Chapter 4 · 7 hours
Project Implementation and Controlling
IOE past exam questions
Past questions and answers
50 questions set from this chapter, 10 of them more than once; 4 are most repeated (set, or a close variant set, in 3 or more exams). Most repeated first.
- Most repeated · 4 of 26 exams
- Asked 4 times
- 2074 Asoj · 1+5 marks
- 2071 Chaitra · 2+4 marks
- 2070 Chaitra (old course) · 4+4 marks
- 2070 Asar · 3+4 marks
Define monitoring, evaluation and controlling. Explain the project control cycle (with a suitable example).
Answer
Monitoring
Project monitoring is the continuous collection, recording and reporting of information on the actual progress of a project (physical work, time, cost, quality, resource use) during implementation, and its comparison with the plan, so that deviations are known.
Evaluation
Project evaluation is the periodic, systematic assessment of a project (during, at the end, or after completion) to judge its relevance, efficiency, effectiveness, impact and sustainability against the objectives, and to draw lessons for decisions and for future projects.
Controlling
Project control is the process of comparing actual performance with the plan, analysing the variances and taking corrective action (or revising the plan) so that the project is completed within the planned time, cost and quality.
Project control cycle
The control cycle is a closed loop that is repeated at every review period.
+--------------+ +------------------+
| 1 Plan: | | 2 Implement and |
| baseline of |---->| measure actual |
| time, cost, | | progress |
| quality | +--------+---------+
+------^-------+ |
| v
+------+-------+ +------------------+
| 5 Take | | 3 Compare actual |
| corrective |<----| with plan and |
| action / | | find variance |
| re-plan | +--------+---------+
+------^-------+ |
| v
| +------------------+
+-------------| 4 Analyse causes |
| and decide |
+------------------+
- Set the baseline plan: approved scope, schedule, budget and quality standards.
- Measure progress: record actual work done, cost spent and quality results through site reports, measurement books and inspections.
- Compare actual with planned values and find the variance (schedule, cost, quality).
- Analyse the variance: find causes (late material, low productivity, design change, weather) and forecast the effect on completion date and final cost.
- Take corrective action: add resources, work overtime, re-sequence activities, change method, or revise the plan with approval.
- Report and update: inform management, update the plan, and repeat the cycle at the next review period (feedback).
Example (road project): 10 km of road is to be built in 100 days (0.1 km per day). At day 50 the progress report shows only 4 km finished (planned 5 km). Variance = 1 km behind (20 %). Analysis finds that the roller was idle for 6 days and rain stopped work for 4 days. Corrective action: hire one more roller, add a second shift and use the float of side-drain work to release labour. At the next review (day 60) the progress is compared again.
- Most repeated · 4 of 26 exams
- Asked 4 times
- 2073 Shrawan · 5 marks
- 2068 Baisakh (old course) · 8 marks
- 2065 Shrawan (old course) · 4 marks
- 2082 Baisakh · 2 marks
Write a short note on Project Management Information System (PMIS).
Answer
Project Management Information System (PMIS) is an organised system (manual or computer-based) of people, procedures, data and tools that collects, stores, processes and reports information needed by project managers to plan, monitor and control a project. It gives the right information, to the right person, at the right time, in the right form.
Components
- Data input: site reports, measurement books, labour and equipment logs, material receipts, bills, test results, drawings.
- Database: schedules, budget, cost records, resource and contract data, risk register.
- Processing tools: spreadsheets, scheduling software (MS Project, Primavera), cost and EVA software.
- Output reports: progress, variance, cost, resource, quality and exception reports, dashboards.
- People and procedures: reporting formats, frequency, responsibilities.
Functions
- Planning and scheduling support; progress and cost tracking.
- Variance and trend analysis; forecasting of final cost and date.
- Early warning of problems (exception reporting).
- Document control and communication among client, consultant and contractor.
- Support for decisions, claims, and audit.
Site data -> Collect -> Store (database) -> Process
|
Decision <- Reports/Dashboard <- Analyse <----+
|
+--> Corrective action --> Site
Benefits
- Faster and better decisions with accurate, current data.
- Better coordination and communication.
- Early detection of delay and overrun.
- Less paperwork; reliable records for evaluation and claims.
Example
On a highway project the site engineer enters daily quantities of earthwork and bitumen, the store keeper enters material stock, and the accountant enters bills. The PMIS prints a weekly report showing physical progress (% complete), cost to date, and variance against the baseline, so that the manager can see which section is behind and act the same week.
- Most repeated · 3 of 26 exams
- Asked 3 times
- 2081 Bhadra · 2+3 marks
- 2076 Chaitra · 6 marks
- 2075 Chaitra · 2+4 marks
What is project control? Write down the steps of the project control cycle. As a project manager, how will you control a project during the implementation phase with the aid of the project control cycle?
Answer
Project control
Project control is the process of comparing actual performance with the plan, analysing the variances and taking corrective action (or revising the plan) so that the project is completed within the planned time, cost and quality. Control keeps the project on the planned path of time, cost and quality.
Steps of the project control cycle
+--------------+ +------------------+
| 1 Plan: | | 2 Implement and |
| baseline of |---->| measure actual |
| time, cost, | | progress |
| quality | +--------+---------+
+------^-------+ |
| v
+------+-------+ +------------------+
| 5 Take | | 3 Compare actual |
| corrective |<----| with plan and |
| action / | | find variance |
| re-plan | +--------+---------+
+------^-------+ |
| v
| +------------------+
+-------------| 4 Analyse causes |
| and decide |
+------------------+
- Set the baseline plan: approved scope, schedule, budget and quality standards.
- Measure progress: record actual work done, cost spent and quality results through site reports, measurement books and inspections.
- Compare actual with planned values and find the variance (schedule, cost, quality).
- Analyse the variance: find causes (late material, low productivity, design change, weather) and forecast the effect on completion date and final cost.
- Take corrective action: add resources, work overtime, re-sequence activities, change method, or revise the plan with approval.
- Report and update: inform management, update the plan, and repeat the cycle at the next review period (feedback).
Controlling the project in the implementation phase
As project manager I would apply the cycle as follows.
- Baseline: fix the approved schedule, budget and quality plan; communicate targets to site engineers and contractors.
- Measure: collect daily and weekly reports of work done, labour, machines and materials; check the quality by tests and inspections; record the bills.
- Compare: hold weekly progress meetings; compare actual with planned physical progress and cost (S-curve, bar chart, earned value).
- Analyse: find the cause of each delay or overrun and its effect on the critical path and the final cost.
- Act: add resources to critical activities, re-sequence work, give incentives, change method, resolve design and payment problems, or get approved changes (variation orders).
- Update and report: revise the schedule, inform the client, and repeat the cycle every week or month.
Close control of critical activities, quick decisions and good records keep the project within time and budget.
- Most repeated · 3 of 26 exams
- Asked 3 times
- 2072 Chaitra · 3+3 marks
- 2076 Asoj · 3+5 marks
- 2081 Bhadra · 4+3 marks
Define monitoring and control. Why is project monitoring and controlling difficult in Nepal? (Why is continuous monitoring and control required in a project?)
Answer
Monitoring and control
Project monitoring is the continuous collection, recording and reporting of information on the actual progress of a project (physical work, time, cost, quality, resource use) during implementation, and its comparison with the plan, so that deviations are known.
Project control is the process of comparing actual performance with the plan, analysing the variances and taking corrective action (or revising the plan) so that the project is completed within the planned time, cost and quality.
Why monitoring and control are difficult in Nepal
- Weak planning and unrealistic estimates, so the baseline itself is poor.
- Poor data and record keeping; no reliable PMIS, and reports are late or inaccurate.
- Delay in budget release and payment, and the fiscal year system (work rush in the last months).
- Political instability and frequent change of ministers and project staff; weak ownership.
- Difficult geography and weather: remote hilly sites, landslides and monsoon, blockages of roads, so site visits and supply are hard.
- Land acquisition, compensation, tree cutting and forest clearance problems.
- Weak contractor capacity (small firms, shortage of skilled labour and equipment) and delay in procurement and approvals.
- Lack of trained managers and monitoring tools; insufficient budget for monitoring.
- Local strikes, bandhs, and law and order problems; weak enforcement of contract provisions.
- Frequent design changes and variation orders, and corruption or pressure that weaken control.
Why continuous monitoring and control are required
- To know actual progress and detect delay or cost overrun early, while correction is cheap.
- To ensure the work meets the quality and safety standards.
- To use resources properly and prevent waste and leakage.
- To get information for timely decisions and for payment and claims.
- To make the staff and contractors accountable.
- Conditions (price, weather, funds) change constantly, so the plan must be updated.
- Asked 2 times
- 2075 Asoj · 8 marks
- 2074 Chaitra · 4+4 marks
Explain the project control cycle and write the factors to be considered during quality control of a project.
Answer
Project control cycle
The project control cycle is the repeated process of planning, measuring, comparing, analysing and correcting that keeps the project on its time, cost and quality targets.
+--------------+ +------------------+
| 1 Plan: | | 2 Implement and |
| baseline of |---->| measure actual |
| time, cost, | | progress |
| quality | +--------+---------+
+------^-------+ |
| v
+------+-------+ +------------------+
| 5 Take | | 3 Compare actual |
| corrective |<----| with plan and |
| action / | | find variance |
| re-plan | +--------+---------+
+------^-------+ |
| v
| +------------------+
+-------------| 4 Analyse causes |
| and decide |
+------------------+
- Set the baseline plan: approved scope, schedule, budget and quality standards.
- Measure progress: record actual work done, cost spent and quality results through site reports, measurement books and inspections.
- Compare actual with planned values and find the variance (schedule, cost, quality).
- Analyse the variance: find causes (late material, low productivity, design change, weather) and forecast the effect on completion date and final cost.
- Take corrective action: add resources, work overtime, re-sequence activities, change method, or revise the plan with approval.
- Report and update: inform management, update the plan, and repeat the cycle at the next review period (feedback).
Factors to be considered in quality control
- Specifications and standards: clear drawings, specifications and codes (Nepal Building Code, IS, NS) with acceptance limits.
- Quality of materials: testing of cement, steel, aggregate, bricks, bitumen before use; approved sources.
- Workmanship and skill: trained labour and supervisors; method statements.
- Equipment and tools: proper, calibrated and well-maintained machines and testing instruments.
- Inspection and testing: a plan of tests (cube test, density test, slump), frequency and sampling.
- Supervision and organisation: clear responsibility; qualified quality engineer.
- Documentation: records of tests, approvals, non-conformance reports.
- Environment and site conditions: weather, curing, storage of material.
- Time and cost pressure: a rush or low rates reduce quality; quality must be planned in the budget and schedule.
- Corrective and preventive action: rework or rejection procedure and feedback to avoid repeat defects.
