- 2070 Magh · 6 marks
EVA numerical with five activities at day 5
Short answer
PV = Rs 27,667; EV = Rs 18,250; AC = Rs 18,100; CV = +Rs 150; SV = −Rs 9,417; CPI = 1.01; SPI = 0.66; EAC ≈ Rs 34,712. Cost is slightly favorable but schedule is seriously behind; only 66% of planned work done. Acceleration is needed.
Perform earned value analysis of a project with five activities as given below. Progress was evaluated at the end of 5th day.
| Activity | Cost | Planned days (of 1 to 8) |
|---|---|---|
| A | 6,000 | 1-3 |
| B | 15,000 | 2-5 |
| C | 10,000 | 4-6 |
| D | 4,000 | 7-8 |
[Figure: bar chart with shaded cells showing the planned days; read from the scan, may be off by a day. Only four activities (A to D) appear in the printed table.]
| At the end of 5th day | % Complete | Actual Cost |
|---|---|---|
| A | 100% | 7000 |
| B | 55% | 7500 |
| C | 40% | 3600 |
| D | 0% | x |
Also comment on the performances.
Assumptions: the cost of each activity is spread uniformly over its planned days (read from the bar chart). Review at the end of day 5. BAC = 6,000 + 15,000 + 10,000 + 4,000 = Rs 35,000.
Planned value at end of day 5
| Activity | Cost | Planned days | Days planned done | PV |
|---|---|---|---|---|
| A | 6,000 | 1-3 (3 days) | 3 of 3 | 6,000 |
| B | 15,000 | 2-5 (4 days) | 4 of 4 | 15,000 |
| C | 10,000 | 4-6 (3 days) | 2 of 3 | 6,667 |
| D | 4,000 | 7-8 | 0 | 0 |
| Total | 35,000 | 27,667 |
Earned value and actual cost
| Activity | % | EV | AC |
|---|---|---|---|
| A | 100 | 6,000 | 7,000 |
| B | 55 | 8,250 | 7,500 |
| C | 40 | 4,000 | 3,600 |
| D | 0 | 0 | 0 |
| Total | 18,250 | 18,100 |
Results
Answer: PV = Rs 27,667; EV = Rs 18,250; AC = Rs 18,100; CV = +Rs 150; SV = −Rs 9,417; CPI = 1.01; SPI = 0.66.
Comment: Cost performance is fine, with a small saving of Rs 150 and CPI slightly above 1 (on A the cost is over, but B and C are under). However, the project is seriously behind schedule: only 66% of the planned work is done. Activity B (55% against 100% planned) and C (40% against 67%) are late. Since the cost is under control but time is not, the management should add resources or crews to B and C, or the following activity D will be delayed and the project will finish late.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- TCTO numerical with time-cost chart (five activities) · Construction Management, chapter 2
- EVA numerical with bar schedule (A to F) · Construction Management, chapter 7
- TCTO numerical: seven activities, Rs 225/day · Construction Management, chapter 2
- Earned value analysis for performance control · Construction Management, chapter 7 · asked 6×
- TCTO numerical: seven activities, Rs 2000/day · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 1000/day · Construction Management, chapter 2
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- EVA; 10 days, 100,000, day 6, spi and cpi · Project Engineering, chapter 4
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×