- 2068 Bhadra (old course) · 10 marks
TCTO numerical: least cost schedule, Rs 2000/week
Short answer
Assuming activity C normal cost Rs8,000, crash Rs10,000 (slope Rs1,000/wk). Least cost schedule: crash C by one week, duration 8 weeks, total cost Rs34,000. Normal 9 weeks costs Rs35,000. Further crashing (B+C) needs Rs4,000/wk > Rs2,000 saved.
The following information are available about various activities of the network. Determine least cost schedule. Project overhead cost are Rs 2000 per week.
| Activity | Normal Duration | Normal cost | Crash Duration | Crash cost |
|---|---|---|---|---|
| 1-2 (A) | 4 | 4000 | 3 | 7000 |
| 1-3 (B) | 8 | 5000 | 7 | 8000 |
| 2-3 (C) | 5 | 8000 [?] | 3 | 1000 [?] |
(The costs of activity 2-3 are blurred in the scan.)
Given data and method
Indirect cost = 2,000 Rs/week. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost.
Assumption: the costs of activity 2-3 (C) are blurred in the scan; they are taken as normal Rs 8,000 and crash Rs 10,000 (slope Rs 1,000/week). The result (optimum 8 weeks) holds for any crash slope of C below Rs 2,000 per week. Network: 1-2 (A) then 2-3 (C) in series, with 1-3 (B) in parallel.
| Activity | Normal dur | Crash dur | Normal cost | Crash cost | Slope |
|---|---|---|---|---|---|
| A | 4 | 3 | 4,000 | 7,000 | 3,000 |
| B | 8 | 7 | 5,000 | 8,000 | 3,000 |
| C | 5 | 3 | 8,000 | 10,000 | 1,000 |
Paths at normal duration
- A-C = 9 weeks
- B = 8 weeks
Critical activities (on the longest path or paths): A, C; normal duration = 9 weeks; normal direct cost = 17,000 Rs.
Crashing, step by step
| Step | Crash (by 1 unit) | Slope/cost | Duration | Direct | Indirect | Total |
|---|---|---|---|---|---|---|
| 0 | - | - | 9 | 17,000 | 18,000 | 35,000 |
| 1 | C | 1,000 | 8 | 18,000 | 16,000 | 34,000 |
| 2 | B+C | 4,000 | 7 | 22,000 | 14,000 | 36,000 |
(Rows with several activities show activities crashed together because two paths are critical.)
Result
- Optimum (minimum-cost) schedule: duration 8 weeks, direct cost 18,000 + indirect 16,000 = 34,000 Rs.
- Activities crashed at the optimum: C by 1. Durations: A=4, B=8, C=4.
- Minimum possible duration: 7 weeks, with total cost 36,000 Rs (direct 22,000 + indirect 14,000).
Answer: least cost schedule = 8 weeks (A = 4, B = 8, C = 4 weeks), total cost Rs 34,000 against Rs 35,000 for the normal 9-week schedule. A further week would need A or C together with B (Rs 4,000 > Rs 2,000 saved).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 2000/day · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 1000/day · Construction Management, chapter 2
- TCTO numerical: optimal crashed time, Rs 3000/week · Construction Management, chapter 2 · asked 2×
- TCTO numerical: seven activities, Rs 225/day · Construction Management, chapter 2
- TCTO numerical: optimal crashed result, Rs 300/week · Construction Management, chapter 2