Pre-feasibility versus feasibility studies

Short answer

Pre-feasibility screening alternatives to select the best layout with approximate costs (±25–30%). Feasibility study detailly confirms the chosenscheme 's technical, economic, and environmental viability with refined costs (±10–15%) to secure financing.

Explain the differences between Pre-feasibility and Feasibility studies in hydropower projects.

Pre-feasibility study is a preliminary study that compares alternative layouts of a hydropower site and selects the most promising one. Feasibility study is a detailed study of the selected scheme to prove that it is technically, economically, financially and environmentally viable and ready for financing.

PointPre-feasibility studyFeasibility study
PurposeScreen alternatives and choose the bestConfirm viability of the chosen scheme
StageAfter reconnaissance/desk studyAfter pre-feasibility, before detailed design
DataExisting maps (1:50,000), short or regional hydrologyDetailed survey (1:1000–1:5000), site flow measurement
InvestigationsSurface geological mapping, few testsDrilling, test pits, seismic survey, material tests
DesignConceptual layouts, rough sizesOptimised layout, preliminary design of all structures
Cost estimate accuracyAbout ±25–30%About ±10–15%
EnvironmentInitial screening of impactsFull IEE/EIA
OutputRecommended alternative, go/no-goBankable report: B/C, IRR, financing plan
Cost and timeLow, a few monthsHigh, one to two years

In short, the pre-feasibility study answers "which option is best?", and the feasibility study answers "is this option worth building, and how?".