- 2075 Chaitra · 12 marks
Case study: plan, feasibility and ROI
Short answer
For the dairy pasteurization plant, the existing manual system caused temperature variation and rejects. The recommended microcontroller-based closed-loop control with PT100, flow sensors, RS-485 Modbus and relay outputs provides ±0.5°C accuracy, reduces rejects and steam waste, with a 10.4-month payback and 115% ROI. Rollback uses a changeover switch to manual valve.
Explain your industrial visit carried out on your case study in terms of existing system circumstances, problem identification and analysis, recommendation plan, requirement and feasibility analysis of the recommended plan and rollback plan if necessary. Also list out the different advantages of the proposed plan in terms of technology, production rate, quality assurance, cost-benefit and return on investment (ROI) for the particular industry.
Assumed case study: a milk pasteurisation and packaging section of a dairy plant (HTST process: raw milk tank, heat exchanger, steam-heated holding tube, cooling, filling). The existing system uses analog panel indicators, bimetal thermostats, a manual steam valve and operator logging. (If your own visit was to another plant, replace the process names; the structure of the answer stays the same.)
Existing system circumstances
Raw milk tank --> pump --> heat exch. --> holding tube
(level sw) (motor (steam valve (72 C, 15 s)
starter) manual) |
cooling --> filling
Panel meters / thermostats <-- operator reads, adjusts
Manual operation with analog gauges; no alarms and no records; operators control the steam valve by judgement.
Problem identification and analysis
Temperature varies by ±3 C (risk of under-pasteurised or burnt milk); about 1.5 percent of batches are rejected; steam is wasted; there are frequent power interruptions; there is no traceability; and the labour need is high. Cause analysis shows that the absence of feedback control and automatic logging is the root cause.
Recommendation plan
Install the microcontroller-based closed-loop control:
PT100 --> Amp/SigCond --+
Level sensor ----------+--> MUX/ADC (12-bit)
Flow sensor ---(pulse)-+ |
Keypad ----------------+---> [Microcontroller] <--> LCD 16x2
| ARM/AVR + flash |
Opto + SSR/relay <----------+ watchdog, timers +--> RS-485
| | (Modbus)
Pump / steam valve / alarm +--> EEPROM log PC / SCADA
Power supply: 24 V + 5 V + UPS
Phases: (1) survey and design, (2) bench prototype and test, (3) pilot installation on one line in parallel with the old system, (4) full commissioning and training, (5) monitoring and review.
Requirement and feasibility analysis
- Technical: all components are available; the accuracy needed is ±0.5 C and the 12-bit ADC gives 0.037 C per count (calculated).
- Economic: investment Rs 12 lakh, monthly saving Rs 1.15 lakh, payback about 10.4 months (assumed).
- Operational: operators can be trained in two weeks; maintenance by plant technicians.
- Schedule: about 3 months.
Rollback plan
Keep the old manual valve and thermostat connected through a changeover switch. If the new controller fails in the pilot or later, switch back to manual control with little or no loss of production, and then debug the fault.
Advantages
- Technology: programmable, networked, upgradable.
- Production rate: less downtime and higher throughput.
- Quality assurance: consistent pasteurisation and records for audits.
- Cost-benefit and ROI: investment Rs 12,00,000 (controller panel, sensors, valves, SCADA PC, installation, training). Monthly savings: manpower Rs 60,000, steam/energy Rs 35,000, reduced rejection Rs 20,000 = Rs 1,15,000. Payback = 12,00,000 / 1,15,000 ≈ 10.4 months; yearly return = 13.8 lakh on 12 lakh, about 115 percent.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Case study: existing vs proposed system · Instrumentation II, chapter 10
- Case study: workflow, factors, proposed design, benefits · Instrumentation II, chapter 10
- Case study: new system vs existing (cost, manpower) · Instrumentation II, chapter 10 · asked 4×
- Case study: feasibility, drawbacks, convincing · Instrumentation II, chapter 10
- Case study: current control and recommendation · Instrumentation II, chapter 10 · asked 3×
- Case study: proposed system design · Instrumentation II, chapter 10
- PDLC and feasibility study · ICT Project Management, chapter 1
- Case study: Nepal Electricity Authority / Telecom · Organization and Management, chapter 9
- Feasibility study and its types · Software Engineering, chapter 1
- Steps of a feasibility study (team leader) · Hydropower Engineering, chapter 2