- 2070 Chaitra · 5 marks
Test of proportion: pumps needing repairs
Short answer
Use right-tailed z-test for a proportion. p̂ = 47/120 = 0.3917, p₀ = 0.30, SE = 0.04183, z = 2.191. Critical z₀.₀₅ = 1.645. Reject H₀: p=0.30. Evidence supports p>0.30, so the manufacturer’s claim is not supported.
A manufacturer of submersible pumps claims that at most 30% of the pumps require within the first 5 years of operation. If a random sample of 120 of the pumps includes 47 which required repairs within the first 5 years, test the null hypothesis p = 0.30 against the alternative hypothesis p > 0.30 at the 0.05 level of significance.
Large-sample, right-tailed test of a single proportion.
n = 120, x = 47, p̂ = 47/120 = 0.3917, p₀ = 0.30, q₀ = 0.70
- H0: p = 0.30 H1: p > 0.30 (more than 30% of pumps need repair)
- Level of significance: α = 0.05
- Test statistic:
SE = √(p₀q₀/n) = √(0.30×0.70/120) = 0.04183
z = (p̂ − p₀)/SE = (0.3917 − 0.30)/0.04183 = 2.191
- Critical value: z(0.05, right-tail) = 1.645. Reject H0 if z > 1.645.
- Decision: z = 2.191 > 1.645 (p-value = 0.014), so reject H0.
Conclusion: at the 5% level the data show that more than 30% of the pumps need repair within the first 5 years, so the manufacturer's claim is not supported.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Null, alternative hypothesis; errors · Probability and Statistics, chapter 7
- Test of proportion: drug test failure rate · Probability and Statistics, chapter 7
- Test of proportion: 95% equipment claim · Probability and Statistics, chapter 7
- Test of proportion: 60 Minutes TV share · Probability and Statistics, chapter 7
- Types of error; single proportion test · Probability and Statistics, chapter 7 · asked 2×
- Procedure: test of single proportion · Probability and Statistics, chapter 7 · asked 2×
- Chi-square test on 100 random numbers · Simulation and Modeling, chapter 6
- Random process; LTI output is WSS if input is WSS · Communication Systems, chapter 9
- Gumbel 500-year flood, 95% limits, 30 years · Engineering Hydrology, chapter 6
- Importance and operation of sample and hold · Digital Control System, chapter 1