 0.1: Q_0.1 = β - (1/α)ln(-ln0.9) = 13824 m³/s.
The annual peak discharge of a river follows the Gumbel's extreme value distribution with a mean of 10000 m/s and a standard deviation of 3000 m/s. What is the probability that the annual peak discharge is more than 15000 m/s? What is the magnitude of the peak discharge with an exceedance probability of 0.1? [Hint: ; ]
Gumbel's cumulative distribution (probability of non-exceedance):
Using the hint:
Probability that the annual peak exceeds 15000 m³/s
Answer: probability ≈ 0.0617 (about 6.17%), a return period of ≈ 16.2 years.
Discharge with exceedance probability 0.1
Exceedance 0.1 means :
Answer: ≈ 13824 m³/s (the 10-year flood).
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Gumbel peak flood and confidence limits, 75 years · Engineering Hydrology, chapter 6
- Gumbel 30-year flood, Lothar River 1989-2009 · Engineering Hydrology, chapter 6
- Flood statistics and exceedance probability, 2000-2009 · Engineering Hydrology, chapter 6
- Gumbel 500-year flood and 80% limits, Kamalamai River · Engineering Hydrology, chapter 6
- Gumbel design flood, safety factor, confidence limits · Engineering Hydrology, chapter 6
- Gumbel 500-year flood, 95% limits, 30 years · Engineering Hydrology, chapter 6
- Standard costing variances, 3000 vs 2500 units · Engineering Economics, chapter 1
- First-order kinematic wave, flood peak at community · Computational Techniques in Civil Engineering, chapter 5
- T/F: radial more reliable than network · Transmission and Distribution System Design, chapter 5 · asked 2×
- T/F: more circuits rather than higher voltage · Transmission and Distribution System Design, chapter 2