Skip to main content

Pre-feasibility vs feasibility; site investigations

Short answer

Pre-feasibility selects the best alternative with moderate survey, short hydrology, mapping, geophysics, few boreholes, cost accuracy ±20-25%, and scoping. Feasibility confirms viability with detailed surveys, long hydrology, floods, sediment, drilling, design optimisation, cost accuracy ±10-15%, and IEE/EIA. Hydrological: gauge, flow measurement, FDC, floods, sediment. Topographical: detailed mapping, cross-sections, alignment survey.

Differentiate between pre-feasibility and feasibility studies of a hydropower project, explaining the site specific hydrological and topographical investigations.

Pre-feasibility selects the best option and decides if detailed study is worthwhile; feasibility confirms the selected option in full detail so that the investment decision can be made.

PointPre-feasibilityFeasibility
AimCompare alternatives, select bestConfirm viability of selected project
SurveyModerate (1:5,000 to 1:2,000)Detailed (1:1,000 to 1:500)
HydrologyShort gauging, regional methodsLong series, floods, sediment
GeologyMapping, geophysics, few holesDrilling at all structures, tests
DesignConceptualPreliminary design, optimisation
Cost accuracy±20-25%±10-15%
EnvironmentScopingIEE/EIA
OutputChoice of layout, go/no-goBankable report

Site-specific hydrological investigations

  • Collect all available rainfall and runoff records (DHM) and the catchment characteristics.
  • Install a staff gauge or automatic gauge at the headworks; measure discharge by current meter or salt dilution regularly; develop the rating curve.
  • Derive the mean monthly flow, flow duration curve and low flow using correlation with a nearby gauged basin or the WECS/MIP method.
  • Estimate floods (return periods 2-1000 years), by frequency analysis or empirical methods, and check for GLOF/snow melt.
  • Measure suspended sediment concentration; estimate the sediment load and the particle size.
  • Record the high flood marks and the tail water level at the powerhouse.

Topographical investigations

  • Topographic mapping with contours at the headworks, along the waterway and at the powerhouse.
  • River cross-sections and longitudinal profile (for the stage-discharge and head).
  • Reservoir area-capacity curve if the pond/reservoir exists.
  • Alignment survey of the canal/tunnel, penstock, access road and transmission line.
  • Benchmark control (GPS/total station), and the location of boreholes and test pits.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Hydropower Engineering chapter 2 questions →