Solid ground floor
Short answer
Solid ground floor layers from bottom: compacted earth, hardcore (100-150 mm), sand blinding (25-50 mm), damp proof membrane, concrete bed (100-150 mm, 1:2:4), screed (20-25 mm, 1:4), and floor finish. Plinth kept 300-450 mm above ground level for drainage.
Describe about solid ground floor with sketch (draw a section of solid ground floor with necessary details).
A solid ground floor is a floor laid directly on the ground, with its layers supported by well-compacted earth fill. It is the most common floor in ground-level rooms.
Layers (from the bottom up)
- Natural/compacted earth: the top soil is removed, then earth is filled in 150 mm layers and rammed to a firm base.
- Hardcore (brick soling or stone): 100-150 mm of broken brick/stone, well rammed, to cut capillary rise and give a firm bed.
- Sand blinding: about 25-50 mm, to fill the voids in the hardcore, stop the concrete grout leaking into it and protect the DPM from puncture.
- Damp proof membrane (DPM): 1000-gauge polythene or a bitumen layer (a 12 mm asphalt coat is also used) to stop ground moisture. It is joined to the DPC of the walls.
- Concrete bed (PCC): 100-150 mm thick, 1:2:4 or 1:3:6, over the whole room.
- Screed: 20-25 mm cement-sand (1:4) to level the surface.
- Floor finish: cement punning, terrazzo, tiles, marble, etc.
wall skirting
+-----+ ___________________ finish
| | ~~~~~~~~~~~~~~~~~~~ screed 25
| | ................... PCC 100-150
| DPC |= ___________________ DPM (laps with DPC)
| | ,,,,,,,,,,,,,,,,,,, sand blinding
| | ooooooooooooooooooo hardcore 150
+-----+ /////////////////// compacted earth
The plinth is normally kept 300-450 mm above the surrounding ground level, so the floor stays above the surrounding earth and rain water. A solid floor is suitable for dry, firm sites.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Solid and suspended ground floor · Building Technology, chapter 7 · asked 2×
- Ground floor with mosaic tiling and external wall · Building Technology, chapter 7
- Suspended ground floor · Building Technology, chapter 7 · asked 2×
- Suspended ground floor; tile flooring · Building Technology, chapter 7
- Hollow section replacing solid compression member · Strength of Materials, chapter 6
- Uplift at inside corners, 50 m floor weir · Irrigation and Drainage Engineering, chapter 5 · asked 2×
- Restrained floor slab, 4x5 m · Design of RCC Structure, chapter 9