Skip to main content

Chapter 5 · 6 hours

Material Requirement Planning (MRP I and MRP II)

Practice questions

Practice questions and answers

5 exam-style questions on this chapter, written for this site from the official syllabus. We haven’t found past IOE papers for this subject yet; if you have some, share them in the community.

  • Practice · 6 marks

Explain the concept of Material Requirement Planning (MRP). Describe its inputs, outputs, benefits and applications.

Answer

MRP is a computer-based planning system that converts the master production schedule of end products into time-phased requirements of the sub-assemblies, components and raw materials. It answers: what to order, how much, and when. It is used for dependent demand items (items whose demand depends on the end product), unlike reorder-point systems for independent demand.

Inputs

 Master Production  Bill of Materials  Inventory records
   Schedule (MPS)        (BOM)         (on hand, on order)
        \                 |                  /
         +--------> MRP LOGIC <-------------+
                       |
   Planned order releases | Reschedule notices | Reports
  1. Master production schedule (MPS): quantity and date of each end product.
  2. Bill of materials (BOM): product structure showing parts per unit at each level.
  3. Inventory status file: on-hand stock, scheduled receipts, lead times, lot-size rules and safety stock.

Working

Gross requirements are exploded level by level; net requirements are found as gross minus (on hand + scheduled receipts); orders are planned and offset backward by the lead time.

Outputs

  • Planned order releases (what to order and when).
  • Order rescheduling notices (move earlier or later).
  • Cancellation notices and exception reports.
  • Inventory and performance reports.

Benefits

  • Lower inventory and work-in-process.
  • Better delivery performance and customer service.
  • Fewer stock-outs and rush orders.
  • Better use of labour and machines; realistic schedules.
  • Quick response to change in MPS.

Applications

Assembly industries with many components and long lead times: machinery, automobiles, electronics, aircraft, furniture.

  • Practice · 8 marks

Product A is assembled from 2 units of component B. The master production schedule requires 50 units of A in week 4 and 80 units of A in week 6. Data: A has on-hand stock of 20 units, lead time 1 week; B has on-hand stock of 40 units, a scheduled receipt of 30 units in week 2, and lead time 2 weeks. Use lot-for-lot ordering. Prepare the MRP records for A and B for weeks 1 to 8 and find the planned order releases.

Answer

Method

For each item: Net requirement = Gross requirement - (projected on hand + scheduled receipt). Planned order receipt = net requirement (lot-for-lot). The planned order release is the receipt moved earlier by the lead time. The releases of A give the gross requirement of B: 2×2 \times A releases.

Item A (LT = 1 week, on hand 20)

Week12345678
Gross requirement0005008000
Scheduled receipts00000000
Projected on hand20202000000
Net requirement0003008000
Planned order receipt0003008000
Planned order release0030080000

Week 4: 50 needed, 20 in stock, so 30 to be produced and released in week 3. Week 6: 80 needed, stock is zero, release in week 5.

Item B (LT = 2 weeks, on hand 40, receipt of 30 in week 2)

Gross requirement of B =2×30=60= 2 \times 30 = 60 in week 3 and 2×80=1602 \times 80 = 160 in week 5.

Week12345678
Gross requirement00600160000
Scheduled receipts030000000
Projected on hand407010100000
Net requirement0000150000
Planned order receipt0000150000
Planned order release0015000000

Week 3: available 70 against need 60, leaving 10. Week 5: need 160, stock 10, so net 150; the release is moved two weeks earlier to week 3.

Answer: Release 30 units of A in week 3 and 80 in week 5; release 150 units of B in week 3.

  • Practice · 5 marks

What is MRP II (Manufacturing Resource Planning)? Explain how it differs from MRP and describe its main modules.

Answer

MRP II extends MRP into a company-wide system that plans all the resources of a manufacturing firm: materials, capacity, labour, machines and money. It links production planning with marketing and finance and uses a common database. It is called "closed loop" because feedback from shop floor and suppliers is used to revise plans.

