Short answer

Causes: moisture and thermal movement, foundation settlement, elastic deformation, reinforcement corrosion, chemical attack, vegetation, earthquake, poor work, overloading, fire. Remedial measures: hairline – cement slurry; small – rake and fill with 1:3 mortar; medium – epoxy injection; wide – stitching, jacketing or rebuild; settlement – underpinning; provide movement joints and good curing.

Write down the causes of cracks that occur in a building and its remedial measures briefly.

Cracks in buildings arise from the following causes.

CauseHow it cracks the building
Moisture movementBricks, blocks and concrete expand on wetting and shrink on drying; mortar and plaster shrinkage
Thermal movementExpansion and contraction with temperature in roofs, long walls, parapets
Settlement of foundationUnequal settlement due to poor or non-uniform soil, wrong foundation level, change in moisture, or inadequate depth
Elastic deformationOverload, deflection of beams and slabs, bending and shear
Corrosion of reinforcementRust expands and splits the concrete cover
Chemical actionSulphate attack, alkali-aggregate reaction, carbonation
VegetationRoots of trees near walls and foundations
Earthquake and windLateral forces on weak walls and joints
Poor workmanship and materialsPoor curing, mix, bonding, early removal of formwork, missing joints
Overloading and design errorExcess load, wrong detailing
Fire, vibrationHeat damage, machine vibration

Remedial measures

Crack widthRemedy
Hairline (< 0.3 mm)Fill with cement slurry or paint-grade filler; fresh plaster
Small (0.3-1.0 mm)Rake out, fill with cement-sand mortar (1:3) or polymer-modified mortar
Medium (1-3 mm)Epoxy injection or cement grout through packers
Wide (> 3 mm)Remove and rebuild, stitching with steel clamps, epoxy mortar, jacketing
Foundation settlementUnderpinning, grouting, soil improvement
RCC cracksEpoxy injection, grouting, jacketing, bonding steel plates
Roof cracksWaterproof treatment, expansion joints, sealants

Additional measures: provide movement joints, good drainage, proper curing, tie beams, and good-quality materials.