EVA; 60 days, 25% work, 50% budget spent
Short answer
PV=Rs 10,000, EV=Rs 5,000, AC=Rs 10,000; SPI=CPI=0.50, project behind schedule and over budget, with forecast cost Rs 40,000 (double budget).
A project is undertaken where the work has to be completed within 60 days with a budget of Rs 20,000. The cost breakdown per month is Rs 10,000. The work scheduled in each month is half of the total work to be completed. According to the progress reports, at the end of the first month, only 25% of the total work has been completed and 50% of the total budget has been spent. Also, for the completion of 25% work, the actual cost incurred is 50% of the total budgeted cost. Perform EVA and comment on performance.
Given data
BAC = Rs 20,000; duration = 60 days (2 months); cost breakdown Rs 10,000 per month; half of the work is scheduled in each month. At the end of month 1: work done = 25 %; spent = 50 % of the budget.
Calculation
Comment
- Schedule: SV = -5,000 and SPI = 0.50, so the project is behind schedule; only 50 % of the planned work is done. If the same rate continues, the duration becomes 120.0 days against 60 days planned.
- Cost: CV = -5,000 and CPI = 0.50, so the project is over budget; each rupee spent has earned Rs 0.50 of work.
- Forecast: EAC = Rs 40,000 against BAC = Rs 20,000, i.e. a final overrun of Rs 20,000.
- Action: find the causes (low productivity, idle equipment, material delay, wastage), add resources or shifts on critical activities, tighten supervision and cost control, and revise the plan with the client.
Answer: SV = Rs -5,000, CV = Rs -5,000, SPI = 0.50, CPI = 0.50; behind schedule and over budget; EAC = Rs 40,000, double the budget.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- EVA; 10 days, 100,000, day 6, spi and cpi · Project Engineering, chapter 4
- EVA and S-curve; Rs 30,00,000, 24 months · Project Engineering, chapter 4