- 2081 Bhadra · 8 marks
Steps of a feasibility study (team leader)
Short answer
The feasibility study includes mobilization, topographic/hydrological/geotechnical surveys, optimization of design discharge and installed capacity, preliminary design of structures and electro-mechanical equipment, cost estimation (±10–15%), environmental and social assessment (IEE), economic and financial analysis (B/C, NPV, IRR), and final report preparation.
Suppose you are a senior consultant engineer with the responsibility of being the team leader for a small hydropower project. Describe the steps and activities that your team must carry out to conduct a feasibility study for this hydropower project.
As team leader of a feasibility study for a small hydropower project, I would organise the work in the following steps.
- Mobilisation and planning: Review the pre-feasibility report and terms of reference; form a team (hydrologist, geologist, civil/structural, hydraulic, electro-mechanical, survey, environment, social, economist, cost engineer); prepare the work plan, schedule and budget; collect maps and data.
- Surveys: Topographic survey at 1:500-1:1000 of headworks, waterway, powerhouse; river cross-sections; alignment survey of access road and transmission line.
- Hydrological study: Install/read the gauge, discharge measurements, long-term flow series by correlation, FDC, design flood, sediment load, environmental flow.
- Geological and geotechnical study: Mapping, geophysics, core drilling, test pits, rock/soil tests, and construction materials survey; assess slope stability.
- Selection of the project parameters: Optimise design discharge and installed capacity (energy vs. cost), fix the intake, waterway type, powerhouse position and the tailrace level.
- Preliminary design: Weir/intake, desander, headrace, forebay, penstock, powerhouse, tailrace, access, and switchyard; hydraulic and structural calculations; turbine selection (type, number, rating).
- Transmission and market: Line route to the grid, substation, and a check with NEA about the PPA/tariff.
- Environmental and social: IEE (up to 50 MW) with baseline data, impact and mitigation, resettlement and land acquisition plan.
- Quantities, cost and schedule: Bill of quantities, unit rates, project cost (±10-15%), construction schedule and implementation plan.
- Economic and financial analysis: Energy and revenue, B/C, NPV, IRR, payback, sensitivity to cost, flow and tariff; financing plan.
- Report: Main report, drawings, annexes; present to the client; revise by comments.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Study stages for 10 MW remote project · Hydropower Engineering, chapter 2
- Pre-feasibility site-specific investigations · Hydropower Engineering, chapter 2
- Development phases; pre-feasibility factors · Hydropower Engineering, chapter 2
- Studies in reconnaissance, pre-feasibility, feasibility · Hydropower Engineering, chapter 2 · asked 3×
- Pre-feasibility vs feasibility; site investigations · Hydropower Engineering, chapter 2
- 300 MW reservoir project: planning to commissioning · Hydropower Engineering, chapter 2
- Case study: feasibility, drawbacks, convincing · Instrumentation II, chapter 10
- Proposal; feasibility study of a road project · Project Engineering, chapter 2
- Stages of hydropower project study · Hydro Power, chapter 3 · asked 3×
- PDLC and feasibility study · ICT Project Management, chapter 1