- Asked 2 times
- 2070 Chaitra (old course) · 4 marks
- 2068 Baisakh (old course) · 4 marks
Write a short note on the feedback control system.
Answer
A feedback control system is a closed-loop system in which the output (actual performance) is measured and fed back to be compared with the desired standard (plan). If a difference (error) exists, a corrective action is taken to bring the output back to the standard. The aim is self-regulation.
Elements
- Standard / plan (set point): target for time, cost, quality.
- Process: the project work.
- Sensor / measurement: records actual progress, cost and quality.
- Comparator: compares actual with standard and finds the variance.
- Decision and corrective action (effector): the manager adjusts input (resources, method) to remove the variance.
Plan / Standard (set point)
|
v
Input --> [ Process: project work ] --> Output
^ |
| v
[ Corrective <---- [ Sensor: measure
action ] actual ]
^ |
| v
+------ [ Comparator: ] <--+
actual vs plan
Example: budgeted cost of a building at 50 % progress is Rs 40 lakh but actual cost is Rs 46 lakh. The report (feedback) shows an overrun of Rs 6 lakh. The manager reduces wastage, renegotiates rates and re-plans the remaining work to bring the cost back to the budget.
Features: continuous, automatic or semi-automatic, corrects after the deviation has occurred (so there is some lag), and works best with timely information.
- Asked 2 times
- 2072 Chaitra · 1+5 marks
- 2079 Baisakh · 6 marks
What is EVA? A construction work had to be completed in 10 days with 50 labour days at Rs 1000 per day, i.e. with a total cost of Rs 50,000. At the end of the third day, only 25% work was completed with the use of 18 labour days at Rs 800 per day. Perform earned value analysis and comment on the performance.
Answer
Earned Value Analysis (EVA)
Earned Value Analysis is a method of measuring project performance by comparing three quantities: the work planned (PV), the value of the work actually done (EV) and the actual cost (AC). It gives schedule and cost variances and indices in one common unit (money), and forecasts the final cost and time.
| Term | Other name | Meaning |
|---|---|---|
| BAC | Budget at completion | Total approved budget of the project |
| PV | BCWS (planned value) | Budgeted cost of the work scheduled up to the date |
| EV | BCWP (earned value) | Budgeted cost of the work actually completed = % complete x BAC |
| AC | ACWP (actual cost) | Actual money spent for the work done up to the date |
Given data
- Budget: 50 labour days x Rs 1,000 = Rs 50,000 for 10 days (assumed uniform, 5 labour days per day).
- At the end of day 3: work done = 25 %; labour used = 18 days at Rs 800 per day.
Calculation
| Parameter | Value |
|---|---|
| PV | Rs 15,000 |
| EV | Rs 12,500 |
| AC | Rs 14,400 |
| SV | Rs -2,500 |
| CV | Rs -1,900 |
| SPI | 0.83 |
| CPI | 0.87 |
| EAC | Rs 57,600 |
Comment on performance
- SV is negative and SPI = 0.83 < 1: the work is behind schedule; only 83 % of the planned work is done. At this rate the job takes 12 days instead of 10.
- CV is negative and CPI = 0.87 < 1: the job is over budget. Although the rate per labour day is lower (Rs 800 against Rs 1,000), more labour days (18 against 15) were used for less work, so productivity is poor.
- The expected final cost is Rs 57,600, an overrun of Rs 7,600.
- Corrective action: improve productivity (better supervision, tools, work method), plan materials, and rearrange crews to catch up the delay.
Answer: SV = Rs -2,500, CV = Rs -1,900, SPI = 0.83, CPI = 0.87; the work is behind schedule and over budget.
- Asked 2 times
- 2081 Baisakh · 2+6 marks
- 2080 Baisakh · 8 marks
Differentiate between quality assurance and quality control. Explain the different types of cost associated with quality.
Answer
Quality assurance and quality control
| Basis | Quality assurance (QA) | Quality control (QC) |
|---|---|---|
| Meaning | Planned, systematic activities that give confidence that quality requirements will be met | Operational techniques that check the product against standards and find defects |
| Nature | Process oriented | Product oriented |
| Aim | Prevent defects | Detect and correct defects |
| Time | Before and during the work | During and after the work |
| Activities | Quality plan, procedures, audits, training | Inspection, testing, sampling, control charts |
| Responsibility | Whole team and management | Quality control staff and inspectors |
| Example | Setting procedure for concrete mixing | Testing concrete cubes |
Costs associated with quality (cost of quality)
The total cost of quality has two groups: the cost of conformance (money spent to achieve good quality) and the cost of non-conformance (money lost due to poor quality).
- Prevention cost (conformance): spent to avoid defects - quality planning, training, better design, procedures, supplier selection.
- Appraisal cost (conformance): spent to find defects - inspection, testing, laboratory, calibration, audits.
- Internal failure cost (non-conformance): defects found before delivery - rework, scrap, re-testing, delay.
- External failure cost (non-conformance): defects found after delivery - repair under warranty, claims, litigation, loss of reputation, compensation.
Total cost of quality
|-- Cost of conformance
| |-- Prevention
| `-- Appraisal
`-- Cost of non-conformance
|-- Internal failure
`-- External failure
Spending more on prevention and appraisal reduces failure costs; the best level is where the total is lowest.
- Asked 2 times
- 2082 Baisakh · 1+5 marks
- 2070 Chaitra · 6 marks
Define quality. Justify the statement "quality costs more but lack of quality costs even more", explaining the total quality cost included to achieve good quality.
Answer
Quality
Quality is the degree to which the project deliverable satisfies the specified requirements and the needs of the client; in simple words "fitness for use" or "conformance to requirements".
Quality costs more, but lack of quality costs even more
Good quality needs money for planning, training, better materials, inspection and testing. But poor quality is far more expensive: rework, rejection, delay, repair, claims, loss of goodwill, and, in construction, failure and loss of life. The total cost of quality is:
| Cost | Examples |
|---|---|
| Prevention | Quality plan, training, procedures, skilled supervision |
| Appraisal | Inspection, material and lab tests, audits |
| Internal failure | Rework of faulty concrete, scrap, re-testing, delay |
| External failure | Repair after handover, warranty, compensation, legal cost |
Illustration (Rs thousand, for one slab-casting package):
| Spending on prevention and appraisal | Failure cost (rework, repair) | Total cost of quality |
|---|---|---|
| 10 | 80 | 90 |
| 20 | 40 | 60 |
| 30 | 20 | 50 |
| 40 | 15 | 55 |
As the money spent on prevention and appraisal increases, failure cost falls much faster, so the total cost falls up to an optimum point. For example, spending Rs 20,000 on testing and supervision of a slab can avoid demolition and recasting costing lakhs. Hence the statement is justified: the cost of lack of quality (failure costs) is greater than the cost of achieving quality.
- Asked 2 times
- 2081 Baisakh · 3 marks
- 2078 Bhadra · 3 marks
Write a short note on project quality control and its techniques.
Answer
Project quality control
Quality control (QC) is the set of operational activities used during the project to check that the work and materials meet the specified standards, to find defects early and to correct their causes. It includes inspection, testing, measurement, and taking action on non-conformance, so that the product is acceptable to the client.
Main steps: set standards and acceptance limits, take samples and test, compare with standards, correct or reject, and record.
Techniques of quality control
- Inspection and testing: visual checks, measurement and laboratory/field tests (cube strength, slump, field density, bitumen content).
- Statistical sampling: a small sample is tested to judge the whole lot, with acceptance limits.
- Control charts: plot test results with upper and lower control limits over time to show whether the process is under control.
- Pareto chart: bar chart arranging the causes of defects in order; shows the vital few causes (80/20 rule).
- Cause-and-effect (fishbone) diagram: finds root causes of a defect under headings such as man, machine, material, method.
- Histogram: shows the distribution of measured values.
- Scatter diagram: shows the relation between two variables (water-cement ratio and strength).
- Check sheet and flow chart: record defects and show process steps.
- Checklists and quality audits of work stages.
- 2076 Asoj · 6 marks
50 units of plantation have to be done in 3 weeks. The per unit cost of plantation is estimated as Rs 2500, of which progress monitoring was done 1 week after the work started. Only 20 units of plantation were found completed and the account record showed that the actual expenditure per unit was Rs 2500. Perform EVA and comment on the performance.
Similar questions: EVA; plantation 50 units, 4 weeks, Rs 200 (2074 Chaitra)
Answer
Earned value analysis (EVA) compares planned value, earned value and actual cost to measure schedule and cost performance. Planned progress is taken as uniform over the 3 weeks.
Data
- Total work = 50 units, rate = Rs 2,500/unit, duration = 3 weeks
- Budget at completion, BAC = 50 x 2,500 = Rs 125,000
- Monitoring at end of week 1: completed = 20 units, actual cost = 20 x 2,500 = Rs 50,000
Calculation
Comment
- Schedule: SV is positive and SPI = 1.200, so the project is ahead of schedule. The work done is 120.0% of the planned work. At this rate the duration becomes about 2.50 against the planned 3 (a change of -0.50).
- Cost: CV is zero and CPI = 1.000, so the project is on budget. Each Rs 1 spent gives Rs 1.00 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 125,000.00 against the budget of Rs 125,000.00 (variance at completion 0.00).
Answer: SV = 8,333.33, CV = 0.00, SPI = 1.200, CPI = 1.000; the project is ahead of schedule and on budget.
Both schedule and cost are favourable. Controlling statements: continue the present method, maintain productivity, keep records, and watch for later risks.
Planned work in week 1 was 16.67 units, but 20 units were finished, so the project is faster than planned and the unit cost is exactly as budgeted.
- 2074 Chaitra · 8 marks
50 units of plantation have to be done in a 4 week period. The per unit cost of plantation is estimated as Rs 200, of which progress monitoring was done 3 weeks after the work was started. Only 60% work was found completed and the account record showed that the actual expenditure for plantation per unit was Rs 300. Perform EVA and comment on the work.
Similar questions: EVA; plantation 50 units, 3 weeks, Rs 2500 (2076 Asoj)
Answer
Data
- Work = 50 units at Rs 200/unit in 4 weeks, so BAC = 50 x 200 = Rs 10,000
- Monitoring after 3 weeks: progress = 60% (30 units); actual rate = Rs 300/unit
- Planned progress after 3 weeks = 3/4 = 75% (uniform progress assumed)
Calculation
Comment
- Schedule: SV is negative and SPI = 0.800, so the project is behind schedule. Only 80.0% of the planned work is done. At this rate the duration becomes about 5.00 against the planned 4 (a change of +1.00).
- Cost: CV is negative and CPI = 0.667, so the project is over budget. Each Rs 1 spent gives Rs 0.67 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 15,000.00 against the budget of Rs 10,000.00 (variance at completion -5,000.00).
