Preloading places temporary surcharge fill on soft clay to induce consolidation settlement before construction, often with vertical drains. Stone columns are compacted crushed stone columns installed by vibro-replacement, increasing bearing capacity, reducing settlement and providing drainage.

In order to increase the engineering properties of soils, soil stabilization is done. Briefly explain the preloading and stone columns for foundation soil improvements.

Soil stabilization improves the strength and reduces the settlement of weak soils. Two common ground-improvement methods are given below.

Preloading

Preloading means placing a temporary load (surcharge fill) on the site before construction, so that most of the consolidation settlement of soft clay occurs beforehand.

  • The fill is kept in place until the expected settlement is achieved, then removed, and the structure is built.
  • Vertical sand drains or prefabricated vertical drains (PVD) are often provided to shorten drainage paths and speed up consolidation.
  • Settlement is monitored with settlement plates and piezometers.
  • It is suitable for soft clays, silts and organic soils where time is available. Disadvantage: it needs time and space.

Stone columns

Stone columns are vertical columns of compacted crushed stone (gravel) installed in soft clay or loose silty soil.

  • A hole is made by a vibrating probe (vibro-replacement) or by driving a casing, then filled with stone in lifts and compacted.
  • The stiff columns carry most of the load and also act as drains.
  • They increase bearing capacity, reduce settlement and reduce liquefaction potential.
  • Typical diameter is 0.6-1.0 m at 1.5-3 m spacing.