- 2080 Baisakh · 6 marks
EVA; 10 days, 100,000, day 6, Rs 65,000
Short answer
PV=Rs 60,000, EV=Rs 70,000, AC=Rs 65,000; SPI=1.17, CPI=1.08. Project is ahead of schedule and slightly under budget, forecast EAC Rs 92,857.
You have a project that is scheduled to be completed in 10 days at a budgeted cost of Rs 100,000. After the completion of 6 days, you do an analysis and you determine the job is 70% of work complete and the expenditure is Rs 65,000. Based on this data, is your work performance on track? Perform EVA and comment on your own performance.
Given data
BAC = Rs 1,00,000; duration = 10 days; at day 6: work done = 70 %, expenditure = Rs 65,000. Planned work is assumed uniform with time.
Calculation
Comment on performance
- Schedule: SV = 10,000 and SPI = 1.17, so the project is ahead of schedule; 117 % of the planned work is done. At this rate the work could finish in about 8.6 days against 10 days planned.
- Cost: CV = 5,000 and CPI = 1.08, so the project is under budget; each rupee spent has earned Rs 1.08 of work.
- Forecast: EAC = Rs 92,857 against BAC = Rs 1,00,000, i.e. a final saving of Rs 7,143.
Yes, the work performance is on track and better than planned: it is ahead of schedule and under budget. The margin on cost is smaller than the margin on time (CPI = 1.08 against SPI = 1.17), so the manager should keep a watch on spending and keep the quality standard while the work goes ahead.
Answer: SV = Rs 10,000, CV = Rs 5,000, SPI = 1.17, CPI = 1.08; EAC = Rs 92,857.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA; 10 days, 100,000, day 6, spi and cpi · Project Engineering, chapter 4
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA; 60 days, 25% work, 50% budget spent · Project Engineering, chapter 4
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EVA and S-curve; Rs 30,00,000, 24 months · Project Engineering, chapter 4
- EVA numerical with five activities at day 5 · Construction Management, chapter 7