Break pressure tank: need and construction
Short answer
In steep gravity schemes, high static pressure can burst pipes; a break pressure tank reduces pressure to atmospheric, limiting the head in the next section so lower-class pipes can be used. It is a small masonry/RCC tank with an inlet float valve, outlet, overflow, washout, vent, and cover.
Why is a break pressure tank (BPT) necessary in a water supply scheme? Describe/explain its construction with a neat sketch.
Why a break pressure tank is needed
In a gravity scheme laid on steep ground, the static pressure at the lower part of the pipe becomes very large (it increases by 1 kg/cm² for every 10 m drop). This can burst pipes, joints and taps, and needs expensive high-class pipes. A break pressure tank (BPT) is a small open tank placed along the pipeline that makes the water pressure zero (atmospheric) at that point, so the static head of the next section is reduced to the height below the tank. Thus lower-class pipes can be used, and pressure at taps stays within safe limits (generally below 60–70 m).
It is also used to remove air and reduce the energy of the incoming water.
Construction
inlet pipe (from above)
| float valve
___|_____ /___ vent/cover
| ~~~~~~~~~ |-- overflow
| water |
|_______________|-- outlet to next section
washout
- The tank is built of stone/brick masonry or RCC with cement plaster, usually 1 m × 1 m to 1.5 m × 1.5 m in plan and about 1–1.5 m deep (volume is just enough to hold a few minutes' flow).
- Inlet pipe with a ball (float) valve closes the supply when the tank is full.
- Outlet pipe to the next section, at 100–150 mm above the floor, with a strainer.
- Overflow pipe, washout pipe for cleaning, a vent, and an RCC cover with a manhole for inspection.
- Free board about 0.3 m. A fence is provided around it and the site is drained.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Necessity and impacts of water supply scheme · Water Supply Engineering, chapter 1 · asked 3×
- BPT requirement; residual head at stand post · Water Supply Engineering, chapter 9
- Is balancing tank necessary: 20000 L/day spring · Water Supply Engineering, chapter 7
- Objectives of supply; wholesome water requirements · Water Supply Engineering, chapter 1 · asked 2×
- Protection and maintenance of water supply · Water Supply Engineering, chapter 7 · asked 4×
- Storage tank capacity and water level, 20000 L/day · Water Supply Engineering, chapter 7 · asked 2×
- Domestic water supply; septic tank and soak pit · Building Technology, chapter 12
- Gauge pressure in cleaning fluid tank · Fluid Mechanics, chapter 2
- Pressure diagram in rotating closed tank · Fluid Mechanics, chapter 2
- Water supply and sanitation management · Building Technology, chapter 12