- 2075 Chaitra · 8 marks
Design period, base period, demand types
Short answer
Design period is years until extension; base period is 2–5 years from survey to operation. Peak hour demand (~2.7 × average daily demand) sizes distribution pipes. Demand types: domestic (45–135 lpcd), institutional, industrial, livestock, public, fire, and losses. Factors: climate, town size, living standard, industry, water cost, metering, pressure, and supply continuity.
What is meant by design period, base period and peak hour demand? Describe the various types of water demand and discuss the factors which affect the rate of demand in a water supply scheme.
Design period
The number of years for which a water supply scheme is designed to serve the growing population before it must be extended or replaced. It is counted from the base year to the design year and depends on the life of the component, the cost of capital, the ease of expansion and the growth rate. Typical values: intake and pipes 20 to 30 years, treatment plant 15 to 20 years, pumps 10 to 15 years, reservoirs 30 to 50 years. For rural schemes in Nepal it is commonly 15 to 20 years.
Base period
The time between the survey (data collection) year and the start of operation of the scheme (it covers design, approval and construction). Typical value: 2 to 5 years. The base year = survey year + base period, and the design year = base year + design period.
Peak hour demand
The maximum rate of demand in any hour of the day; this rate is used to design the distribution system. Peak hour demand maximum daily demand average daily demand.
Types of water demand
| Type | Examples | Usual rate |
|---|---|---|
| Domestic | Drinking, cooking, bathing, washing, flushing | 45 lpcd (rural) to 135 lpcd (urban) |
| Institutional and public | Schools, offices, hospitals, hotels, public standposts | 5 to 45 l/head/day; hospitals 340 l/bed/day |
| Commercial and industrial | Shops, factories, cinemas, markets | Depends on the type |
| Livestock | Cows, buffaloes, goats, poultry | 45 l/day per big animal, 5 l/day per small animal |
| Public use | Road washing, parks, fountains, sewer flushing | About 5 percent of the total |
| Fire demand | Fire fighting | l/min, P in thousands |
| Losses and wastage | Leakage, theft, faulty meters | 15 to 20 percent |
Factors affecting the demand
Climate, size and nature of the town, standard of living, industry and commerce, quality and cost of water (tariff), metering, supply pressure, continuous or intermittent supply, leakage control, and the habits and culture of the people.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Demand of rural municipality, base period 3 years · Water Supply Engineering, chapter 3
- Demand of village 2070 BS, base period 5 years · Water Supply Engineering, chapter 3
- Factors affecting water demand; variation · Water Supply Engineering, chapter 3 · asked 5×
- Demand 2074 BS, geometric and decreasing rate · Water Supply Engineering, chapter 3
- Necessity and impacts of water supply scheme · Water Supply Engineering, chapter 1 · asked 3×
- Rural village demand, survey 2070 BS, base year 2073 · Water Supply Engineering, chapter 3
- Peak hour volume and PHF from counts · Transportation Engineering II, chapter 1
- Peak demand of load center from load pattern · Transmission and Distribution System Design, chapter 6 · asked 2×
- T/F: peak demand as sum of class peaks · Transmission and Distribution System Design, chapter 6
- Nepal electricity demand, supply and trend · Power Plant Design, chapter 1