Answer: SV = -1,500.00, CV = -3,000.00, SPI = 0.800, CPI = 0.667; the project is behind schedule and over budget.
Both schedule and cost are unfavourable. Controlling statements: increase productive resources (labour, equipment, extra shifts), improve supervision and productivity, review rates and wastage, re-sequence activities and revise the plan or budget with the client's approval.
The project is late and also costly, because only 60% is done against 75% planned and the unit cost is 50% above the estimate (Rs 300 against Rs 200).
- 2073 Shrawan · 5 marks
What is the difference between evaluation and controlling? Discuss the elements of project control.
Answer
Difference between evaluation and controlling
| Basis | Evaluation | Controlling |
|---|---|---|
| Meaning | Judging the worth and results of the project | Regulating the work to keep it on plan |
| Time | Periodic; mainly end or mid-term | Continuous during implementation |
| Concern | Objectives achieved, impact, lessons | Time, cost, quality, scope variances |
| Result | Recommendations and judgement | Corrective actions and decisions |
| Direction | Looks back (and forward for new projects) | Acts on the present to correct the future |
Elements of project control
- Plan / standard (baseline): approved scope, schedule, budget and quality standards against which performance is judged.
- Measurement of performance: collecting actual data of progress, cost, quality and resource use (monitoring).
- Comparison and variance analysis: finding the difference between actual and planned and its cause and effect on the project.
- Corrective action: decisions to bring the project back to plan (more resources, re-sequencing, change of method) or to revise the plan.
- Information and reporting (feedback): timely reports to the manager and the client; the result of the action is fed back to the next cycle.
- Organisation and authority: clear responsibility, authority and people for control at each level.
Plan -> Measure -> Compare -> Act -> Feedback
^ |
+------------------------------------+
- 2072 Kartik
Discuss "monitoring, evaluation and control" is a must to succeed in a project. Explain the project management information system and justify "the right information at the right time reduces the risk of wrong decision".
Answer
Why monitoring, evaluation and control are a must
A project is a one-time, costly and uncertain job with limited time and money. Plans are made on assumptions, but conditions change during implementation. Without monitoring and control the project drifts.
- Monitoring shows the actual progress, cost and quality continuously, so that delay or overspend is seen early.
- Control compares the actual with the plan and takes corrective action so that time, cost and quality targets are achieved.
- Evaluation judges whether the objectives are being achieved and whether the project is still relevant and efficient, and gives lessons for decisions and future projects.
- Together they give accountability, avoid waste and loss, reduce risk, satisfy the client and donor, and improve the chance of success.
+--------------+ +------------------+
| 1 Plan: | | 2 Implement and |
| baseline of |---->| measure actual |
| time, cost, | | progress |
| quality | +--------+---------+
+------^-------+ |
| v
+------+-------+ +------------------+
| 5 Take | | 3 Compare actual |
| corrective |<----| with plan and |
| action / | | find variance |
| re-plan | +--------+---------+
+------^-------+ |
| v
| +------------------+
+-------------| 4 Analyse causes |
| and decide |
+------------------+
Project Management Information System (PMIS)
Project Management Information System (PMIS) is an organised system (manual or computer-based) of people, procedures, data and tools that collects, stores, processes and reports information needed by project managers to plan, monitor and control a project. It gives the right information, to the right person, at the right time, in the right form.
Components
- Data input: site reports, measurement books, labour and equipment logs, material receipts, bills, test results, drawings.
- Database: schedules, budget, cost records, resource and contract data, risk register.
- Processing tools: spreadsheets, scheduling software (MS Project, Primavera), cost and EVA software.
- Output reports: progress, variance, cost, resource, quality and exception reports, dashboards.
- People and procedures: reporting formats, frequency, responsibilities.
Functions
- Planning and scheduling support; progress and cost tracking.
- Variance and trend analysis; forecasting of final cost and date.
- Early warning of problems (exception reporting).
- Document control and communication among client, consultant and contractor.
- Support for decisions, claims, and audit.
Site data -> Collect -> Store (database) -> Process
|
Decision <- Reports/Dashboard <- Analyse <----+
|
+--> Corrective action --> Site
Benefits
- Faster and better decisions with accurate, current data.
- Better coordination and communication.
- Early detection of delay and overrun.
- Less paperwork; reliable records for evaluation and claims.
"The right information at the right time reduces the risk of wrong decisions"
A decision is as good as the information behind it. If the manager learns of a delay or overspend only after the project is finished, it is too late to correct. Timely and accurate information from the PMIS means that:
- a 2-week delay is seen in the weekly report, and extra resources are applied to a critical activity while the delay is still small;
- cost variance is known at 30 % progress, not at 90 %, so scope or method can still be changed;
- the choice between alternatives (overtime or new equipment) is made on facts, not guesses;
- risk is lowered because uncertain assumptions are replaced by measured data. Late, wrong or excessive information, on the other hand, causes wrong decisions, delay and loss.
- 2080 Bhadra · 2+4 marks
Differentiate between monitoring and evaluation. What are the different tools of project quality control?
Answer
Difference between monitoring and evaluation
| Basis | Monitoring | Evaluation |
|---|---|---|
| Meaning | Continuous tracking of progress against plan | Periodic assessment of results and value |
| Time | Throughout implementation (daily, weekly, monthly) | Mid-term, end of project, post-project |
| Focus | Inputs, activities, outputs (are we doing the work right?) | Outcomes, impact, relevance (did we do the right work?) |
| Done by | Project staff and managers (internal) | Often external or independent team |
| Purpose | Early warning and day-to-day correction | Judgement, learning, future decisions |
| Output | Progress reports, variance reports | Evaluation report with recommendations |
| Frequency | Frequent | Occasional |
Tools of project quality control
- Inspection and testing of materials and work (cube test, slump, field density, bitumen test).
- Check sheet: a form to record the number and type of defects.
- Histogram: shows the frequency distribution of measured values.
- Pareto chart: ranks causes of defects, showing the vital few (80/20 rule).
- Cause-and-effect (fishbone) diagram: traces the root cause of a defect under man, machine, material and method.
- Scatter diagram: shows the relation between two variables, e.g. water-cement ratio and strength.
- Control chart: plots results against upper and lower control limits to show whether the process is stable.
- Flow chart of the process and statistical sampling plans.
- 2068 Baisakh (old course) · 8 marks
Differentiate monitoring and controlling by explaining the project control cycle. Explain the concept of Earned Value Analysis used for controlling cost.
Answer
Monitoring and controlling
| Basis | Monitoring | Controlling |
|---|---|---|
| Nature | Observing, measuring and reporting progress | Acting on the findings to bring the project back to plan |
| Question | What is happening? | What should be done about it? |
| Output | Progress and variance reports | Corrective action, revised plan |
| Stage in cycle | Measure and compare | Analyse, decide and act |
| Authority | Information gathering, any level | Decision of project manager/management |
Project control cycle
+--------------+ +------------------+
| 1 Plan: | | 2 Implement and |
| baseline of |---->| measure actual |
| time, cost, | | progress |
| quality | +--------+---------+
+------^-------+ |
| v
+------+-------+ +------------------+
| 5 Take | | 3 Compare actual |
| corrective |<----| with plan and |
| action / | | find variance |
| re-plan | +--------+---------+
+------^-------+ |
| v
| +------------------+
+-------------| 4 Analyse causes |
| and decide |
+------------------+
Monitoring covers steps 2 and 3 (measure and compare); controlling covers steps 4 and 5 (analyse and act), and the cycle is repeated at every review.
Earned Value Analysis (EVA) for cost control
EVA compares the planned value (PV), the earned value (EV) and the actual cost (AC) at a status date, so that cost and schedule performance are seen in one common unit (money).
| Term | Other name | Meaning |
|---|---|---|
| BAC | Budget at completion | Total approved budget of the project |
| PV | BCWS (planned value) | Budgeted cost of the work scheduled up to the date |
| EV | BCWP (earned value) | Budgeted cost of the work actually completed = % complete x BAC |
| AC | ACWP (actual cost) | Actual money spent for the work done up to the date |
| Indicator | Value | Meaning |
|---|---|---|
| SV, SPI | SV > 0, SPI > 1 | Ahead of schedule |
| SV = 0, SPI = 1 | On schedule | |
| SV < 0, SPI < 1 | Behind schedule | |
| CV, CPI | CV > 0, CPI > 1 | Under budget (cost efficient) |
| CV = 0, CPI = 1 | On budget | |
| CV < 0, CPI < 1 | Over budget (cost inefficient) |
Example: BAC = Rs 10 lakh; at the status date PV = Rs 5 lakh, EV = Rs 4 lakh, AC = Rs 6 lakh. lakh, lakh, , , lakh. The project is behind schedule and over budget, so corrective action is needed at once.
- 2066 Bhadra (old course) · 4+6 marks
Define monitoring, evaluation and control. Explain briefly quality control, cost control and schedule control in the project.
Answer
Definitions
Project monitoring is the continuous collection, recording and reporting of information on the actual progress of a project (physical work, time, cost, quality, resource use) during implementation, and its comparison with the plan, so that deviations are known.
Project evaluation is the periodic, systematic assessment of a project (during, at the end, or after completion) to judge its relevance, efficiency, effectiveness, impact and sustainability against the objectives, and to draw lessons for decisions and for future projects.
Project control is the process of comparing actual performance with the plan, analysing the variances and taking corrective action (or revising the plan) so that the project is completed within the planned time, cost and quality.
Quality control
Checking that materials and work meet the specifications and standards, through inspection, sampling and testing (cube test, density test), use of control charts and Pareto/fishbone analysis, and correcting or rejecting defective work. It is done by a quality engineer with a test plan and records.
Cost control
Keeping the actual cost within the approved budget. The budget is set by WBS/cost codes, the actual cost is recorded, the variance is found (actual against budget, or by earned value: CV and CPI), the final cost is forecast (EAC) and corrective actions are taken (reduce wastage, improve productivity, control variations and procurement).
Schedule control
Keeping the work on the planned time table. Actual progress is compared with the baseline (bar chart, S-curve, SV and SPI); the cause of delay and its effect on the critical path are found; the corrective action is taken (more resources, overtime, re-sequencing, fast-tracking, crashing) and the schedule is updated.
- 2078 Bhadra · 6 marks
Define project schedule control. Explain the schedule control cycle. How can a project be kept on schedule? Explain.
Answer
Project schedule control
Schedule control is the process of monitoring the actual progress of the project, comparing it with the baseline schedule, finding the causes of any delay and taking corrective action (or approved changes) so that the project is completed on the planned date.
