TCTO numerical: least cost schedule, Rs 2000/week

Short answer

Assuming activity C normal cost Rs8,000, crash Rs10,000 (slope Rs1,000/wk). Least cost schedule: crash C by one week, duration 8 weeks, total cost Rs34,000. Normal 9 weeks costs Rs35,000. Further crashing (B+C) needs Rs4,000/wk > Rs2,000 saved.

The following information are available about various activities of the network. Determine least cost schedule. Project overhead cost are Rs 2000 per week.

ActivityNormal DurationNormal costCrash DurationCrash cost
1-2 (A)4400037000
1-3 (B)8500078000
2-3 (C)58000 [?]31000 [?]

(The costs of activity 2-3 are blurred in the scan.)

Given data and method

Indirect cost = 2,000 Rs/week. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost.

Assumption: the costs of activity 2-3 (C) are blurred in the scan; they are taken as normal Rs 8,000 and crash Rs 10,000 (slope Rs 1,000/week). The result (optimum 8 weeks) holds for any crash slope of C below Rs 2,000 per week. Network: 1-2 (A) then 2-3 (C) in series, with 1-3 (B) in parallel.

Cost slope=Crash cost−Normal costNormal duration−Crash duration\text{Cost slope}=\frac{\text{Crash cost}-\text{Normal cost}}{\text{Normal duration}-\text{Crash duration}}
ActivityNormal durCrash durNormal costCrash costSlope
A434,0007,0003,000
B875,0008,0003,000
C538,00010,0001,000

Paths at normal duration

  • A-C = 9 weeks
  • B = 8 weeks

Critical activities (on the longest path or paths): A, C; normal duration = 9 weeks; normal direct cost = 17,000 Rs.

Crashing, step by step

StepCrash (by 1 unit)Slope/costDurationDirectIndirectTotal
0--917,00018,00035,000
1C1,000818,00016,00034,000
2B+C4,000722,00014,00036,000

(Rows with several activities show activities crashed together because two paths are critical.)

Result

  • Optimum (minimum-cost) schedule: duration 8 weeks, direct cost 18,000 + indirect 16,000 = 34,000 Rs.
  • Activities crashed at the optimum: C by 1. Durations: A=4, B=8, C=4.
  • Minimum possible duration: 7 weeks, with total cost 36,000 Rs (direct 22,000 + indirect 14,000).

Answer: least cost schedule = 8 weeks (A = 4, B = 8, C = 4 weeks), total cost Rs 34,000 against Rs 35,000 for the normal 9-week schedule. A further week would need A or C together with B (Rs 4,000 > Rs 2,000 saved).