- 2078 Kartik · 6 marks
EOQ, stock levels and ROL for cement
Short answer
EOQ = sqrt(2*20000*10000/45) = 2981 bags. Daily use = 20000/365 ≈ 54.79 bags; safety = 548 bags; lead consumption =274 bags. ROP =822 bags, max =3529 bags, min =548 bags, avg =2039 bags. Total ordering + carrying cost = Rs 1,34,164; including purchase = Rs 1,81,34,164.
Calculate EOQ, Maximum Stock level, minimum, average stock level, and ROP/ROL if annual cement required for a construction project is 20000 bags; ordering cost is Rs. 10,000; Carrying cost is 5%; Cement rate is Rs. 900 per bag; Safety stock is 10 days; lead time is 5 days. Also calculate the total inventory cost.
Data
bags/year, Rs 10,000/order, Rs 900/bag, carrying cost = 5% of price, so Rs 45 per bag per year. A working year of 365 days is assumed, so daily use = 20,000/365 = 54.79 bags/day. Safety stock = 10 days, lead time = 5 days.
EOQ
Stock levels
- Safety (minimum) stock = 10 x 54.79 = 547.9 bags 548 bags
- Lead-time consumption = 5 x 54.79 = 274.0 bags
- Re-order level (ROP/ROL) = 274.0 + 547.9 = 821.9 bags 822 bags
- Maximum stock level = safety stock + EOQ = 547.9 + 2,981.4 = 3,529.3 bags 3,529 bags
- Minimum stock level = safety stock 548 bags
- Average stock level = (3,529.3 + 547.9)/2 = 2,038.6 bags 2,039 bags
Total inventory cost
- Number of orders = 20,000/2,981.4 = 6.71 per year
- Ordering cost = 6.71 x 10,000 = Rs 67,082
- Carrying cost = (EOQ/2) x 45 = 1,490.7 x 45 = Rs 67,082
- Total ordering + carrying cost = Rs 1,34,164
- Purchase cost = 20,000 x 900 = Rs 1,80,00,000
(If the carrying cost of the safety stock is also included, add 547.9 x 45 = Rs 24,658, giving Rs 1,58,822 before purchase cost.)
Answer: EOQ = 2,981 bags; ROL = 822 bags; maximum = 3,529 bags; minimum = 548 bags; average = 2,039 bags. Total inventory cost (ordering + carrying) = Rs 1,34,164; including the purchase cost, Rs 1,81,34,164.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Material classification, EOQ, GiT and re-order level · Construction Management, chapter 3
- EOQ and reorder point for rebar · Construction Management, chapter 3
- ABC categories and EOQ of cement · Construction Management, chapter 3
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- Capitalised value from Rs 20,000 monthly rent · Construction Management, chapter 13
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
- EOQ, total cost and reorder point numerical · Industrial Engineering and Management, chapter 4
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- Annual charge and pf improvement (Rs 1300/kVA tariff) · Utilization of Electrical Energy, chapter 6 · asked 3×