Schedule control cycle
+-----------------+ +------------------+
| Baseline |-->| Record actual |
| schedule | | progress |
+--------^--------+ +---------+--------+
| v
+--------+--------+ +------------------+
| Update schedule | | Compare with plan|
| and report | | (SV, SPI, float) |
+--------^--------+ +---------+--------+
| v
+--------+--------+ +------------------+
| Corrective |<--| Analyse delay, |
| action | | critical path |
+-----------------+ +------------------+
- Baseline schedule: approved bar chart or network with milestones.
- Record actual progress: percent complete and actual start/finish of each activity.
- Compare with plan: bar chart, S-curve, schedule variance , , float used.
- Analyse: which activities are delayed, whether they are critical, and the effect on completion; forecast the new date.
- Corrective action: see below.
- Update and report the schedule; repeat at the next review.
How to keep the project on schedule
- Make a realistic plan, with the critical path and float known.
- Arrange materials, equipment, drawings, land and payments in advance.
- Give priority in resources to critical activities; monitor them daily.
- Hold regular progress meetings and take quick decisions.
- If delayed: add labour or equipment, work overtime or extra shifts (crashing), do activities in parallel (fast tracking), change the method or logic, or use float of non-critical work.
- Control changes and variation orders; manage risks (weather, strikes) with contingency.
- Use incentives for early completion and penalty for delay in the contract.
- 2079 Baisakh · 1+2+3 marks
Discuss cost control, cost control cycle and methods of cost control in brief.
Answer
Cost control
Cost control is the process of keeping the actual cost of the project within the approved budget by recording costs, comparing them with the budget, finding the variances and taking corrective action.
Cost control cycle
Budget baseline -> Record actual cost -> Compare with budget
^ |
| v
Update budget <- Corrective action <- Analyse variance
and forecast cost
- Prepare the budget baseline from the WBS and cost codes.
- Record the actual costs (labour, material, equipment) from bills and site records.
- Compare actual with budgeted (earned) cost and find the variance.
- Analyse the causes and forecast the final cost (EAC).
- Take corrective action; revise the budget through approved changes; repeat.
Methods of cost control
- Cost budgeting and cost codes by WBS, with a responsible person for each item.
- Variance analysis and exception reports (actual against budget).
- Earned value analysis: CV, CPI and EAC.
- S-curve and cash flow control of planned against actual expenditure.
- Control of changes and variation orders; claims management.
- Procurement and material control: bulk buying, store control, reducing wastage.
- Productivity improvement, better equipment use, and work study.
- Time-cost trade-off (crashing only when the benefit is greater) and value engineering.
- 2065 Shrawan (old course) · 8 marks
Describe the elements of cost control, system of control and feedback control system.
Answer
Elements of cost control
- Cost estimate and budget baseline prepared from the WBS, with cost codes.
- Cost accounting: recording the actual costs of each work item.
- Cost reporting: regular reports of budget, actual cost, commitments and forecast.
- Variance analysis: comparing actual with budget (or earned value) and finding the causes.
- Forecasting: estimate at completion (EAC) and cash needs.
- Corrective action and change control: actions to reduce cost or approved change in the budget.
- Responsibility and authority: each cost centre has an accountable person.
System of control
A control system can be:
- Open system: no feedback; the output is not compared with the target, so errors are not corrected automatically (e.g. a fixed monthly allocation, without checking progress).
- Closed system: the output is measured and fed back, compared with the target and corrected (e.g. monthly comparison of actual cost with the budget). Project cost control is a closed system.
Feedback control system
Plan / Standard (set point)
|
v
Input --> [ Process: project work ] --> Output
^ |
| v
[ Corrective <---- [ Sensor: measure
action ] actual ]
^ |
| v
+------ [ Comparator: ] <--+
actual vs plan
The sensor measures the actual cost, the comparator finds the variance against the budget, and the manager (effector) takes corrective action. The result of the action is again measured, so the loop keeps the cost close to the budget. Feedback should be quick and accurate; a long delay in the report weakens control.
- 2067 Asar (old course) · 8 marks
Explain with examples closed system and open system of control. Justify the statement "Quality costs more, but lack of quality costs even more".
Answer
Closed and open system of control
OPEN LOOP CLOSED LOOP
Input -> [Process] -> Out Input -> [Process] -> Out
^ |
+-- [Compare]<------+
(feedback)
| Basis | Open system | Closed system |
|---|---|---|
| Feedback | None | Present |
| Output compared with target | No | Yes |
| Self-correction | No; changes in conditions are not corrected | Yes; deviation is corrected |
| Complexity and cost | Simple, cheap | More complex, needs measurement |
| Accuracy | Low | High |
| Examples | Pump run on a timer; releasing funds monthly without checking progress; a plan carried out blindly | Thermostat of a heater; monthly comparison of actual cost with budget and correction; irrigation gate controlled by water level sensor |
Project control should be a closed system because the environment changes and errors must be corrected.
"Quality costs more, but lack of quality costs even more"
Good quality needs money for prevention (planning, training, procedures) and appraisal (inspection and tests). Poor quality costs far more through failure: rework and rejection (internal failure) and repair, claims and loss of reputation (external failure). For example, testing concrete cubes costs a few hundred rupees, but a defective slab may cost lakhs to demolish and recast.
As spending on prevention and appraisal increases, the failure cost falls faster, so the total cost goes down to an optimum. Hence lack of quality is more costly than quality.
- 2072 Chaitra · 4 marks
Write a short note on the elements of project control.
Answer
Project control is the process of keeping the project on its planned time, cost and quality by comparing actual performance with the plan and taking corrective action. Its elements are:
- Plan / standard (baseline): approved scope, schedule, budget and quality standards against which performance is judged.
- Measurement of performance: collecting actual data of progress, cost, quality and resource use (monitoring).
- Comparison and variance analysis: finding the difference between actual and planned and its cause and effect on the project.
- Corrective action: decisions to bring the project back to plan (more resources, re-sequencing, change of method) or to revise the plan.
- Information and reporting (feedback): timely reports to the manager and the client; the result of the action is fed back to the next cycle.
- Organisation and authority: clear responsibility, authority and people for control at each level.
The elements work as a loop: after action is taken, performance is measured again and the result is fed back, so control is continuous until the project is complete.
- 2081 Baisakh · 3 marks
Write a short note on project monitoring, evaluation and controlling.
Answer
- Project monitoring is the continuous collection, recording and reporting of information on the actual progress of a project (physical work, time, cost, quality, resource use) during implementation, and its comparison with the plan, so that deviations are known.
- Project evaluation is the periodic, systematic assessment of a project (during, at the end, or after completion) to judge its relevance, efficiency, effectiveness, impact and sustainability against the objectives, and to draw lessons for decisions and for future projects.
- Project control is the process of comparing actual performance with the plan, analysing the variances and taking corrective action (or revising the plan) so that the project is completed within the planned time, cost and quality.
Monitoring gives the information, evaluation judges the results, and control uses both to correct the project. The three together form the basis of good project management.
- 2070 Chaitra (old course) · 2+2+4 marks
Why is cost control necessary in a project? What is earned value? Explain the EVA approach of cost control.
Answer
Why cost control is necessary
- The budget is limited, and overspending can make the project unviable.
- Costs change with price rise, wastage, variations and delay; they must be watched.
- It gives early warning of overrun, while correction is still possible.
- It helps funding and cash-flow planning, and satisfies the client and the lender.
- It improves efficiency and profit of the contractor.
Earned value
Earned value (EV) is the budgeted cost of the work actually completed at the status date: . It tells what the completed work was worth according to the budget.
EVA approach of cost control
At each review the following three quantities are found:
| Term | Other name | Meaning |
|---|---|---|
| BAC | Budget at completion | Total approved budget of the project |
| PV | BCWS (planned value) | Budgeted cost of the work scheduled up to the date |
| EV | BCWP (earned value) | Budgeted cost of the work actually completed = % complete x BAC |
| AC | ACWP (actual cost) | Actual money spent for the work done up to the date |
| Indicator | Value | Meaning |
|---|---|---|
| SV, SPI | SV > 0, SPI > 1 | Ahead of schedule |
| SV = 0, SPI = 1 | On schedule | |
| SV < 0, SPI < 1 | Behind schedule | |
| CV, CPI | CV > 0, CPI > 1 | Under budget (cost efficient) |
| CV = 0, CPI = 1 | On budget | |
| CV < 0, CPI < 1 | Over budget (cost inefficient) |
CV and CPI show cost performance; SV and SPI show schedule performance. EAC forecasts the final cost. If CPI < 1 the manager looks for the cause (low productivity, wastage, high rates) and acts to bring the cost back to the budget; the forecast is updated every month.
- 2082 Baisakh · 3+3 marks
What is Earned Value Analysis? Mention the different parameters of Earned Value Analysis and their interpretation.
Answer
Earned Value Analysis
EVA is a project control technique that measures project progress by comparing the budgeted value of the work done (earned value) with the planned value and with the actual cost. It integrates scope, time and cost, giving variances and indices and forecasts of final cost and time.
Parameters and interpretation
| Term | Other name | Meaning |
|---|---|---|
| BAC | Budget at completion | Total approved budget of the project |
| PV | BCWS (planned value) | Budgeted cost of the work scheduled up to the date |
| EV | BCWP (earned value) | Budgeted cost of the work actually completed = % complete x BAC |
| AC | ACWP (actual cost) | Actual money spent for the work done up to the date |
| Parameter | Formula | Interpretation |
|---|---|---|
| Schedule variance SV | Positive: ahead; zero: on time; negative: behind schedule | |
| Cost variance CV | Positive: under budget; zero: on budget; negative: over budget | |
| Schedule performance index SPI | > 1 ahead; = 1 on time; < 1 behind. E.g. 0.8 means only 80 % of planned work is done | |
| Cost performance index CPI | > 1 efficient; = 1 on budget; < 1 over budget. E.g. 0.8 means Rs 0.80 of value earned for each Rs 1 spent | |
| Estimate at completion EAC | Forecast of final cost | |
| Estimate to complete ETC | Cost still to be spent | |
| Variance at completion VAC | Expected under or overrun at the end | |
| Forecast duration | planned duration / SPI | Expected completion time |
- 2082 Bhadra · 2+6 marks
How is earned value analysis applicable for monitoring the performance of a construction project? A project has a planned budget of Rs 10,00,000 and a schedule of 50 days. During its implementation you have monitored the following data: (i) have so far worked for 35 days; (ii) Rs 8,00,000 already spent; (iii) 60% of work has been accomplished. Perform EVA and comment on the performance of the project.
Answer
Applicability of EVA for monitoring
EVA is suitable for monitoring a construction project because it measures performance with one common unit, money. At every review the planned value (PV), earned value (EV) and actual cost (AC) are found. From them the schedule variance, cost variance and the SPI and CPI show whether the project is ahead or behind and over or under budget, and the EAC forecasts the final cost. Since the physical progress is converted to a value, the cost and time performance of different activities can be added and compared with the baseline at any date.
