Short note: Rankine's method of curve setting

Short answer

Rankine's method sets out a circular curve using a theodolite at the first tangent point, sighting the intersection point with vernier zero. Each point is fixed by turning the cumulative deflection angle (sum of tangential angles δ = 1718.87c/R minutes for chord c) and measuring the chord from the previous point; the final cumulative angle must equal Δ/2 as a check.

Write a short note on setting out of circular curve by Rankine's method.

Rankine's method (also called the deflection angle method or tangential angle method) sets out a circular curve using a theodolite and a tape. The curve is located by a series of short chords, and each point is fixed by the angle at the tangent point between the tangent and the chord to that point, together with the length of the chord.

Principle

The angle between the tangent and a chord equals half the central angle subtended by that chord. For a chord cc on a curve of radius RR:

δ=90∘ cπR (degrees)=1718.87 cR (minutes)\delta = \frac{90^\circ\,c}{\pi R}\ \text{(degrees)} = \frac{1718.87\,c}{R}\ \text{(minutes)}

The deflection angle of any point from the first tangent is the sum of the tangential angles up to that point: Δn=δ1+δ2+⋯+δn\Delta_n = \delta_1+\delta_2+\dots+\delta_n.

Data to compute

  1. RR, T=Rtan⁡(Δ/2)T = R\tan(\Delta/2) and L=πRΔ/180L = \pi R\Delta/180.
  2. Chainages of the first tangent point T₁ = IP − T and last tangent point T₂ = T₁ + L.
  3. First sub-chord c1c_1 (from T₁ to the next full peg), full chords cc, and last sub-chord cnc_n (to T₂).
  4. Tangential angle of each chord and the cumulative deflection angles.

Field procedure

  1. Locate T₁ and T₂ by measuring TT back and forward from the IP along the tangents.
  2. Set up the theodolite at T₁, level it, and with the vernier at zero sight the IP.
  3. Set the first deflection angle δ1\delta_1 and measure the sub-chord c1c_1 from T₁ with the tape; the arrow end gives point 1.
  4. Set the cumulative angle Δ2\Delta_2; swing the tape from point 1 with length cc until it cuts the line of sight, fixing point 2. Repeat for all points.
  5. The last cumulative angle must equal Δ/2\Delta/2, and the last point must coincide with T₂ (check). If the error is small, adjust the last points.
          IP
         /\
        /  \
   T1  /    \  T2
     o'      'o
      \  . .  /
       1 2 3 4

Merits: accurate, needs only one instrument setup and is suitable for long and moderate curves. Limitation: errors accumulate along the curve; obstacles on the curve require shifting the instrument.