Chapter 5 · 6 hours
Material Requirement Planning (MRP I and MRP II)
Practice questions
Practice questions and answers
5 exam-style questions on this chapter, written for this site from the official syllabus. We haven’t found past IOE papers for this subject yet; if you have some, share them in the community.
- Practice · 6 marks
Explain the concept of Material Requirement Planning (MRP). Describe its inputs, outputs, benefits and applications.
Answer
MRP is a computer-based planning system that converts the master production schedule of end products into time-phased requirements of the sub-assemblies, components and raw materials. It answers: what to order, how much, and when. It is used for dependent demand items (items whose demand depends on the end product), unlike reorder-point systems for independent demand.
Inputs
Master Production Bill of Materials Inventory records
Schedule (MPS) (BOM) (on hand, on order)
\ | /
+--------> MRP LOGIC <-------------+
|
Planned order releases | Reschedule notices | Reports
- Master production schedule (MPS): quantity and date of each end product.
- Bill of materials (BOM): product structure showing parts per unit at each level.
- Inventory status file: on-hand stock, scheduled receipts, lead times, lot-size rules and safety stock.
Working
Gross requirements are exploded level by level; net requirements are found as gross minus (on hand + scheduled receipts); orders are planned and offset backward by the lead time.
Outputs
- Planned order releases (what to order and when).
- Order rescheduling notices (move earlier or later).
- Cancellation notices and exception reports.
- Inventory and performance reports.
Benefits
- Lower inventory and work-in-process.
- Better delivery performance and customer service.
- Fewer stock-outs and rush orders.
- Better use of labour and machines; realistic schedules.
- Quick response to change in MPS.
Applications
Assembly industries with many components and long lead times: machinery, automobiles, electronics, aircraft, furniture.
- Practice · 8 marks
Product A is assembled from 2 units of component B. The master production schedule requires 50 units of A in week 4 and 80 units of A in week 6. Data: A has on-hand stock of 20 units, lead time 1 week; B has on-hand stock of 40 units, a scheduled receipt of 30 units in week 2, and lead time 2 weeks. Use lot-for-lot ordering. Prepare the MRP records for A and B for weeks 1 to 8 and find the planned order releases.
Answer
Method
For each item: Net requirement = Gross requirement - (projected on hand + scheduled receipt). Planned order receipt = net requirement (lot-for-lot). The planned order release is the receipt moved earlier by the lead time. The releases of A give the gross requirement of B: A releases.
Item A (LT = 1 week, on hand 20)
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|
| Gross requirement | 0 | 0 | 0 | 50 | 0 | 80 | 0 | 0 |
| Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Projected on hand | 20 | 20 | 20 | 0 | 0 | 0 | 0 | 0 |
| Net requirement | 0 | 0 | 0 | 30 | 0 | 80 | 0 | 0 |
| Planned order receipt | 0 | 0 | 0 | 30 | 0 | 80 | 0 | 0 |
| Planned order release | 0 | 0 | 30 | 0 | 80 | 0 | 0 | 0 |
Week 4: 50 needed, 20 in stock, so 30 to be produced and released in week 3. Week 6: 80 needed, stock is zero, release in week 5.
Item B (LT = 2 weeks, on hand 40, receipt of 30 in week 2)
Gross requirement of B in week 3 and in week 5.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|
| Gross requirement | 0 | 0 | 60 | 0 | 160 | 0 | 0 | 0 |
| Scheduled receipts | 0 | 30 | 0 | 0 | 0 | 0 | 0 | 0 |
| Projected on hand | 40 | 70 | 10 | 10 | 0 | 0 | 0 | 0 |
| Net requirement | 0 | 0 | 0 | 0 | 150 | 0 | 0 | 0 |
| Planned order receipt | 0 | 0 | 0 | 0 | 150 | 0 | 0 | 0 |
| Planned order release | 0 | 0 | 150 | 0 | 0 | 0 | 0 | 0 |
Week 3: available 70 against need 60, leaving 10. Week 5: need 160, stock 10, so net 150; the release is moved two weeks earlier to week 3.
Answer: Release 30 units of A in week 3 and 80 in week 5; release 150 units of B in week 3.
- Practice · 5 marks
What is MRP II (Manufacturing Resource Planning)? Explain how it differs from MRP and describe its main modules.
