Short answer

Depth is determined by maximum scour depth (2d for piers) plus grip length (≥1/3 of that), bearing capacity, and stability. Sinking above water level uses a sand island or floating caisson; a cutting edge is placed, steining cast, soil dredged evenly under own weight with kentledge, verticality checked, a bottom plug placed by tremie, then filling and capping.

How do you determine the depth of the well? Describe the sinking process of the well (in a site having water table above the ground level).

Depth of a well foundation

The depth is fixed by:

  1. Scour depth. The founding level is the maximum scour depth plus a grip length. The normal scour depth by Lacey's formula is d=1.34(q2f)1/3d = 1.34\left(\dfrac{q^2}{f}\right)^{1/3} (qq = discharge per metre width, ff = silt factor). The maximum scour depth is taken as 2d2d at piers (or 1.27d1.27d to 1.5d1.5d for abutments), measured below HFL.
  2. Grip length: at least 13\tfrac{1}{3} of the maximum scour depth below the maximum scour level, for lateral stability.
  3. Bearing capacity: a stratum that can carry the load safely (settlement within limits).
  4. Stability against overturning and sliding (passive resistance of soil), and the depth at which a firm stratum or rock is found.
  5. The depth must also avoid liquefiable or soft layers.

Sinking of a well (in a site with water above ground level)

  1. Construction site: a sand island (a temporary sand-filled island enclosed by sandbags/bamboo) is built above the water level in shallow water, or a floating caisson (a steel shell) is used in deep water.
  2. Cutting edge and curb: these are placed on the island and a first lift of steining (about 2 to 3 m) is cast over them.
  3. Dredging: soil is removed from the dredge hole by a grab, an air-lift or divers, so the well sinks under its own weight. Steining is built in lifts as the well sinks, keeping its top about 1 m above water.
  4. Aids to sinking: kentledge (extra weights), water jetting to reduce skin friction, bentonite slurry (lubrication), or pulling.
  5. Verticality control: tilt and shift are corrected as sinking continues.
  6. Founding: at the founding level the base is cleaned and inspected, and the bottom plug is placed by tremie under water.
  7. Finishing: the well is dewatered, filled with sand, topped with a top plug and capped by the well cap.