Given data
BAC = Rs 10,00,000; planned duration = 50 days; at day 35: progress = 60 %, cost spent = Rs 8,00,000. Planned work is assumed uniform with time.
Calculation
Comment
- Schedule: SV = -1,00,000 and SPI = 0.86, so the project is behind schedule; only 86 % of the planned work is done. If the same rate continues, the duration becomes 58.3 days against 50 days planned.
- Cost: CV = -2,00,000 and CPI = 0.75, so the project is over budget; each rupee spent has earned Rs 0.75 of work.
- Forecast: EAC = Rs 13,33,333 against BAC = Rs 10,00,000, i.e. a final overrun of Rs 3,33,333.
- Action: find the causes (low productivity, idle equipment, material delay, wastage), add resources or shifts on critical activities, tighten supervision and cost control, and revise the plan with the client.
Answer: SV = Rs -1,00,000, CV = Rs -2,00,000, SPI = 0.86, CPI = 0.75; behind schedule and over budget; EAC = Rs 13,33,333.
- 2081 Bhadra · 6 marks
A project is undertaken where the work has to be completed within 60 days with a budget of Rs 20,00,000. According to the progress reports, at the end of the first month, only 25% of the total work has been completed and at the cost of Rs 12,00,000. Perform earned value analysis (EVA) for this project.
Answer
Given data
BAC = Rs 20,00,000; planned duration = 60 days; at the end of the first month (30 days) 25 % of the work is complete and the cost is Rs 12,00,000. Planned work is assumed uniform, so half of the work is planned in the first month.
Calculation
Comment
- Schedule: SV = -5,00,000 and SPI = 0.50, so the project is behind schedule; only 50 % of the planned work is done. If the same rate continues, the duration becomes 120.0 days against 60 days planned.
- Cost: CV = -7,00,000 and CPI = 0.42, so the project is over budget; each rupee spent has earned Rs 0.42 of work.
- Forecast: EAC = Rs 48,00,000 against BAC = Rs 20,00,000, i.e. a final overrun of Rs 28,00,000.
- Action: find the causes (low productivity, idle equipment, material delay, wastage), add resources or shifts on critical activities, tighten supervision and cost control, and revise the plan with the client.
Answer: SV = Rs -5,00,000, CV = Rs -7,00,000, SPI = 0.50, CPI = 0.42; the project is badly behind schedule and over budget, EAC = Rs 48,00,000.
- 2081 Baisakh · 6 marks
A project is undertaken where the work has to be completed within 60 days with a budget of Rs 20,000. The cost breakdown per month is Rs 10,000. The work scheduled in each month is half of the total work to be completed. According to the progress reports, at the end of the first month, only 25% of the total work has been completed and 50% of the total budget has been spent. Also, for the completion of 25% work, the actual cost incurred is 50% of the total budgeted cost. Perform EVA and comment on performance.
Answer
Given data
BAC = Rs 20,000; duration = 60 days (2 months); cost breakdown Rs 10,000 per month; half of the work is scheduled in each month. At the end of month 1: work done = 25 %; spent = 50 % of the budget.
Calculation
Comment
- Schedule: SV = -5,000 and SPI = 0.50, so the project is behind schedule; only 50 % of the planned work is done. If the same rate continues, the duration becomes 120.0 days against 60 days planned.
- Cost: CV = -5,000 and CPI = 0.50, so the project is over budget; each rupee spent has earned Rs 0.50 of work.
- Forecast: EAC = Rs 40,000 against BAC = Rs 20,000, i.e. a final overrun of Rs 20,000.
- Action: find the causes (low productivity, idle equipment, material delay, wastage), add resources or shifts on critical activities, tighten supervision and cost control, and revise the plan with the client.
Answer: SV = Rs -5,000, CV = Rs -5,000, SPI = 0.50, CPI = 0.50; behind schedule and over budget; EAC = Rs 40,000, double the budget.
- 2080 Bhadra · 6 marks
Suppose you have a project that is scheduled to be completed in 10 days at a budgeted cost of 100,000. At the end of day 6, you do an analysis and you determine the job is 70% complete and you have spent 55000. (i) Is the project ahead, behind schedule or on time? (ii) Is the project expected to complete on budget, under or over budget? (iii) What is the project's SPI and CPI at day 6?
Answer
Given data
BAC = Rs 1,00,000 (100,000); duration = 10 days; at day 6: work done = 70 %, cost spent = Rs 55,000. Planned work is assumed uniform with time.
Calculation
Answers
(i) and : the project is ahead of schedule (70 % done against 60 % planned). At this rate it can finish in about 8.6 days.
(ii) and : the project is expected to complete under budget; EAC = Rs 78,571 against Rs 1,00,000, a saving of Rs 21,429.
(iii) SPI = 1.17 and CPI = 1.27 at day 6.
- Action: continue the same management, keep the quality standard (do not save cost by poor work), and use the saved time/money as contingency or to release resources for other tasks.
- 2080 Baisakh · 6 marks
You have a project that is scheduled to be completed in 10 days at a budgeted cost of Rs 100,000. After the completion of 6 days, you do an analysis and you determine the job is 70% of work complete and the expenditure is Rs 65,000. Based on this data, is your work performance on track? Perform EVA and comment on your own performance.
Answer
Given data
BAC = Rs 1,00,000; duration = 10 days; at day 6: work done = 70 %, expenditure = Rs 65,000. Planned work is assumed uniform with time.
Calculation
Comment on performance
- Schedule: SV = 10,000 and SPI = 1.17, so the project is ahead of schedule; 117 % of the planned work is done. At this rate the work could finish in about 8.6 days against 10 days planned.
- Cost: CV = 5,000 and CPI = 1.08, so the project is under budget; each rupee spent has earned Rs 1.08 of work.
- Forecast: EAC = Rs 92,857 against BAC = Rs 1,00,000, i.e. a final saving of Rs 7,143.
Yes, the work performance is on track and better than planned: it is ahead of schedule and under budget. The margin on cost is smaller than the margin on time (CPI = 1.08 against SPI = 1.17), so the manager should keep a watch on spending and keep the quality standard while the work goes ahead.
Answer: SV = Rs 10,000, CV = Rs 5,000, SPI = 1.17, CPI = 1.08; EAC = Rs 92,857.
- 2079 Bhadra · 6 marks
Er. Jack has to complete 450 cum brickwork in canal construction in 40 days. According to the contract agreement, the cost per cum brickwork is Rs 16000. After the brickwork is started, the monitoring team visited the project in 20 days; they found that only 30% of the total cum brickwork is completed. The actual cost per cum expensed is Rs 16500. Based on the above statement, find Cost Variance, Schedule Variance, Cost Performance Index and Schedule Performance Index and analyse the situation of the project.
Answer
Given data
- Quantity = 450 cum; rate = Rs 16,000 per cum, so .
- Duration = 40 days; status date = day 20; work completed = 30 % of 450 = 135 cum.
- Actual rate = Rs 16,500 per cum. Planned work is assumed uniform with time.
Calculation
Analysis of the situation
- Schedule: SV = -14,40,000 and SPI = 0.60, so the project is behind schedule; only 60 % of the planned work is done. If the same rate continues, the duration becomes 66.7 days against 40 days planned.
- Cost: CV = -67,500 and CPI = 0.97, so the project is over budget; each rupee spent has earned Rs 0.97 of work.
- Forecast: EAC = Rs 74,25,000 against BAC = Rs 72,00,000, i.e. a final overrun of Rs 2,25,000.
The cost overrun is small (CPI close to 1), but the schedule delay is serious: only 135 cum is done against 225 cum planned (SPI = 0.60). The job needs about 67 days at the present rate. Er. Jack should add masons and curing/material arrangements and work extra shifts to recover the 90 cum backlog, while controlling rate of Rs 16,500 against Rs 16,000.
Answer: CV = Rs -67,500, SV = Rs -14,40,000, CPI = 0.97, SPI = 0.60; the project is behind schedule and slightly over budget.
- 2078 Bhadra · 8 marks
A company has signed a fixed cost contract to install 1000 new parking meters at a cost of Rs 20,00,000. Old parking meters have to be removed from their stands and replaced with new ones. The cost of doing this is Rs 2000 per meter. It is estimated that 25 meters are installed each day. On the review date at day 18 only 400 meters have been installed and it was found that the actual cost of work performed equals Rs 10,00,000. Find out all the parameters of earned value analysis and comment on the performance status of this project.
Answer
Given data
- Fixed contract: 1000 meters at Rs 20,00,000, i.e. Rs 2,000 per meter, so .
- Planned rate = 25 meters/day, so the planned duration = 1000 / 25 = 40 days.
- Review at day 18: meters installed = 400; .
Calculation
Comment
- Schedule: SV = -1,00,000 and SPI = 0.89, so the project is behind schedule; only 89 % of the planned work is done. If the same rate continues, the duration becomes 45.0 days against 40 days planned.
- Cost: CV = -2,00,000 and CPI = 0.80, so the project is over budget; each rupee spent has earned Rs 0.80 of work.
- Forecast: EAC = Rs 25,00,000 against BAC = Rs 20,00,000, i.e. a final overrun of Rs 5,00,000.
Only 400 meters are installed against 450 planned (50 meters behind), and the actual cost per meter installed is 10,00,000 / 400 = Rs 2,500 against the budgeted Rs 2,000 (25 % higher). At the present rate the installation needs about 45 days instead of 40 days. Action: add installation crews, check why the cost per meter is high (rework, transport, idle labour) and control it, since the contract is fixed-cost and the overrun is borne by the company.
Answer: PV = Rs 9,00,000; EV = Rs 8,00,000; AC = Rs 10,00,000; SV = Rs -1,00,000; CV = Rs -2,00,000; SPI = 0.89; CPI = 0.80; EAC = Rs 25,00,000; behind schedule and over budget.
- 2076 Chaitra · 8 marks
A project has a planned budget of Rs 30,00,000 and a schedule of 24 months. During its implementation you have monitored the following data. Perform EVA and comment on the performance and also draw the S-curve to forecast the final completion budget and schedule.
Months Work completed Actual Expenditure (Rs) 5 20% 7,00,000 10 45% 13,00,000 15 60% 20,00,000 20 70% 24,00,000
Answer
Given data
BAC = Rs 30,00,000; planned duration = 24 months. The planned progress is assumed uniform, so . ; AC is given.
