Case study: problems after implementation

Short answer

After implementation, technical issues like EMI, sensor drift, software hangs, and communication faults can occur, along with operator resistance and spares dependency. Mitigations include shielding, UPS, watchdog, pilot run, training, manual override, and preventive maintenance.

Mention different types of problems that might occur after implementing the [system] [question text is cut off in the scan].

The question text is cut off in the scan; it is read as: problems that might occur after implementing the proposed (automatic control) system in the case-study plant.

Technical problems

  1. Electrical noise and EMI from motors, relays and VFDs corrupt sensor signals and cause false triggering (need shielding, grounding, filters).
  2. Ground loops and power-quality problems: voltage dips, surges and power cuts reset the controller (use UPS, surge protection).
  3. Sensor drift and failure, needing periodic calibration; wiring faults.
  4. Software bugs and controller hang-ups (watchdog needed); loss of settings.
  5. Communication errors on the network (RS-485 faults, wrong baud rate or addresses).
  6. Single point of failure if there is no redundancy or manual bypass.
  7. Compatibility problems with old equipment.

Organisational problems

  • Operator resistance and lack of skills; training needed.
  • Dependence on a few experts or on the supplier for spares and support.
  • Higher maintenance cost and spare-part availability.
  • Data and cyber security, and production stoppage during commissioning.

Remedies

Pilot run, parallel operation with the old system, training, preventive maintenance, spares stock, manual override, documentation and a support contract.