EVA; plantation 50 units, 4 weeks, Rs 200
Short answer
BAC Rs 10,000; at week 3, PV = (3/4)×BAC = Rs 7,500, EV = 60% × BAC = Rs 6,000, AC = 30 units × Rs 300 = Rs 9,000. SV = –Rs 1,500, CV = –Rs 3,000, SPI = 0.80, CPI = 0.667, EAC = Rs 15,000. Project behind schedule and over budget.
50 units of plantation have to be done in a 4 week period. The per unit cost of plantation is estimated as Rs 200, of which progress monitoring was done 3 weeks after the work was started. Only 60% work was found completed and the account record showed that the actual expenditure for plantation per unit was Rs 300. Perform EVA and comment on the work.
Data
- Work = 50 units at Rs 200/unit in 4 weeks, so BAC = 50 x 200 = Rs 10,000
- Monitoring after 3 weeks: progress = 60 % (30 units); actual rate = Rs 300/unit
- Planned progress after 3 weeks = 3/4 = 75 % (uniform progress assumed)
Calculation
Comment
- Schedule: SV is negative and SPI = 0.80, so the project is behind schedule. Only 80 % of the planned work is done. At this rate the work will take about 5 weeks instead of the planned 4 weeks (1 week late).
- Cost: CV is negative and CPI = 0.667, so the project is over budget. Each Rs 1 spent gives only Rs 0.67 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 15,000 against the budget of Rs 10,000 (variance at completion = -Rs 5,000).
Answer: SV = -Rs 1,500, CV = -Rs 3,000, SPI = 0.80, CPI = 0.667; the project is behind schedule and over budget.
Both schedule and cost are unfavourable. Controlling statements: increase productive resources (labour, equipment, extra shifts), improve supervision and productivity, review rates and wastage, re-sequence activities, and revise the plan or budget with the client's approval.
The work is both late and costly: only 60 % is done against 75 % planned, and the unit cost is 50 % above the estimate (Rs 300 against Rs 200).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA; plantation 50 units, 3 weeks, Rs 2500 · Project Engineering, chapter 4 · asked 2×
- EVA; 60 days, 25% work, 50% budget spent · Project Engineering, chapter 4
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4