- Practice · 8 marks
MRP explosion with lot-for-lot ordering
Short answer
MRP for A: release 30 units in week 3 and 80 in week 5. For B: release 150 units in week 3 (lead time 2 weeks). Lot-for-lot ordering used.
Product A is assembled from 2 units of component B. The master production schedule requires 50 units of A in week 4 and 80 units of A in week 6. Data: A has on-hand stock of 20 units, lead time 1 week; B has on-hand stock of 40 units, a scheduled receipt of 30 units in week 2, and lead time 2 weeks. Use lot-for-lot ordering. Prepare the MRP records for A and B for weeks 1 to 8 and find the planned order releases.
Method
For each item: Net requirement = Gross requirement - (projected on hand + scheduled receipt). Planned order receipt = net requirement (lot-for-lot). The planned order release is the receipt moved earlier by the lead time. The releases of A give the gross requirement of B: A releases.
Item A (LT = 1 week, on hand 20)
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|
| Gross requirement | 0 | 0 | 0 | 50 | 0 | 80 | 0 | 0 |
| Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Projected on hand | 20 | 20 | 20 | 0 | 0 | 0 | 0 | 0 |
| Net requirement | 0 | 0 | 0 | 30 | 0 | 80 | 0 | 0 |
| Planned order receipt | 0 | 0 | 0 | 30 | 0 | 80 | 0 | 0 |
| Planned order release | 0 | 0 | 30 | 0 | 80 | 0 | 0 | 0 |
Week 4: 50 needed, 20 in stock, so 30 to be produced and released in week 3. Week 6: 80 needed, stock is zero, release in week 5.
Item B (LT = 2 weeks, on hand 40, receipt of 30 in week 2)
Gross requirement of B in week 3 and in week 5.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|
| Gross requirement | 0 | 0 | 60 | 0 | 160 | 0 | 0 | 0 |
| Scheduled receipts | 0 | 30 | 0 | 0 | 0 | 0 | 0 | 0 |
| Projected on hand | 40 | 70 | 10 | 10 | 0 | 0 | 0 | 0 |
| Net requirement | 0 | 0 | 0 | 0 | 150 | 0 | 0 | 0 |
| Planned order receipt | 0 | 0 | 0 | 0 | 150 | 0 | 0 | 0 |
| Planned order release | 0 | 0 | 150 | 0 | 0 | 0 | 0 | 0 |
Week 3: available 70 against need 60, leaving 10. Week 5: need 160, stock 10, so net 150; the release is moved two weeks earlier to week 3.
Answer: Release 30 units of A in week 3 and 80 in week 5; release 150 units of B in week 3.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Safety stock and reorder level with lead time · Industrial Engineering and Management, chapter 4
- MRP compared with JIT · Industrial Engineering and Management, chapter 5
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- Lead compensator for 4/[s(s+2)], Kv=20, PM≥50° · Control Systems, chapter 7 · asked 2×
- Lead compensator for 2/[s(1+0.5s)], Kv > 20, PM 50° · Control Systems, chapter 7
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
All Industrial Engineering and Management chapter 5 questions →