- 2079 Jestha · 8 marks
TCTO numerical with time-cost chart (five activities)
Short answer
Time-cost trade-off crashes the cheapest critical activity per week while saving Rs 1.6 thousand/week indirect. Normal 42 weeks at Rs 93.2k. Optimum: 40 weeks, total cost Rs 93,000. Minimum duration: 28 weeks at Rs 113.8k.
Perform time-cost trade-off based on given information regarding a project comprising five different activities. Also, draw the time-cost trade-off chart. Take time dependent cost per week of Rs 1.6 thousand.
| Activity | Predecessors | Time (Week) Normal | Time (Week) Crash | Cost (Thousand Rs.) Normal | Cost (Thousand Rs.) Crash |
|---|---|---|---|---|---|
| A | - | 26 | 18 | 4 | 20 |
| B | - | 28 | 22 | 5 | 20 |
| C | A | 10 | 5 | 6 | 11 |
| D | A | 4 | 2 | 8 | 11 |
| E | B, D | 12 | 6 | 3 | 14 |
Given data and method
Indirect cost = 1.6 thousand Rs/week. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost. To draw the full trade-off chart, crashing is continued to the minimum possible duration.
| Activity | Normal dur | Crash dur | Normal cost | Crash cost | Slope |
|---|---|---|---|---|---|
| A | 26 | 18 | 4 | 20 | 2 |
| B | 28 | 22 | 5 | 20 | 2.5 |
| C | 10 | 5 | 6 | 11 | 1 |
| D | 4 | 2 | 8 | 11 | 1.5 |
| E | 12 | 6 | 3 | 14 | 1.83 |
Paths at normal duration
- A-C = 36 weeks
- A-D-E = 42 weeks
- B-E = 40 weeks
Critical activities (on the longest path or paths): A, D, E; normal duration = 42 weeks; normal direct cost = 26 thousand Rs.
Crashing, step by step (costs in thousand Rs)
| Step | Crash (by 1 unit) | Slope/cost | Duration | Direct | Indirect | Total |
|---|---|---|---|---|---|---|
| 0 | - | - | 42 | 26.00 | 67.2 | 93.20 |
| 1 | D | 1.5 | 41 | 27.50 | 65.6 | 93.10 |
| 2 | D | 1.5 | 40 | 29.00 | 64.0 | 93.00 |
| 3 | E | 1.83 | 39 | 30.83 | 62.4 | 93.23 |
| 4 | E | 1.83 | 38 | 32.67 | 60.8 | 93.47 |
| 5 | E | 1.83 | 37 | 34.50 | 59.2 | 93.70 |
| 6 | E | 1.83 | 36 | 36.33 | 57.6 | 93.93 |
| 7 | C+E | 2.83 | 35 | 39.17 | 56.0 | 95.17 |
| 8 | C+E | 2.83 | 34 | 42.00 | 54.4 | 96.40 |
| 9 | A+B | 4.5 | 33 | 46.50 | 52.8 | 99.30 |
| 10 | A+B | 4.5 | 32 | 51.00 | 51.2 | 102.20 |
| 11 | A+B | 4.5 | 31 | 55.50 | 49.6 | 105.10 |
| 12 | A+B | 4.5 | 30 | 60.00 | 48.0 | 108.00 |
| 13 | A+B | 4.5 | 29 | 64.50 | 46.4 | 110.90 |
| 14 | A+B | 4.5 | 28 | 69.00 | 44.8 | 113.80 |
(At 40 weeks A-D-E and B-E are both critical and D is fully crashed, so E, common to both, is crashed. At 36 weeks A-C also becomes critical, so C+E is the cheapest cut of all three paths. At 34 weeks D and E are at their crash limits, so A and B must be crashed together. At 28 weeks B and E are both fully crashed, so B-E cannot be shortened further.)
Result
- Optimum (minimum-cost) schedule: duration 40 weeks, direct cost 29 + indirect 64 = 93 thousand Rs.
- Activities crashed at the optimum: D by 2. Durations: A=26, B=28, C=10, D=2, E=12.
- Crashing beyond 40 weeks costs more than the Rs 1.6 thousand/week saved (E slope 1.83 > 1.6), so the total cost rises.
- Minimum possible duration: 28 weeks, with total cost 113.8 thousand Rs (direct 69 + indirect 44.8).
Time-cost trade-off chart (total cost against duration)
Duration Total cost (Rs '000); bar length = cost above 90
(weeks)
42 | ###### 93.20 (normal)
41 | ###### 93.10
40 | ###### 93.00 <-- minimum total cost (optimum)
39 | ###### 93.23
38 | ####### 93.47
37 | ####### 93.70
36 | ######## 93.93
35 | ########## 95.17
34 | ############# 96.40
33 | ################### 99.30
32 | ######################## 102.20
31 | ############################## 105.10
30 | #################################### 108.00
29 | ########################################## 110.90
28 | ################################################ 113.80 (crash)
On graph paper, plot direct cost (falling with duration), indirect cost (a straight line rising at 1.6 per week) and their sum; the total cost curve is lowest at 40 weeks.
Answer: optimum duration 40 weeks; minimum total cost Rs 93.0 thousand (direct 29.0 + indirect 64.0). The shortest possible duration is 28 weeks, at a total cost of Rs 113.8 thousand.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- TCTO numerical: optimal crashed time, Rs 2500/week · Construction Management, chapter 2 · asked 2×
- TCTO numerical: optimal crashed time, Rs 3000/week · Construction Management, chapter 2 · asked 2×
- TCTO numerical: seven activities, Rs 225/day · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 1000/day · Construction Management, chapter 2
- Independent events; computer errors per week · Probability and Statistics, chapter 1 · asked 2×
- Aeroplane angle of attack and take-off power · Fluid Mechanics, chapter 9