Calculation (Rs)
| Month | PV | EV | AC | SV | CV | SPI | CPI |
|---|---|---|---|---|---|---|---|
| 5 | 6,25,000 | 6,00,000 | 7,00,000 | -25,000 | -1,00,000 | 0.96 | 0.86 |
| 10 | 12,50,000 | 13,50,000 | 13,00,000 | 1,00,000 | 50,000 | 1.08 | 1.04 |
| 15 | 18,75,000 | 18,00,000 | 20,00,000 | -75,000 | -2,00,000 | 0.96 | 0.90 |
| 20 | 25,00,000 | 21,00,000 | 24,00,000 | -4,00,000 | -3,00,000 | 0.84 | 0.88 |
Sample (month 20): ; ; .
Forecast at the latest review (month 20):
Comment on performance
-
Month 5: slightly behind schedule (SPI 0.96) and over budget (CPI 0.86).
-
Month 10: ahead of schedule (SPI 1.08) and slightly under budget (CPI 1.04); the best position.
-
Months 15 and 20: the performance has dropped; SPI falls to 0.84 and CPI to 0.88. The project is behind schedule and over budget, and the trend is getting worse.
-
Schedule: SV = -4,00,000 and SPI = 0.84, so the project is behind schedule; only 84 % of the planned work is done. If the same rate continues, the duration becomes 28.6 months against 24 months planned.
-
Cost: CV = -3,00,000 and CPI = 0.88, so the project is over budget; each rupee spent has earned Rs 0.88 of work.
-
Forecast: EAC = Rs 34,28,571 against BAC = Rs 30,00,000, i.e. a final overrun of Rs 4,28,571.
S-curve (cumulative values, Rs lakh)
P = planned value, E = earned value, A = actual cost, F = forecast (completion time, EAC), * = overlapping points.
36 |
| F
33 |
|
30 | P
|
27 |
| P
24 | A
|
21 | E
| A
18 | *
|
15 |
| *
12 | P
|
9 |
| A
6 | *
|
3 |
|
0 |*
+-------------------------------
0 5 10 15 20 25 30 months
The planned S-curve ends at Rs 30 lakh in month 24. The earned value curve lies below it (except around month 10) and the actual cost curve lies above the earned value curve. Extending the trend, the project will be completed in about 28.6 months (instead of 24) at a cost of about Rs 34,28,571 (instead of Rs 30,00,000), an overrun of Rs 4,28,571. The manager must speed up the critical work and control cost to reduce this.
Answer: at month 20, SV = Rs -4,00,000, CV = Rs -3,00,000, SPI = 0.84, CPI = 0.88; forecast cost Rs 34,28,571 and forecast duration 28.6 months.
- 2076 Chaitra · 8 marks
How is EVA used in controlling the cost of a project during project implementation? Explain EVA with 3 different examples requiring different approaches in control.
Answer
Use of EVA in controlling cost
During implementation, at every review date the manager finds PV, EV and AC and calculates the variances and indices:
CV and CPI show the cost performance; SV and SPI show the schedule performance; EAC forecasts the final cost. The result decides the control action; the same figures are plotted every month, so the trend is visible. A project with BAC = Rs 10,00,000, 10 months, and status at month 5 (PV = Rs 5,00,000) is used for the three examples.
Example 1: behind schedule and over budget
PV = Rs 5,00,000, EV = Rs 4,00,000, AC = Rs 6,00,000. , , , , .
Status: behind schedule, over budget. Control approach: Both schedule and cost are in trouble, so the control must be strong: find the causes, add resources only to the critical activities, tighten cost control (wastage, rates), and revise the plan or scope with the client. If CPI is very low, consider stopping low-value work.
Example 2: ahead of schedule and under budget
PV = Rs 5,00,000, EV = Rs 5,50,000, AC = Rs 4,80,000. , , , , .
Status: ahead of schedule, under budget. Control approach: The project is doing better than planned. Control means keeping the good performance: check that quality is not being sacrificed, keep the contingency, and release the extra resources or crew to other work. No corrective action is required.
Example 3: on schedule but over budget
PV = Rs 5,00,000, EV = Rs 5,00,000, AC = Rs 6,00,000. , , , , .
Status: on schedule, over budget. Control approach: Time is satisfactory but money is being lost. The control is on cost only: reduce wastage, improve productivity, renegotiate rates or procurement, and control variations. Adding resources to speed up the work is not needed and would increase the cost.
| Example | SPI | CPI | Status | Main control |
|---|---|---|---|---|
| 1 | 0.80 | 0.67 | Behind and over | Recovery plan, resources on critical work, cost control |
| 2 | 1.10 | 1.15 | Ahead and under | Maintain, protect quality |
| 3 | 1.00 | 0.83 | On schedule, over budget | Cost reduction only |
Another case is behind schedule but under budget (EV = 4,50,000, AC = 4,00,000, SPI = 0.90, CPI = 1.13): here the saving can be used to add resources and recover time.
- 2075 Chaitra · 8 marks
Perform EVA on the basis of the following given information of the "Earthquake Affected Monasteries Reconstruction Project" (EMRP), which was monitored after 6 months of its implementation. State controlling statements on the basis of your evaluation.
Description (Budget/Plan) Standard information Description (monitored) Monitored progress (completed) 1. Number of monasteries to be reconstructed 753 units 1. Reconstructed monasteries 179 units 2. Reconstruction project to be completed in 30 months 2. Average expended reconstruction cost per unit Rs 7.8 millions 3. Average reconstruction cost per unit Rs 9.3 millions
Answer
EVA is carried out in Rs million. Planned progress is taken as uniform over 30 months.
Data
- BAC = 753 x 9.3 = Rs 7,002.90 million
- Planned progress after 6 months = 6/30 = 20%
- Completed = 179 units; actual average cost = Rs 7.8 million/unit
(all values in Rs million; planned units after 6 months = 150.6, completed = 179)
Calculation
Comment
- Schedule: SV is positive and SPI = 1.189, so the project is ahead of schedule. The work done is 118.9% of the planned work. At this rate the duration becomes about 25.24 against the planned 30 (a change of -4.76).
- Cost: CV is positive and CPI = 1.192, so the project is under budget. Each Rs 1 spent gives Rs 1.19 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 5,873.40 against the budget of Rs 7,002.90 (variance at completion 1,129.50).
Answer: SV = 264.12, CV = 268.50, SPI = 1.189, CPI = 1.192; the project is ahead of schedule and under budget.
Both schedule and cost are favourable. Controlling statements: continue the present method, maintain productivity, keep records, and watch for later risks.
Controlling statements
- The project is ahead of schedule by about 18.9% and below cost by about 19.2%, so the present work method is good and should be continued.
- Check that quality and structural safety have not been reduced to save time and cost.
- Keep the same crew and material supply, and update the forecast regularly because the later reconstruction in remote hill areas may be harder.
- Use the saving as contingency for price rise and the monsoon.
- 2073 Shrawan · 7 marks
For a particular project the budgeted cost of work scheduled was Rs 9,50,000 and the budgeted value of the work performed was Rs 8,00,000 at a point of reporting date, i.e. at 20 weeks from starting date. But the actual cost of work performed was Rs 10,00,000 and the project completion time is 45 weeks. The project has an estimated cost of Rs 50,00,000. Based on the above information, draw the features of that project and comment on each parameter of earned value analysis.
Answer
Data
BCWS = PV = Rs 9,50,000; BCWP = EV = Rs 8,00,000; ACWP = AC = Rs 10,00,000; BAC = Rs 50,00,000; reporting date = week 20 of 45 weeks.
Calculation
Comment
- Schedule: SV is negative and SPI = 0.842, so the project is behind schedule. Only 84.2% of the planned work is done. At this rate the duration becomes about 53.44 against the planned 45 (a change of +8.44).
- Cost: CV is negative and CPI = 0.800, so the project is over budget. Each Rs 1 spent gives Rs 0.80 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 6,250,000 against the budget of Rs 5,000,000 (variance at completion -1,250,000).
Answer: SV = -150,000, CV = -200,000, SPI = 0.842, CPI = 0.800; the project is behind schedule and over budget.
Both schedule and cost are unfavourable. Controlling statements: increase productive resources (labour, equipment, extra shifts), improve supervision and productivity, review rates and wastage, re-sequence activities and revise the plan or budget with the client's approval.
Features of the project
Cost (Rs lakh)
50| .-- BAC
| .-'
10| ACWP o .-'
9.5| PV o .-'
8 | EV o-'
| .-'
+----------|---------------- weeks
0 20 45
- Planned progress = 9.5/50 = 19%; earned progress = 8/50 = 16%; money spent = 20% of the budget.
- Since AC > PV > EV, the project is behind schedule and over budget (the worst situation).
Comment on each parameter
- SV = -1,50,000: work worth Rs 1.5 lakh planned is not yet done; the project is behind schedule.
- SPI = 0.842: only 84.2% of the planned work is done.
- CV = -2,00,000: the work done cost Rs 2 lakh more than its budget.
- CPI = 0.80: each Rs 1 spent gives Rs 0.80 of work.
- EAC = Rs 6,250,000: the project will cost Rs 12.5 lakh more than BAC if the trend continues. ETC = EAC - AC = Rs 52,50,000.
- Forecast duration = 45/0.842 = 53.4 weeks, about 8.4 weeks late.
Corrective action is needed: increase resources and productivity, control waste and unit rates, and revise the schedule.
- 2067 Asar (old course) · 4+4 marks
Explain earned value analysis graphically showing favourable and unfavourable cases of variance. For a particular project, the budgeted cost of work scheduled was Rs 9,50,000 and the budgeted value of the work actually completed or earned value was Rs 8,00,000 at a point of reporting date, i.e. at 20 weeks from starting date. The completion time of the project is 45 weeks. Based on the above details, draw the features of that project and comment on the schedule performance.
Answer
Earned value analysis graphically
EVA plots three cumulative cost curves against time: BCWS (planned value), BCWP (earned value) and ACWP (actual cost). The gaps between them are the variances.
- Schedule variance: SV = BCWP - BCWS
- Cost variance: CV = BCWP - ACWP
FAVOURABLE UNFAVOURABLE
Cost Cost
| EV .-- | AC .--
| PV .-'-' | PV .-'-'
| .-' AC | .-' EV
| .' | .'
+--------- time +--------- time
EV above PV: ahead EV below PV: behind
EV above AC: saving EV below AC: overrun
| Case | Condition | Meaning |
|---|---|---|
| Favourable | SV > 0 (EV above PV) | Ahead of schedule |
| Favourable | CV > 0 (EV above AC) | Under budget |
| Unfavourable | SV < 0 (EV below PV) | Behind schedule |
| Unfavourable | CV < 0 (EV below AC) | Over budget |
| On target | EV = PV = AC | As planned |
Numerical (schedule performance)
Data: PV = Rs 9,50,000, EV = Rs 8,00,000 at week 20; planned duration = 45 weeks. The total budget and the actual cost are not given, so only schedule performance can be found.
