- 2070 Chaitra · 5 marks
Pre-feasibility site-specific investigations
Explain site specific hydrological, geological and topographical investigations to be carried out during the pre-feasibility study level of a hydropower project.
Site-specific investigations in the pre-feasibility study are done only at a moderate level to select the best layout.
Hydrological investigations
- Collect rainfall, flow, and climate data from DHM stations in or near the basin.
- Set up a gauge at the headworks and measure discharge across seasons (current meter, floats, salt dilution).
- Estimate mean monthly flows and the flow duration curve by regional methods (WECS/DHM, MIP) and correlation with a nearby station.
- Estimate flood flows of different return periods (frequency analysis, regional formula), and check for GLOF and landslide dam outburst.
- Sample suspended sediment to estimate load and plan the desander.
Geological investigations
- Review regional geology maps and satellite images; do detailed surface mapping of the sites for the weir, intake, tunnel alignment, powerhouse and slope stability.
- Find structures: faults, folds, shear zones, joint sets, and landslides.
- Geophysical survey (seismic refraction, resistivity) to find overburden thickness and rock quality.
- A few boreholes and test pits at the headworks and powerhouse; identify construction materials (quarry, borrow, sand).
- Seismic hazard check.
Topographical investigations
- Topographic map (1:5,000 to 1:2,000) with contours of the project area.
- River cross-sections and profile at the weir and powerhouse.
- Alignment of the waterway and access road options.
- Benchmarks and control points for later detailed survey.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Pre-feasibility vs feasibility; site investigations · Hydropower Engineering, chapter 2
- Studies in reconnaissance, pre-feasibility, feasibility · Hydropower Engineering, chapter 2 · asked 3×
- Development phases; pre-feasibility factors · Hydropower Engineering, chapter 2
- Steps of a feasibility study (team leader) · Hydropower Engineering, chapter 2
- Proposal; feasibility study of a road project · Project Engineering, chapter 2
- Topographical and geological maps for materials · Engineering Geology II, chapter 7 · asked 7×
- Stages of hydropower project study · Hydro Power, chapter 3 · asked 3×
- PDLC and feasibility study · ICT Project Management, chapter 1