- 2066 Magh (old course) · 8 marks
Short note: Setting out vertical curve
Short answer
Vertical curves are parabolic arcs (summit or sag). Length L from permissible grade change rate or sight distance. BVC at IP−L/2, EVC at IP+L/2; their RLs computed from IP. Curve RL at x from BVC: RL_BVC + (g1/100)x + ((g2−g1)/(200L))x². Peg at intervals, set by offset from tangent level and checked at EVC.
Write a short note on setting out vertical curve.
Vertical curves are provided at changes of grade on roads and railways to give a smooth transition, safe sight distance and comfort. A parabola is used: the rate of change of grade is constant.
Types
- Summit (crest) curve: the grade changes from rising to falling or less rising.
- Sag (valley) curve: the grade changes from falling to rising or less falling.
Summit curve Sag curve
___ \ /
__/ \__ \_ _/
‾‾
Data required
- Grades and (in %), chainage and RL of the intersection point.
- Length of the curve, either given or found from the permissible rate of change of grade : , or from sight distance requirements.
Computations (equal tangent parabola)
- Chainage of BVC = IP − , of EVC = IP + .
- RL of BVC ; RL of EVC .
- RL of any point at distance from BVC:
- Mid-ordinate (offset at the IP): . Level of mid-point of curve (+ for sag, − for summit).
- Turning point (highest or lowest): from BVC.
Setting out in the field
- Fix the IP, BVC and EVC by measuring along the two tangents.
- Peg the curve at regular intervals (usually 20 or 30 m) from BVC.
- Compute the offsets and the tangent levels, then the curve RL (tabulated).
- Using a level and staff, set each peg so that its top is at the computed RL (or measure the offset from the tangent level).
- Check that the RL at EVC agrees with the computed value.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Setting out right hand side composite curve · Surveying II, chapter 6
- Setting out simple curve by Rankine's method · Surveying II, chapter 6
- Short note: Rankine's method of curve setting · Surveying II, chapter 6
- Vertical curve -1% and +0.5% by parabolic method · Surveying II, chapter 6 · asked 2×
- Vertical curve -1% and +0.5%, IP 500 m · Surveying II, chapter 6 · asked 2×
- Vertical curve table, -4.5% and +3.5%, 200 m · Surveying II, chapter 6
- Setting out of a building · Building Technology, chapter 2
- Vertical curve -3.5% and +4%, 250 m night · Transportation Engineering I, chapter 3 · asked 2×
- Vertical curve -3% and +4.5% at 320.8 m · Transportation Engineering I, chapter 3 · asked 2×
- Vertical curve with intermediate sight distance · Transportation Engineering I, chapter 3