- 2076 Chaitra · 8 marks
EVA and S-curve; Rs 30,00,000, 24 months
Short answer
With BAC Rs 30,00,000 and uniform progress, at month 20: PV = 20/24 × 30,00,000 = Rs 25,00,000, EV = 70% × BAC = Rs 21,00,000, AC = Rs 24,00,000. SV = –Rs 4,00,000, CV = –Rs 3,00,000, SPI = 0.84, CPI = 0.88. EAC = BAC/CPI = Rs 34,28,571, forecast duration = 24/SPI = 28.6 months. Project behind schedule and over budget.
A project has a planned budget of Rs 30,00,000 and a schedule of 24 months. During its implementation you have monitored the following data. Perform EVA and comment on the performance and also draw the S-curve to forecast the final completion budget and schedule.
| Months | Work completed | Actual Expenditure (Rs) |
|---|---|---|
| 5 | 20% | 7,00,000 |
| 10 | 45% | 13,00,000 |
| 15 | 60% | 20,00,000 |
| 20 | 70% | 24,00,000 |
Given data
BAC = Rs 30,00,000; planned duration = 24 months. The planned progress is assumed uniform, so . ; AC is given.
Calculation (Rs)
| Month | PV | EV | AC | SV | CV | SPI | CPI |
|---|---|---|---|---|---|---|---|
| 5 | 6,25,000 | 6,00,000 | 7,00,000 | -25,000 | -1,00,000 | 0.96 | 0.86 |
| 10 | 12,50,000 | 13,50,000 | 13,00,000 | 1,00,000 | 50,000 | 1.08 | 1.04 |
| 15 | 18,75,000 | 18,00,000 | 20,00,000 | -75,000 | -2,00,000 | 0.96 | 0.90 |
| 20 | 25,00,000 | 21,00,000 | 24,00,000 | -4,00,000 | -3,00,000 | 0.84 | 0.88 |
Sample (month 20): ; ; .
Forecast at the latest review (month 20):
Comment on performance
-
Month 5: slightly behind schedule (SPI 0.96) and over budget (CPI 0.86).
-
Month 10: ahead of schedule (SPI 1.08) and slightly under budget (CPI 1.04); the best position.
-
Months 15 and 20: the performance has dropped; SPI falls to 0.84 and CPI to 0.88. The project is behind schedule and over budget, and the trend is getting worse.
-
Schedule: SV = -4,00,000 and SPI = 0.84, so the project is behind schedule; only 84 % of the planned work is done. If the same rate continues, the duration becomes 28.6 months against 24 months planned.
-
Cost: CV = -3,00,000 and CPI = 0.88, so the project is over budget; each rupee spent has earned Rs 0.88 of work.
-
Forecast: EAC = Rs 34,28,571 against BAC = Rs 30,00,000, i.e. a final overrun of Rs 4,28,571.
S-curve (cumulative values, Rs lakh)
P = planned value, E = earned value, A = actual cost, F = forecast (completion time, EAC), * = overlapping points.
36 |
| F
33 |
|
30 | P
|
27 |
| P
24 | A
|
21 | E
| A
18 | *
|
15 |
| *
12 | P
|
9 |
| A
6 | *
|
3 |
|
0 |*
+-------------------------------
0 5 10 15 20 25 30 months
The planned S-curve ends at Rs 30 lakh in month 24. The earned value curve lies below it (except around month 10) and the actual cost curve lies above the earned value curve. Extending the trend, the project will be completed in about 28.6 months (instead of 24) at a cost of about Rs 34,28,571 (instead of Rs 30,00,000), an overrun of Rs 4,28,571. The manager must speed up the critical work and control cost to reduce this.
Answer: at month 20, SV = Rs -4,00,000, CV = Rs -3,00,000, SPI = 0.84, CPI = 0.88; forecast cost Rs 34,28,571 and forecast duration 28.6 months.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6
- EVA graphically; BCWS 9,50,000, BCWP 8,00,000 · Project Engineering, chapter 4
- EVA; 60 days, 25% work, 50% budget spent · Project Engineering, chapter 4
- EVA numerical with bar schedule (A to F) · Construction Management, chapter 7