Steps to develop the rating curve of a hydrological station:

  1. Select the gauging site with a stable control, a straight reach and easy access.
  2. Install the gauge (staff or automatic recorder) and fix its datum with a benchmark.
  3. Measure discharge at the section by the area-velocity method (current meter) at different stages from low flow to flood, and record the stage at the time of each measurement.
  4. Tabulate stage (GG) and discharge (QQ) pairs, covering the whole range of stages (about 15 to 20 pairs).
  5. Plot GG against QQ on arithmetic paper and draw a smooth curve.
  6. Find the stage for zero discharge aa by the three-point method or trial and error.
  7. Plot log⁡Q\log Q against log⁡(G−a)\log(G-a); fit a straight line (least squares) to get bb and CC in Q=C(G−a)bQ=C(G-a)^b, and find the correlation coefficient.
  8. Extend the curve to high floods by extrapolation, and check it using the slope-area method for floods.
  9. Verify and update the curve with new measurements; correct for shifts in the control.