- Practice · 6 marks
EOQ, total cost and reorder point numerical
Short answer
EOQ = 490 units; 24.5 orders/year, cycle 12.2 days; total ordering+holding cost = Rs 14,697; reorder point = 400 units; ordering 600 units increases annual cost by Rs 303.
A firm uses 12,000 units of an item per year. The unit cost is Rs 150, the ordering cost is Rs 300 per order and the carrying cost is 20% of the unit cost per year. The firm works 300 days a year and the lead time is 10 days. Find (a) the EOQ, (b) the number of orders per year and the time between orders, (c) the annual ordering plus holding cost, (d) the reorder point, and (e) the extra annual cost if the firm orders 600 units each time.
Given
units/year, Rs 300, Rs 30 per unit per year, 300 working days, days.
(a) EOQ
(b) Orders and cycle time
(c) Annual ordering plus holding cost
Ordering cost Rs 7,348; holding cost Rs 7,348.
(Purchase cost is Rs 1,800,000, so the total annual cost including purchase is Rs 1,814,697.)
(d) Reorder point
Daily demand units/day.
An order of 490 units is placed when the stock falls to 400 units.
(e) Order quantity of 600
Extra cost Rs 303 per year (about 2.1% higher).
Answer: EOQ = 490 units; 24.5 orders/year, every 12.2 working days; TC = Rs 14,697; ROP = 400 units; ordering 600 costs Rs 303 more per year.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Break-even cost comparison of three sites · Industrial Engineering and Management, chapter 2
- Safety stock and reorder level with lead time · Industrial Engineering and Management, chapter 4
- MRP explosion with lot-for-lot ordering · Industrial Engineering and Management, chapter 5
- Derivation of economic order quantity · Industrial Engineering and Management, chapter 4
- ABC analysis from annual consumption data · Industrial Engineering and Management, chapter 4
- EOQ and reorder point for rebar · Construction Management, chapter 3
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- Material classification, EOQ, GiT and re-order level · Construction Management, chapter 3
- EPS; total capital Rs 15,00,000 · Project Engineering, chapter 6
All Industrial Engineering and Management chapter 4 questions →