Features and comment
Cost
9.5 | PV o
8.0 | EV o (below PV)
+----------|----------- weeks
20 45
- The earned value curve lies below the planned curve, so the project is behind schedule.
- Only 84.2% of the planned work is complete; work worth Rs 1,50,000 is delayed.
- If the same performance continues, the expected duration = 45/0.842 = 53.4 weeks, i.e. about 8.4 weeks of delay.
- Remedies: add labour and equipment, work overtime, fast-track activities that are not on the critical path and re-plan the remaining schedule.
Answer: SV = -Rs 1,50,000; SPI = 0.842; the project is behind schedule.
- 2071 Chaitra · 2+4 marks
Why is cost control important? A contractor agreed to build 50 doghouses in 90 days at a price of $1000 per unit. 20 days later, the contractor has finished 10 doghouses with an actual cost of $8500. What is the status of the project?
Answer
Why cost control is important
Cost control means monitoring actual expenditure against the budget and taking action on variances. It is important because it:
- keeps the project within the approved budget and prevents cost overrun;
- gives early warning of problems so that corrective action is taken in time;
- improves profit for the contractor and value for the client;
- helps to forecast the final cost and cash flow;
- supports good decisions and accountability on resources and prices.
Status of the project by EVA
- BAC = 50 x $1,000 = $50,000; time elapsed = 20 of 90 days (planned progress = 22.22%)
- Completed = 10 doghouses (20%); actual cost AC = $8,500
Calculation
Comment
- Schedule: SV is negative and SPI = 0.900, so the project is behind schedule. Only 90.0% of the planned work is done. At this rate the duration becomes about 100.00 against the planned 90 (a change of +10.00).
- Cost: CV is positive and CPI = 1.176, so the project is under budget. Each $ 1 spent gives $ 1.18 of work.
- Forecast: if the present cost trend continues, the final cost will be $ 42,500.00 against the budget of $ 50,000.00 (variance at completion 7,500.00).
Answer: SV = -1,111.11, CV = 1,500.00, SPI = 0.900, CPI = 1.176; the project is behind schedule and under budget.
Cost is favourable but progress is slow. Controlling statements: add resources or work extra shifts to recover the delay, remove bottlenecks (material, equipment, approvals), and keep the present cost discipline.
Status
The contractor is slightly behind schedule (SPI = 0.90; about 100 days needed instead of 90) but under budget (CPI = 1.18, forecast final cost $42,500 against $50,000). The cost saving is good, but resources should be increased to recover the delay.
- 2070 Chaitra · 6 marks
A construction company is planned to fix 100 units of precast window in 20 days with a budget of 25 lakhs. The progress status was reviewed on 10 days from the date of start of fixing and only 40 units were fixed with the expenses of 9 lakhs. Find out all the parameters of earned value analysis and comment on its performance.
Answer
All money values are in Rs lakh.
Data
- BAC = Rs 25 lakh for 100 windows in 20 days, so budget = Rs 0.25 lakh/window
- At day 10: planned = 50% of work; fixed = 40 windows (40%); expenses = Rs 9 lakh
Calculation
Comment
- Schedule: SV is negative and SPI = 0.800, so the project is behind schedule. Only 80.0% of the planned work is done. At this rate the duration becomes about 25.00 against the planned 20 (a change of +5.00).
- Cost: CV is positive and CPI = 1.111, so the project is under budget. Each Rs 1 spent gives Rs 1.11 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 22.50 against the budget of Rs 25.00 (variance at completion 2.50).
Answer: SV = -2.50, CV = 1.00, SPI = 0.800, CPI = 1.111; the project is behind schedule and under budget.
Cost is favourable but progress is slow. Controlling statements: add resources or work extra shifts to recover the delay, remove bottlenecks (material, equipment, approvals), and keep the present cost discipline.
The company is late (40 windows fixed against 50 planned) but each unit costs less than budgeted (Rs 0.225 lakh against Rs 0.25 lakh).
- 2070 Asar · 3+4 marks
Why is cost control important in a project? 15 houses were to be completed in three months with a per unit cost of Rs 25,00,000. In one month 4 houses were completed with a total expenditure of Rs 96,00,000. Use earned value analysis to find the status of the project.
Answer
Importance of cost control
- It keeps actual cost within the budget and avoids overrun.
- It shows variances early so that corrective action can be taken.
- It helps to forecast the final cost and the cash needed.
- It increases profit, efficiency and the client's confidence.
Earned value analysis
Money is in Rs lakh (Rs 25,00,000 = 25 lakh per house).
- BAC = 15 x 25 = Rs 375 lakh (3.75 crore)
- After 1 month: planned = 1/3 of the work; completed = 4 houses; actual cost = Rs 96 lakh
Calculation
Comment
- Schedule: SV is negative and SPI = 0.800, so the project is behind schedule. Only 80.0% of the planned work is done. At this rate the duration becomes about 3.75 against the planned 3 (a change of +0.75).
- Cost: CV is positive and CPI = 1.042, so the project is under budget. Each Rs 1 spent gives Rs 1.04 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 360.00 against the budget of Rs 375.00 (variance at completion 15.00).
Answer: SV = -25.00, CV = 4.00, SPI = 0.800, CPI = 1.042; the project is behind schedule and under budget.
Cost is favourable but progress is slow. Controlling statements: add resources or work extra shifts to recover the delay, remove bottlenecks (material, equipment, approvals), and keep the present cost discipline.
Planned completion in one month = 5 houses, but only 4 were finished. The project is behind schedule (needs about 3.75 months instead of 3) but the cost is slightly under control.
- 2065 Shrawan (old course) · 8 marks
Explain earned value analysis. When 125 cub.m. of concrete is to be done in 10 days at the cost of Rs 1,250,000, at the end of the third day 40 cub.m. of concrete was completed with expenses of Rs 3,75,000. Find EVA and comment on the performance.
Answer
Earned value analysis
EVA is a project control technique that integrates scope, time and cost. It compares the planned value (PV), the earned value (EV) and the actual cost (AC) at a reporting date to find schedule and cost variance and to forecast the final cost and duration. It is based on the budgeted cost of work scheduled (BCWS), the budgeted cost of work performed (BCWP) and the actual cost of work performed (ACWP).
| Term | Meaning |
|---|---|
| PV (BCWS) | Planned value: budgeted cost of work scheduled up to the date |
| EV (BCWP) | Earned value: budgeted cost of work actually completed |
| AC (ACWP) | Actual cost spent for the work completed |
| SV = EV - PV | Schedule variance (positive = ahead) |
| CV = EV - AC | Cost variance (positive = under budget) |
| SPI = EV/PV | Schedule performance index (>1 ahead) |
| CPI = EV/AC | Cost performance index (>1 under budget) |
| EAC = BAC/CPI | Estimate at completion |
Numerical
- BAC = Rs 12,50,000 for 125 m³ in 10 days (Rs 10,000/m³)
- At day 3: planned = 30% of the work; done = 40 m³ (32%); expenses = Rs 3,75,000
Calculation
Comment
- Schedule: SV is positive and SPI = 1.067, so the project is ahead of schedule. The work done is 106.7% of the planned work. At this rate the duration becomes about 9.38 against the planned 10 (a change of -0.62).
- Cost: CV is positive and CPI = 1.067, so the project is under budget. Each Rs 1 spent gives Rs 1.07 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 1,171,875 against the budget of Rs 1,250,000 (variance at completion 78,125).
Answer: SV = 25,000, CV = 25,000, SPI = 1.067, CPI = 1.067; the project is ahead of schedule and under budget.
Both schedule and cost are favourable. Controlling statements: continue the present method, maintain productivity, keep records, and watch for later risks.
Planned concrete by day 3 was 37.5 m³; 40 m³ was placed, so the work is ahead. The actual unit cost is Rs 9,375/m³ against the budget of Rs 10,000/m³.
- 2066 Bhadra (old course) · 4 marks
Write a short note on earned value analysis.
Answer
Earned value analysis (EVA) is a project monitoring and control technique that measures project performance by comparing the value of work planned, the value of work actually done, and the actual money spent, all at the same date. It shows schedule and cost status in one system.
Basic terms
| Term | Meaning |
|---|---|
| PV (BCWS) | Planned value: budgeted cost of work scheduled up to the date |
| EV (BCWP) | Earned value: budgeted cost of work actually completed |
| AC (ACWP) | Actual cost spent for the work completed |
| SV = EV - PV | Schedule variance (positive = ahead) |
| CV = EV - AC | Cost variance (positive = under budget) |
| SPI = EV/PV | Schedule performance index (>1 ahead) |
| CPI = EV/AC | Cost performance index (>1 under budget) |
| EAC = BAC/CPI | Estimate at completion |
Graphical view
Cost
| BAC
| AC .--
| PV .-'-'
| .-' EV
| .'
+------------ time
Uses
- Finds schedule and cost variance at any reporting date.
- Forecasts final cost (EAC) and the estimate to complete (ETC = EAC - AC).
- Gives early warning, so corrective action is taken early.
- Works for any project: construction, hydropower, road.
Interpretation
| Result | Meaning |
|---|---|
| SPI > 1, CPI > 1 | Ahead of schedule, under budget |
| SPI < 1, CPI < 1 | Behind schedule, over budget |
| SPI = 1, CPI = 1 | As planned |
- 2079 Bhadra · 2+2+2 marks
Define quality. Distinguish between Quality Assurance and Quality Control. List out different factors disturbing the quality of projects in Nepal.
Answer
Quality
Quality is the degree to which a set of inherent characteristics of a product or service meets the requirements: the specified standards, the client's needs and fitness for use. In construction, quality means the work follows the drawings, specifications and codes and is safe, durable and functional.
Quality assurance and quality control
| Basis | Quality assurance (QA) | Quality control (QC) |
|---|---|---|
| Meaning | Planned system of activities to give confidence that quality requirements will be met | Operational techniques to check that the work meets the requirement |
| Focus | Process; prevents defects | Product; detects defects |
| Nature | Proactive | Reactive |
| When | Before and during the work | During and after the work |
| Responsibility | Whole organisation and management | Site and testing team |
| Tools | Quality plan, audits, procedures, training | Inspection, tests (cube test, slump, compaction), checklists |
| Example | Setting the method statement and approving materials | Testing concrete cubes at 7 and 28 days |
Factors disturbing the quality of projects in Nepal
- Poor and incomplete design, drawings and estimates; weak site investigation.
- Lowest-bid contractors with low capacity, and unrealistic bid prices.
- Lack of skilled labour, supervisors and trained engineers.
- Weak supervision and monitoring by the client or consultant.
- Poor quality of materials (cement, aggregate, steel) and lack of testing labs near site.
- Delay in payment and shortage of funds, causing shortcuts.
