TCTO numerical: lowest cost schedule, Rs 400/week

Short answer

Time-cost trade-off: crash B by 2, C by 1, and E by 1 week. Lowest-cost schedule is 22 weeks, total cost Rs 28,050. Further crashing E would cost Rs 250/week vs. Rs 400 saved, so 22 weeks is optimal.

The details of a project are shown below. If the indirect cost per week is Rs. 400, find the lowest cost schedule of the project.

ActivityPredecessor(s)Time (weeks) NormalTime (weeks) CrashCost (Rs) NormalCost (Rs) Crash
A-8520002200
B-10838004000
CB6527002600
DA9641004300
EC10931003350
FB121231003100

Given data and method

Indirect cost = 400 Rs/week. Time-cost trade-off (TCTO) crashes the activities on the critical path, one time-unit at a time, always choosing the cheapest cost slope, as long as the saving in indirect cost is more than the extra direct cost.

Assumption: for C the table shows crash cost (2,600) lower than normal cost (2,700). The two values are taken as interchanged, so normal cost = Rs 2,600 and crash cost = Rs 2,700. F cannot be crashed.

Cost slope=Crash cost−Normal costNormal duration−Crash duration\text{Cost slope}=\frac{\text{Crash cost}-\text{Normal cost}}{\text{Normal duration}-\text{Crash duration}}
ActivityNormal durCrash durNormal costCrash costSlope
A852,0002,20066.67
B1083,8004,000100
C652,6002,700100
D964,1004,30066.67
E1093,1003,350250
F12123,1003,100cannot crash

Paths at normal duration

  • A-D = 17 weeks
  • B-C-E = 26 weeks
  • B-F = 22 weeks

Critical activities (on the longest path or paths): B, C, E; normal duration = 26 weeks; normal direct cost = 18,700 Rs.

Crashing, step by step

StepCrash (by 1 unit)Slope/costDurationDirectIndirectTotal
0--2618,70010,40029,100
1B1002518,80010,00028,800
2B1002418,9009,60028,500
3C1002319,0009,20028,200
4E2502219,2508,80028,050

Result

  • Optimum (minimum-cost) schedule: duration 22 weeks, direct cost 19,250 + indirect 8,800 = 28,050 Rs.
  • Activities crashed at the optimum: B by 2, C by 1, E by 1. Durations: A=8, B=8, C=5, D=9, E=9, F=12.
  • Minimum possible duration: 22 weeks, with total cost 28,050 Rs (direct 19,250 + indirect 8,800).

Answer: lowest-cost schedule = 22 weeks, total cost Rs 28,050.