Painting on masonry; causes and remedies of cracks

Short answer

Masonry painting: let plaster cure 3-4 weeks, clean, repair, apply alkali primer and wall putty, then two coats of paint (cement paint wetted and cured). Causes: moisture and thermal movement, settlement, elastic deformation, corrosion, chemical attack, vegetation, earthquakes, poor work. Remedial: hairline – cement slurry; small – rake and mortar; medium – epoxy injection; wide – stitch/jacket; settlement – underpinning.

Explain the process of painting works on masonry surfaces. What may be the causes of cracks occurred in a building and what are remedial measure to cracks?

Painting on masonry surfaces

  1. Preparation: plaster must be at least 3-4 weeks old and fully dry. Remove dust, oil, loose particles and efflorescence with a wire brush and wash.
  2. Repair: fill cracks and holes with cement mortar or putty and let them dry.
  3. Primer: apply an alkali-resistant primer.
  4. Putty: apply wall putty in two coats; rub down with sandpaper after each.
  5. Painting: apply two coats of emulsion, distemper or cement paint with a brush or roller. The second coat is applied after 4-6 hours. For cement paint, wet the surface first, and cure the paint for 2 days.

Causes of cracks in buildings

CauseHow it cracks the building
Moisture movementBricks, blocks and concrete expand on wetting and shrink on drying; mortar and plaster shrinkage
Thermal movementExpansion and contraction with temperature in roofs, long walls, parapets
Settlement of foundationUnequal settlement due to poor or non-uniform soil, wrong foundation level, change in moisture, or inadequate depth
Elastic deformationOverload, deflection of beams and slabs, bending and shear
Corrosion of reinforcementRust expands and splits the concrete cover
Chemical actionSulphate attack, alkali-aggregate reaction, carbonation
VegetationRoots of trees near walls and foundations
Earthquake and windLateral forces on weak walls and joints
Poor workmanship and materialsPoor curing, mix, bonding, early removal of formwork, missing joints
Overloading and design errorExcess load, wrong detailing
Fire, vibrationHeat damage, machine vibration

Remedial measures

Crack widthRemedy
Hairline (< 0.3 mm)Fill with cement slurry or paint-grade filler; fresh plaster
Small (0.3-1.0 mm)Rake out, fill with cement-sand mortar (1:3) or polymer-modified mortar
Medium (1-3 mm)Epoxy injection or cement grout through packers
Wide (> 3 mm)Remove and rebuild, stitching with steel clamps, epoxy mortar, jacketing
Foundation settlementUnderpinning, grouting, soil improvement
RCC cracksEpoxy injection, grouting, jacketing, bonding steel plates
Roof cracksWaterproof treatment, expansion joints, sealants