Answer
MRP II extends MRP into a company-wide system that plans all the resources of a manufacturing firm: materials, capacity, labour, machines and money. It links production planning with marketing and finance and uses a common database. It is called "closed loop" because feedback from shop floor and suppliers is used to revise plans.
Main modules
Business plan -> Sales & operations plan
|
Master Production Schedule (MPS) -> Rough-cut capacity
|
MRP (material plan) -> Capacity requirements planning
|
Shop-floor control & purchasing
| (feedback to upper levels)
- Business and sales/production planning: long-range plan in money and units.
- Master production schedule and rough-cut capacity planning.
- MRP: time-phased material plan.
- Capacity requirements planning (CRP): checks that machines and labour can meet the MRP plan.
- Shop-floor control and purchasing: dispatching, order release and supplier control.
- Finance, costing and simulation: cost, budgets and "what-if" analysis.
MRP versus MRP II
| Basis | MRP | MRP II |
|---|---|---|
| Scope | Material planning only | All manufacturing resources |
| Capacity | Assumed infinite | Checked by CRP |
| Money | Not included | Financial planning included |
| Feedback | Limited | Closed loop |
| Integration | Production only | Marketing, finance, engineering, production |
The later extension is ERP, which covers the whole enterprise including HR and accounts.
- Practice · 5 marks
Explain the Japanese approach to material planning (Just-in-Time and kanban). Describe how a two-card kanban system works.
Answer
The Japanese approach, developed by Taiichi Ohno at Toyota, is the Toyota Production System. Its aim is to produce only what is needed, when it is needed, in the quantity needed (Just-in-Time, JIT), with the elimination of waste (muda).
Main elements
- Pull system: production starts only when the next process asks for parts, whereas MRP "pushes" parts according to a forecast schedule.
- Small lots and short set-up times (SMED).
- Levelled production (heijunka) and uniform loading.
- Elimination of seven wastes: overproduction, waiting, transport, over-processing, inventory, motion, defects.
- Total quality control and jidoka (stop on defect), multi-skilled workers, supplier partnership, U-shaped cells.
Kanban (card) system
Kanban means signboard or card. Two kinds are used:
- Production kanban: authorises the process to produce a container of parts.
- Withdrawal (move) kanban: authorises the next process to take a container from the preceding store.
Process A ---> [Store A] ---> Process B
^ production | withdrawal |
| kanban | kanban |
+---<-------------+-----<----------+
Working:
- Process B uses a container of parts; its withdrawal kanban goes to the store of A and a full container is taken.
- The production kanban that was on that container is freed and returned to Process A.
- Process A produces one container to replace it.
The number of kanbans is (D demand rate, waiting, processing time, container size, safety factor). Fewer cards means less inventory.
- Practice · 5 marks
Compare MRP and Just-in-Time (JIT) concepts. In what situations is each suitable?
Answer
MRP is a computer-based push system that plans orders from the master schedule, BOM and inventory records. JIT is a pull philosophy aimed at zero inventory and continuous elimination of waste, in which parts are produced only when the next stage uses them.
| Basis | MRP | JIT |
|---|---|---|
| Basic idea | Plan using forecasts and schedule | React to actual consumption |
| Flow of material | Push | Pull (kanban) |
| Inventory | Accepted as needed buffer (safety stock) | Seen as waste; to be minimised |
| Lot size | Computed (lot-for-lot, EOQ) | Very small, ideally one |
| Lead time | Fixed, planned | Continuously reduced |
| Set-up | Accepted as given | Reduced (SMED) |
| Information | Computer, complex | Visual cards, simple |
| Suppliers | Arm's length, many | Long-term partners, few, frequent small deliveries |
| Quality | Some defects allowed for | Zero defects required |
| Demand pattern | Variable, complex products | Stable, repetitive, levelled |
| Cost of system | Software, data accuracy | Discipline, training, supplier cooperation |
Suitability
- MRP: complex products with many levels in the BOM, variable demand, job-shop or batch production (aircraft, machinery).
- JIT: repetitive, high-volume production with stable demand, short set-ups and reliable suppliers (automobile, electronics assembly).
- Combined: many firms use MRP for planning and JIT/kanban for shop-floor execution.
Written from the official syllabus. Questions and answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