Forces include vertical loads (dead, live, self-weight, buoyancy), horizontal forces (braking, centrifugal, wind, water current, seismic), earth pressure (active/passive), secondary forces (temperature, shrinkage), forces during sinking (skin friction), and water pressure. The resultant horizontal force H and moment M at scour level must be resisted by soil.
What are the different forces acting on a well foundation?
The forces acting on a well foundation are:
- Vertical loads: dead load of the superstructure and the pier, live load on the bridge, self-weight of the well, and buoyancy (uplift).
- Horizontal forces: braking/tractive force of vehicles, centrifugal force on curves, wind load, water current force on the pier and well, and earthquake (seismic) forces.
- Earth pressure: active and passive earth pressure on the well, and surcharge on the soil, for abutments.
- Secondary forces: temperature, shrinkage and friction at bearings.
- Forces during sinking: skin friction of the soil, and the stresses from the weight and kentledge.
- Water pressure: buoyancy and seepage forces.
The horizontal forces and their moments (force times lever arm) at the scour level give a resultant horizontal force and moment , which the lateral resistance of the soil must resist.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Components of well foundation with sketch · Foundation Engineering, chapter 9 · asked 9×
- When well foundation is suitable · Foundation Engineering, chapter 9 · asked 2×
- Remedies for tilt and shift of well · Foundation Engineering, chapter 9 · asked 9×
- Depth of well and sinking process · Foundation Engineering, chapter 9 · asked 3×
- Methods of lateral stability analysis of well · Foundation Engineering, chapter 9 · asked 2×
- Precautions against tilt and shift of well · Foundation Engineering, chapter 9
- Forces acting on gravity dam · Hydro Power, chapter 4
- Well foundation: excavation, sinking, brick, PCC curb · Estimating and Costing, chapter 6 · asked 2×
- Well foundation: sinking, brick, sand filling, PCC · Estimating and Costing, chapter 6 · asked 2×
- Well foundation, 5 m internal diameter · Estimating and Costing, chapter 6 · asked 2×