TCTO numerical: optimal crashed result, Rs 300/week

Short answer

Optimal crashed result: 20 weeks, total cost Rs 24,225. Crash B (2 weeks at Rs 150/wk) and C (1 week at Rs 125/wk). Crashing E (Rs 325/wk) is not economical because it exceeds the Rs 300/wk indirect saving.

The details of a project are shown below. If the indirect cost per week is Rs. 300, find the optimal crashed result of the project network.

ActivityImmediate Predecessor(s)Time (Weeks) NormalTime (Weeks) CrashCost (Rs.) NormalCost (Rs.) Crash
A-7418002100
B-9735003800
CB5425002625
DA8540004225
EC9830003325
FB11113000-

Given data and method

Indirect cost = 300 Rs/week. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost.

F cannot be crashed.

Cost slope=Crash cost−Normal costNormal duration−Crash duration\text{Cost slope}=\frac{\text{Crash cost}-\text{Normal cost}}{\text{Normal duration}-\text{Crash duration}}
ActivityNormal durCrash durNormal costCrash costSlope
A741,8002,100100
B973,5003,800150
C542,5002,625125
D854,0004,22575
E983,0003,325325
F11113,0003,000cannot crash

Paths at normal duration

  • A-D = 15 weeks
  • B-C-E = 23 weeks
  • B-F = 20 weeks

Critical activities (on the longest path or paths): B, C, E; normal duration = 23 weeks; normal direct cost = 17,800 Rs.

Crashing, step by step

StepCrash (by 1 unit)Slope/costDurationDirectIndirectTotal
0--2317,8006,90024,700
1C1252217,9256,60024,525
2B1502118,0756,30024,375
3B1502018,2256,00024,225
4E3251918,5505,70024,250

Result

  • Optimum (minimum-cost) schedule: duration 20 weeks, direct cost 18,225 + indirect 6,000 = 24,225 Rs.
  • Activities crashed at the optimum: B by 2, C by 1. Durations: A=7, B=7, C=4, D=8, E=9, F=11.
  • Minimum possible duration: 19 weeks, with total cost 24,250 Rs (direct 18,550 + indirect 5,700).

Answer: optimal crashed result = 20 weeks; minimum total cost = Rs 24,225. (Crashing E to reach 19 weeks costs Rs 325 against a saving of Rs 300, so it is not worthwhile.)