Main modules

 Business plan -> Sales & operations plan
        |
   Master Production Schedule (MPS) -> Rough-cut capacity
        |
   MRP (material plan) -> Capacity requirements planning
        |
   Shop-floor control & purchasing
        |  (feedback to upper levels)
  1. Business and sales/production planning: long-range plan in money and units.
  2. Master production schedule and rough-cut capacity planning.
  3. MRP: time-phased material plan.
  4. Capacity requirements planning (CRP): checks that machines and labour can meet the MRP plan.
  5. Shop-floor control and purchasing: dispatching, order release and supplier control.
  6. Finance, costing and simulation: cost, budgets and "what-if" analysis.

MRP versus MRP II

BasisMRPMRP II
ScopeMaterial planning onlyAll manufacturing resources
CapacityAssumed infiniteChecked by CRP
MoneyNot includedFinancial planning included
FeedbackLimitedClosed loop
IntegrationProduction onlyMarketing, finance, engineering, production

The later extension is ERP, which covers the whole enterprise including HR and accounts.

  • Practice · 5 marks

Explain the Japanese approach to material planning (Just-in-Time and kanban). Describe how a two-card kanban system works.

Answer

The Japanese approach, developed by Taiichi Ohno at Toyota, is the Toyota Production System. Its aim is to produce only what is needed, when it is needed, in the quantity needed (Just-in-Time, JIT), with the elimination of waste (muda).

Main elements

  • Pull system: production starts only when the next process asks for parts, whereas MRP "pushes" parts according to a forecast schedule.
  • Small lots and short set-up times (SMED).
  • Levelled production (heijunka) and uniform loading.
  • Elimination of seven wastes: overproduction, waiting, transport, over-processing, inventory, motion, defects.
  • Total quality control and jidoka (stop on defect), multi-skilled workers, supplier partnership, U-shaped cells.

Kanban (card) system

Kanban means signboard or card. Two kinds are used:

  • Production kanban: authorises the process to produce a container of parts.
  • Withdrawal (move) kanban: authorises the next process to take a container from the preceding store.
 Process A ---> [Store A] ---> Process B
   ^   production    |  withdrawal    |
   |   kanban        |  kanban        |
   +---<-------------+-----<----------+

Working:

  1. Process B uses a container of parts; its withdrawal kanban goes to the store of A and a full container is taken.
  2. The production kanban that was on that container is freed and returned to Process A.
  3. Process A produces one container to replace it.

The number of kanbans is N=D (Tw+Tp)(1+α)CN = \dfrac{D\,(T_w + T_p)(1+\alpha)}{C} (D demand rate, TwT_w waiting, TpT_p processing time, CC container size, α\alpha safety factor). Fewer cards means less inventory.

  • Practice · 5 marks

Compare MRP and Just-in-Time (JIT) concepts. In what situations is each suitable?

Answer

MRP is a computer-based push system that plans orders from the master schedule, BOM and inventory records. JIT is a pull philosophy aimed at zero inventory and continuous elimination of waste, in which parts are produced only when the next stage uses them.

BasisMRPJIT
Basic ideaPlan using forecasts and scheduleReact to actual consumption
Flow of materialPushPull (kanban)
InventoryAccepted as needed buffer (safety stock)Seen as waste; to be minimised
Lot sizeComputed (lot-for-lot, EOQ)Very small, ideally one
Lead timeFixed, plannedContinuously reduced
Set-upAccepted as givenReduced (SMED)
InformationComputer, complexVisual cards, simple
SuppliersArm's length, manyLong-term partners, few, frequent small deliveries
QualitySome defects allowed forZero defects required
Demand patternVariable, complex productsStable, repetitive, levelled
Cost of systemSoftware, data accuracyDiscipline, training, supplier cooperation

Suitability

  • MRP: complex products with many levels in the BOM, variable demand, job-shop or batch production (aircraft, machinery).
  • JIT: repetitive, high-volume production with stable demand, short set-ups and reliable suppliers (automobile, electronics assembly).
  • Combined: many firms use MRP for planning and JIT/kanban for shop-floor execution.

Written from the official syllabus. Questions and answers are written for this site; check them against your class notes.

Chapter titles and hours from the IOE syllabus ↗