- 2078 Kartik · 7 marks
EVA numerical with bar schedule (A to F)
Short answer
PV = Rs 25,500; EV = Rs 23,800; AC = Rs 25,500. CV = SV = −Rs 1,700, CPI = SPI = 0.93, EAC ≈ Rs 48,214. The project is over budget and behind schedule by work worth Rs 1,700; if trend continues, final cost will be about Rs 48,214, requiring corrective action.
Perform EVA and comment on the performance for the given project.
| Activity | Cost (Rs.) | Planned days (of 1 to 7) |
|---|---|---|
| A | 5000 | 1-2 |
| B | 10000 | 2-5 |
| C | 15000 | 5-6 |
| D | 7000 | 6-7 |
| E | 6000 | 5-6 |
| F | 2000 | 6-7 |
[Figure: bar chart with shaded cells showing the planned days of each activity, as in the table; read from the scan, may be off by a day.]
The progress was monitored and recorded at the end of 5th day.
| Activity | % Completed | Expenditure (Rs) |
|---|---|---|
| A | 100 | 5000 |
| B | 80 | 9000 |
| C | 60 | 8000 |
| D | 0 | X |
| E | 30 | 3500 |
| F | 0 | X |
Assumptions: the cost of each activity is spread uniformly over its planned (shaded) days, from day 1 to day 7. The review is at the end of day 5. Activities D and F have not started, so their actual cost ("X") is taken as zero.
Planned value (PV) at end of day 5
| Activity | Cost (Rs) | Planned days | Days done by day 5 | PV (Rs) |
|---|---|---|---|---|
| A | 5,000 | 1-2 (2 days) | 2 of 2 | 5,000 |
| B | 10,000 | 2-5 (4 days) | 4 of 4 | 10,000 |
| C | 15,000 | 5-6 (2 days) | 1 of 2 | 7,500 |
| D | 7,000 | 6-7 | 0 | 0 |
| E | 6,000 | 5-6 (2 days) | 1 of 2 | 3,000 |
| F | 2,000 | 6-7 | 0 | 0 |
| Total | 45,000 | 25,500 |
Earned value (EV) = % complete × budget
| Activity | % done | Budget | EV (Rs) | AC (Rs) |
|---|---|---|---|---|
| A | 100 | 5,000 | 5,000 | 5,000 |
| B | 80 | 10,000 | 8,000 | 9,000 |
| C | 60 | 15,000 | 9,000 | 8,000 |
| E | 30 | 6,000 | 1,800 | 3,500 |
| Total | 23,800 | 25,500 |
BAC = 5,000 + 10,000 + 15,000 + 7,000 + 6,000 + 2,000 = Rs 45,000.
Variances and indices
Answer: PV = Rs 25,500; EV = Rs 23,800; AC = Rs 25,500; CV = −Rs 1,700; SV = −Rs 1,700; CPI = SPI = 0.93.
Comment: The project is over budget by Rs 1,700 and behind schedule by work worth Rs 1,700 (about 7%). Activity E is the main problem (30% done but 58% of its budget spent); B is also overspent. If the same trend continues, the final cost will be about Rs 48,214, i.e. Rs 3,214 above the budget. Corrective action is needed: speed up activities B, C and E, control the cost of E, and re-plan D and F.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 2000/day · Construction Management, chapter 2
- EVA numerical with five activities at day 5 · Construction Management, chapter 7
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- TCTO numerical: seven activities, Rs 1000/day · Construction Management, chapter 2
- TCTO numerical with time-cost chart (five activities) · Construction Management, chapter 2
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4