- 2071 Bhadra · 6 marks
EOQ and reorder point for rebar
Short answer
EOQ minimizes total ordering and carrying costs. Carrying cost =15% of Rs 90,000 = Rs 13,500/tonne/year. EOQ = sqrt(2*1000*10000/13500) ≈ 38.5 tonnes. Reorder point = lead time consumption (4*50 t) + safety stock (50 t) = 250 tonnes.
Define economic order quantity. Calculate EOQ and reorder point if rebar required is 1000 tonnes; Ordering Cost is Rs. 10,000; Carrying Cost is 15%, rebar rate is Rs. 90,000 per tonne; Safety Stock is 50 tonnes; lead time is 4 day and consumption per day is 50 tonnes.
Economic order quantity
EOQ is the order size that makes the total of ordering cost and carrying cost a minimum:
where is the annual requirement, the ordering cost per order and the carrying cost per unit per year.
Calculation
t, Rs 10,000, carrying cost = 15% of Rs 90,000 = Rs 13,500 per tonne per year.
Number of orders = 1000/38.49 = 26.0 per year.
Re-order point
Lead-time consumption = 4 days x 50 t/day = 200 t. Safety stock = 50 t.
Answer: EOQ = 38.49 tonnes (about 38.5 t); re-order point = 250 tonnes.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Material classification, EOQ, GiT and re-order level · Construction Management, chapter 3
- EOQ, stock levels and ROL for cement · Construction Management, chapter 3
- Define economic order quantity · Construction Management, chapter 3
- Valuation of a cinema hall (land Rs 15 lakh) · Construction Management, chapter 13 · asked 2×
- Capitalised value from Rs 20,000 monthly rent · Construction Management, chapter 13
- TCTO numerical: seven activities, Rs 1000/day · Construction Management, chapter 2
- EOQ, total cost and reorder point numerical · Industrial Engineering and Management, chapter 4
- Derivation of economic order quantity · Industrial Engineering and Management, chapter 4
- EPS; total capital Rs 15,00,000 · Project Engineering, chapter 6
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×