- Corruption, commission and political interference.
- Difficult geography, monsoon and poor access to remote sites.
- Frequent change of design and variation orders.
- Low use of quality standards, such as the Nepal Building Code and Nepal Standards, and weak penalties.
- 2074 Asoj · 1+2+3 marks
Define quality. Differentiate between quality assurance and quality control. As a site engineer what steps would you follow to control quality?
Answer
Quality
Quality is the degree to which a set of inherent characteristics of a product or service meets the requirements: the specified standards, the client's needs and fitness for use. In construction, quality means the work follows the drawings, specifications and codes and is safe, durable and functional.
Quality assurance and quality control
| Basis | Quality assurance (QA) | Quality control (QC) |
|---|---|---|
| Meaning | Planned system of activities to give confidence that quality requirements will be met | Operational techniques to check that the work meets the requirement |
| Focus | Process; prevents defects | Product; detects defects |
| Nature | Proactive | Reactive |
| When | Before and during the work | During and after the work |
| Responsibility | Whole organisation and management | Site and testing team |
| Tools | Quality plan, audits, procedures, training | Inspection, tests (cube test, slump, compaction), checklists |
| Example | Setting the method statement and approving materials | Testing concrete cubes at 7 and 28 days |
Steps by a site engineer to control quality
- Study the drawings, specifications, BOQ and codes before starting; clarify doubts with the designer.
- Prepare a quality plan and method statements, with checklists for each activity.
- Approve materials: check source, samples and test reports of cement, steel, aggregate and sand before use; reject bad materials.
- Check setting out and levels, formwork, reinforcement (size, spacing, cover) before concreting.
- Supervise the work: control mix proportion, water-cement ratio, mixing, placing, compaction and curing.
- Test: slump test, cube test, density test, etc., on the frequency in the specification; keep records.
- Check workmanship with trained and skilled workers and keep the work as per the approved method.
- Document daily reports, inspection records and photographs; issue non-conformance reports.
- Correct defects at once (rework or repair) and find the cause so that it does not happen again.
- Coordinate with the client, consultant and contractor and hold regular quality meetings.
- 2082 Bhadra · 1+3+4 marks
Define quality. Explain the importance of cost of quality. How can the quality of a product be assured?
Answer
Quality
Quality is the degree to which a set of inherent characteristics of a product or service meets the requirements: the specified standards, the client's needs and fitness for use. In construction, quality means the work follows the drawings, specifications and codes and is safe, durable and functional.
Importance of cost of quality
Cost of quality (COQ) is the total cost spent to achieve quality and the cost of the failure to achieve it.
| Type | Meaning | Example |
|---|---|---|
| Prevention cost | Cost of preventing defects | Training, planning, design review |
| Appraisal cost | Cost of checking quality | Inspection, testing, audits |
| Internal failure cost | Defects found before delivery | Rework, scrap, delay |
| External failure cost | Defects found after delivery | Repair, warranty, claims, bad reputation |
Importance:
- Shows how much money is lost by poor quality, so management can act.
- A small extra cost on prevention and appraisal reduces much larger failure costs.
- Helps to choose the best level of quality and to justify quality budgets.
- Improves profit, client satisfaction and company reputation.
- Is used to compare projects and to find the areas for improvement.
How quality is assured
- Clear requirements: complete drawings, specifications and standards.
- A quality plan, with responsibilities, procedures and checklists.
- Selecting competent contractors and trained staff.
- Approval and testing of materials and equipment.
- Inspection at hold points and testing during the work.
- Quality audits, documentation and traceability.
- Corrective and preventive action for non-conformities.
- Continuous improvement (PDCA cycle) and feedback from the client.
- 2082 Baisakh · 4 marks
Differentiate between quality control and quality assurance.
Answer
Quality assurance (QA) is the planned and systematic set of activities in the process that gives confidence that quality requirements will be fulfilled. Quality control (QC) is the set of operational techniques used to inspect and test the product to check that it meets the requirement.
| Basis | Quality assurance (QA) | Quality control (QC) |
|---|---|---|
| Meaning | Planned system of activities to give confidence that quality requirements will be met | Operational techniques to check that the work meets the requirement |
| Focus | Process; prevents defects | Product; detects defects |
| Nature | Proactive | Reactive |
| When | Before and during the work | During and after the work |
| Responsibility | Whole organisation and management | Site and testing team |
| Tools | Quality plan, audits, procedures, training | Inspection, tests (cube test, slump, compaction), checklists |
| Example | Setting the method statement and approving materials | Testing concrete cubes at 7 and 28 days |
In short, QA is building quality into the process and QC is checking quality in the product.
- 2072 Chaitra · 6 marks
Define quality. Explain how quality can be controlled in the construction of urban roads.
Answer
Quality
Quality is the degree to which a set of inherent characteristics of a product or service meets the requirements: the specified standards, the client's needs and fitness for use. In construction, quality means the work follows the drawings, specifications and codes and is safe, durable and functional.
Quality control in urban road construction
Quality control checks every stage of the road work against the specification (for example the Standard Specification for Road and Bridge Works of the Department of Roads, Nepal) using inspection and tests.
Wearing course (bituminous)
Binder / base course
Sub-base (granular)
Subgrade (compacted)
- Survey and setting out: check alignment, levels, width and camber before work.
- Subgrade: test soil (CBR, Proctor density); compact to the required density and check by field density (sand replacement) test.
- Sub-base and base: test aggregate gradation, Los Angeles abrasion value and plasticity; check layer thickness, moisture and compaction.
- Drainage and utilities: make drains, culverts and utility ducts first, so that the road is not cut after paving.
- Bituminous work: check bitumen grade and content, aggregate quality, mix temperature, and laying and rolling; do Marshall test and core density.
- Concrete work (kerb, footpath, rigid pavement): control mix, slump, cubes and curing.
- Finish: check surface regularity with straight edge, levels, cross fall and thickness.
- Traffic and safety management during construction to protect workers and the public.
- Documentation: daily records, test results, inspection and approval before the next layer; corrective action for failed tests.
- Supervision by trained engineers, regular audits and final inspection before handing over.
- 2067 Asar (old course) · 8 marks
Define Project Management Information System (PMIS), stating the objectives of PMIS. Explain the various choices of information channel in a project.
Answer
Definition
Project Management Information System (PMIS) is a system of tools, techniques, people, procedures and software that collects, stores, processes and distributes project information to the people who need it, so that planning, monitoring and decision making are timely and accurate.
Objectives of PMIS
- Provide correct and timely information to managers for decisions.
- Support planning, scheduling, budgeting and resource allocation.
- Monitor progress, cost and quality against the plan and find variances early.
- Improve communication and coordination between client, consultant, contractor and other stakeholders.
- Keep complete records and reports (progress, cost, change, risk, lessons learned).
- Reduce paperwork, delay and duplication of data.
- Help to forecast cost, time and resource needs.
Choices of information channel
Top management
^ reports | instructions
Project manager <------+
^ ^ horizontal (coordination)
Section heads <---> Section heads
^ reports
Site staff
| Channel | Description | Example |
|---|---|---|
| Formal vertical (downward) | Orders, plans, policies from top to bottom | Work order, instruction letter |
| Formal vertical (upward) | Progress and problem reports from site to management | Weekly progress report |
| Horizontal / lateral | Between same-level people or departments | Design and construction team meeting |
| Informal | Unofficial talk and grapevine | Site talk, phone call |
| Written | Permanent record, legal value | Letters, minutes, drawings, reports |
| Oral / meetings | Quick, two-way | Site meeting, phone call |
| Electronic | Fast sharing of large data | Email, project software, shared drive, MIS dashboard |
The channel is chosen by the speed needed, the need of a record, the cost, the distance between people and the importance of the message. Important instructions go in writing, and daily coordination is done orally or electronically.
- 2066 Bhadra (old course) · 8 marks
Define Project Management Information System (PMIS). Why is PMIS important for effective coordination of project activities?
Answer
Definition
Project Management Information System (PMIS) is a system of tools, techniques, people, procedures and software that collects, stores, processes and distributes project information to the people who need it, so that planning, monitoring and decision making are timely and accurate.
Importance of PMIS for coordination
A project has many parties (owner, designer, contractor, suppliers, government) and many activities done at the same time. Coordination is possible only when everyone has the same, correct and current information. PMIS does this in these ways:
- Common database: drawings, schedule, budget and contracts are in one place, so all teams use the same data.
- Timely communication: progress, delay and change are reported quickly, so that dependent activities (e.g. formwork, steel, concrete) are arranged on time.
- Integration of time, cost and quality: managers see the full picture and settle conflicts between them.
- Early warning: variances and risks are found early, so the corrective action is joint and fast.
- Clear responsibility: each person knows tasks, deadlines and reporting lines.
- Better decisions: reliable reports help in resource allocation and change control.
- Less duplication and conflict: records of orders, approvals and variations avoid disputes and rework.
- Stakeholder reporting: regular, uniform reports for the client, donors and authorities.
- Learning: historical data supports future projects.
Without PMIS, information is late, repeated or lost, which causes delay, wrong decisions and cost overrun.
- 2078 Bhadra · 6 marks
What do you mean by Project Procurement Management? Explain the different processes adopted for procurement in a construction project.
Answer
Project procurement management is the set of processes used to purchase or acquire the goods, works and services needed from outside the project team, such as materials, equipment, consultants and contractors. It covers planning what to buy, selecting suppliers, awarding and administering contracts, and closing them.
Processes
- Plan procurement: decide what to procure, how, when, and the type of contract (make-or-buy, package division, budget and estimate).
- Prepare documents: prepare bidding documents (instruction to bidders, conditions of contract, specifications, drawings, BOQ), and the terms of reference for consultants.
- Conduct procurement (invite and select): call bids by notice, hold pre-bid meeting, receive and open bids, evaluate (technical and financial), and select the best bidder.
- Contract award: negotiate if needed, give the letter of acceptance, take performance security, sign the contract.
- Administer procurement: monitor performance, measure progress, handle variation, payment, claims and disputes.
- Close procurement: final inspection, handover, final payment, release of security and records.
Methods used in construction in Nepal
Under the Public Procurement Act, 2063 and its Regulations:
| Method | Use |
|---|---|
| Open competitive bidding (NCB/ICB) | Large works; any qualified bidder can take part |
| Limited bidding / prequalification | Special or complex works with few qualified firms |
| Quotation (sealed quotation) | Small value works |
| Direct purchase | Very small value or single source |
| User group / community participation | Small local works by community |
| Force account | Done by own staff |
Contract types: unit rate, lump sum, cost-plus, design and build (EPC), and BOT for large infrastructure.
Questions from Old Question Collection (CE 701) (IOE CE 701 exam papers from 2065 Shrawan to 2082 Bhadra). Answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